2014-09-23

The Surveyors’ Construction Handbook



The Surveyors’ Construction Handbook Contents (12/03) Page 1

CONTENTS

Foreword

Acknowledgements

List of Abbreviations

Introduction 1

A        Aim and Scope of this Handbook 1

B        Arrangement of Content 1

C        Status of Content 2

D        Currency of References 3

E        Invitation 3

F         Subscription Service 3

Part 1: The Client

Section 1.1: The Client’s Requirements and Roles 1

1.1.1  Establishing the Client’s Objectives 1

1.1.2  The Role for Independent Advice 3

1.1.3  Project Brief 3

1.1.4  The Client’s Role 4

1.1.5  The Client’s Responsibilities 6

1.1.6  Appointment of Project Manager (where appropriate) 8

1.1.7  Appointment of Consultants 8

1.1.8  Appointment of Constructors 9

Appendix A: Further Reading 1

Section 1.2: Value Engineering 1

Introduction 1

1.2.1  Why Value Engineering? 2

1.2.2  Applicability 2

1.2.3  At What Stage Should Value Engineering be Carried Out? 3

1.2.4  Who Should Carry Out Value Engineering? 4

1.2.5  How Long Should It Last? 5

1.2.6  Preparing for a Value Engineering Workshop 5

1.2.7  Functional Analysis of Design Relative to the Client’s

Requirements 5

1.2.8  Pricing the FAST Diagram 8

1.2.9  Presenting a Design Solution to a Value Engineering Workshop    8

1.2.10 The Workshop 8

1.2.11 Assessing the Value of the Workshop 9

1.2.12 Implementing the Results 10

1.2.13 Feedback from Post-Occupancy Evaluation 10

Appendix A: Health Centre Value Tree 1

Appendix B: Typical Example of a Value Engineering Process 1

Appendix C: Further Reading 1Page 2 Contents (12/03) The Surveyors’ Construction Handbook

Part 2: Construction Design and Economics

Section 2.1: Pre-contract Cost Planning and Cost Management 1

Introduction 1

2.1.1  Pre-contract Cost Planning and Cost Management 2

2.1.2  Preliminary Cost Studies and Feasibility Studies 4

2.1.3  Budget 4

2.1.4  The Cost Plan at Outline Proposals Stage 8

2.1.5  The Cost Plan at Scheme Design Stage 11

2.1.6  Cost Checking 13

2.1.7  Action after Receipt of Tenders 14

Appendix A: Sources of Cost Information 1

Appendix B: Format of Budget and Cost Plans 1

Appendix C: Element Unit Quantities Generation for Hypothetical

Buildings 1

Appendix D: Further Reading 1

Section 2.2: Life Cycle Costing 1

Introduction 1

2.2.1  The Client Context 1

2.2.2  The Life Cycle Costing Calculation 5

2.2.3  Tax Allowances, Incentives and Business Rates 10

2.2.4  Data Sources 14

2.2.5  Worked Examples 15

Appendix A: Residual Values 1

Appendix B: Obsolescence 1

Appendix C: Costs And Values 1

Appendix D: Glossary of Terms for Taxation 1

Appendix E: Examples of Items of Expenditure Likely to Attract

Taxation Allowances 1

Appendix F: Further Reading 1

Section 2.3: Elements for Buildings 1

Introduction 1

2.3.1  Elements 1

2.3.2  Elemental Cost Analysis 1

2.3.3  Other Uses 2

Appendix A: BCIS Standard Elements 1

Section 2.4: Design and Build - Guidance for Employer’s Agents 1

Introduction 1

2.4.1  Background 2

2.4.2  Contract Documentation 3

2.4.3  Additional Services 3

2.4.4  Employer’s Requirements and Contractor’s Proposals

(including contract sum analysis) 5

2.4.5  Design and Build Variants 6

2.4.6  Novation 8

Appendix A: Potential Services Associated with the Role

of Employer’s Agent 1

Appendix B: Employer’s Requirements/Contractor’s Proposal Checklist    1The Surveyors’ Construction Handbook Contents (12/03) Page 3

Section 2.5: The Chartered Surveyor as Lead Consultant  1

Introduction 1

2.5.1  Definitions: The Difference Between a Project Manager and

Lead Consultant 1

2.5.2  Benefits of Appointing a Chartered Surveyor as Lead Consultant  2

2.5.3  Issues to Consider before Undertaking the Role 3

2.5.4  Schedule of Lead Consultant Duties 3

Section 2.6 Defining Sustainable Construction 1

Introduction 1

2.6.1  Technology Swaps 2

2.6.2  How Can the Environment and Sustainability be Valued? 3

2.6.3  How Does This Effect the Construction Industry? 4

2.6.4  Green Building Materials 7

2.6.5  Whole Building Sustainability 8

2.6.6  The Government Line 9

2.6.7  What Might the Future Hold 11

Appendix A: Embodied Energy Content of Building Material 1

Appendix B: Useful Addresses 1

Part 3: Construction Planning and Procurement

Section 3.1: Developing an Appropriate Building Procurement Strategy 1

Introduction 1

3.1.1  The Client’s Role 2

3.1.2  Procurement Strategy 12

3.1.3  Selection of Most Appropriate Procurement Strategy 25

3.1.4  Implementation 29

Appendix A: Procurement Options 1

Section 3.2: Building Services Procurement 1

Introduction 1

3.2.1  Appointing the Building Services Designer 3

3.2.2  Design Coordination 11

3.2.3  Appointing a Building Services Contractor 19

3.2.4  Tender Documents 34

Appendix A: Typical Example 1

Part 4: Construction Administration and Management

Section 4.1: The Problems of Practical Completion 1

Introduction  1

4.1.1  What Happens in Practice 1

4.1.2  Standard Form Approaches 3

4.1.3  Effects of Practical Completion 13

4.1.4  Methods for Dealing with Practical Completion 14

4.1.5  Definitions 16

4.1.6  Subsidiary Issues 20

Appendix A: General Objectives to be Achieved at Practical

Completion for Small to Medium-sized Building Projects 1

Appendix B: Table of Cases 1

Appendix C: Further Reading 1Page 4 Contents (12/03) The Surveyors’ Construction Handbook

Section 4.2: Ascertaining the Amount of Loss and

Expense Incurred in Building Projects 1

Introduction 1

4.2.1  General Principles 1

4.2.2  Definitions 4

4.2.3  Entitlement 4

4.2.4  Ascertainment 7

4.2.5  Admissible Items 9

4.2.6  Inadmissible Items 13

Appendix A: Ascertaining the Cost of Running a Site 1

Appendix B: Disruption 1

Appendix C: Ascertaining the Cost of Head Office Overheads 1

Appendix D: Checklist of Items for which Loss and/or Expense are

Allowed 1

Appendix E: Checklist of Steps Required when Considering

Submissions by Contractor 1

Appendix F: Further Reading 1

Section 4.3: The Management of Risk 1

Introduction 1

4.3.1  Definitions 2

4.3.2  The Rationale for Risk Management in the Construction Process    2

4.3.3  The Risk Management Process 5

4.3.4  Summary 14

Appendix A: Further Reading 1

Section 4.4: Valuations for Interim Certificates 1

Introduction 1

4.4.1  Valuations 1

4.4.2  Assumptions 2

4.4.3  Valuation Under a JCT Contract: Background 3

4.4.4  Recommended Action at the Start of a Contract 4

4.4.5  Communications 5

4.4.6  Approach 6

4.4.7  Content of a Valuation 8

4.4.8  Administration 15

4.4.9  Special Situations 16

4.4.10 Other Contract Terms (relative to valuations) 17

4.4.11 Valuations Under Other Forms of Contract 18

Appendix A: Further Reading 1

Appendix B: JCT Definition of ‘Reasonable Proof’ 1

Appendix C: Example of Priced Activity Schedule 1

Section 4.5: Extension of Time 1

Introduction 1

4.5.1  Extension of Time Clauses 2

4.5.2  Assumptions 2

4.5.3  Extension of Time Under a JCT Contract 3

4.5.4  Notice by the Contractor of Delay to Progress 4

4.5.5  The Award of an Extension of Time during the Contract

Period and Before the Completion Date 5

4.5.6  The Award of an Extension of Time after the Completion Date      6

4.5.7  Relevant Events 7

4.5.8  Concurrent Delays 12

4.5.9  Consequential Entitlement 13The Surveyors’ Construction Handbook Contents (12/03) Page 5

4.5.10 Administration 13

4.5.11 Extension of Time under an ICE Contract 14

4.5.12 Extension of Time under a GC Works Contract 14

Appendix A: Further Reading 1

Part 5: Additional Guidance and Information

Section 5.1: Surveying Safely 1

Section 5.2: Construction (Design and Management) Information 1

5.2.1  Schedule of Sources of Useful CDM Information 2

Section 5.3: Built environment group roles and information 1

Section 5.4: Building Cost Information Service 1

5.4.3  BCIS Online 1

5.4.4  Other BCIS Publications and Services 2

5.4.5  Further details 4

Section 5.5: Building Occupancy Cost Information (BMI) 1

5.5.2  BMI Quarterly Cost Briefing 1

5.5.3  Building Maintenance Price Book 1

5.5.4  Special Reports for Benchmarking 2

5.5.5  News, Digests and Reports 2

Section 5.6: Electronic document storage – legal admissibility 1

Introduction 1

5.6.1  Code of Practice – DISC PD 0008: 1999  2

5.6.2  Weight of evidence and document destruction 3

5.6.3  Authenticity 3

5.6.4  Photocopies, microfilm and image processing 4

5.6.5  Document storage 4

5.6.6  Storage and access procedures 5

5.6.7  Format of the Code of Practice 6

5.6.8  Conclusion 20

Appendix A: Specimen form for recording scanning information 1

Appendix B: Specimen form for recording retrieval 1

Appendix C: References 1

Index 1The Surveyors’ Construction Handbook Abbreviations (10/02) Page 1

LIST OF ABBREVIATIONS

ABE Association of Building Engineers

ABI Association of British Insurers

ACA Association of Consultant Architects

ACE Association of Consulting Engineers

AQL Acceptable quality level

BCIS Building Cost Information Service

BEC Building Employers’ Confederation

BMI Building Maintenance Information

BRE Building Research Establishment

BRECSU Building Research Energy Conservation Support Unit

BREEAM Building Research Establishment Environmental

Assessment Method

BSI Building Standards’ Institution

BSRIA Building Services Research and Information Association

BWIC Builder’s Work in Connection

CA Contract Administrator

CAWS Common Arrangement of Works Section for Building

Works

CDM Construction (Design and Management)

CD-R Compact disc recordable

CECA Civil Engineering Contractors’ Association

CIB Construction Industry Board

CIBSE Chartered Institution of Building Services Engineers

CIC Construction Industry Council

CIRIA Construction Industry Research and Information

Association

CITES Control in Trade of Endangered Species

CCT Compulsory Competitive Tendering

CSM Chartered Surveyors Monthly

DBFO Design Build Fund and Operate

DoE Department of the Environment (now known as the

DETR)

DETR Department of the Environment, Transport and the

Regions (formerly the DoE)

DMS Document Management System

DOM Domestic Sub-Contract

EC European Commission

EU European Union

FAST Functional Analysis Systems Technique

FCEC Federation of Civil Engineering Contractors

GNP Gross National Product

HBF House Builders’ Federation

HMSO Her Majesty’s Stationery Office (now known as

The Stationery Office)

HSE Health and Safety Executive

IChemE Institution of Chemical Engineers

ICE Institution of Civil Engineers

IDMA Information and Document Management AssociationIFC Intermediage Form of Contract

JCT Joint Contracts Tribunal

LCC Life Cycle Costing

LQ Limiting quality

M & E Mechanical and Electrical

MERA Multiple Estimate Risk Anaylsis

MW Minor Works

NEC New Engineering Contract

NEDO National Economics Development Office

NJCC National Joint Consultative Committee for Building

NSC Nominated Sub-Contract

OMR Optical Mark Reading

PFI Private Finance Initiative

PSA Property Services Agency

RIBA Royal Institute of British Architects

RICS Royal Institution of Chartered Surveyors

VAT Value Added Tax

WCD With Contractor’s Design

WORM Write-Once-Read-Many

WRC Water Research Centre

Show more