ODOT District Two Weekly Construction Update – July 26
For Immediate Release
Thursday, July 23, 2015
Updates are highlighted in bold and underlined.
Lucas/Wood Counties
1. Interstate 75: Widening *UPDATE*
Wood & Hancock Counties (170-14, 199-14, 237-14 & 3000-14):
Interstate Restrictions:
Through November, overnight, from 7pm until 6am, single lane restrictions are possible on I-75 between the I-75/I-475 interchange in Perrysburg and CR 99 in Hancock County.
Through December, one lane of northbound I-75 traffic, from Roachton Road to US 20, is maintained in the northbound lane and one lane of northbound I-75 traffic, from Roachton Road to US 20, is maintained on southbound I-75. Through 2016, southbound I-75 is reduced to two lanes from US 20 to I-475 in Perrysburg. Through 2016, 11-foot lane width restrictions are in place on I-75 between US 20 in Perrysburg and CR 99 in Hancock County.
Ramp Restrictions:
Effective Monday, August 10, through September, the ramp from northbound I-75 to SR 582 will be closed for pavement widening. Detour: SR 795; I-75 southbound. Additionally at this time, the ramp from SR 582 to northbound I-75 will be closed for pavement widening. Detour: I-75 southbound; SR 64/SR 105.
Through July 2016, 11-foot lane width restrictions are in place on the ramps from northbound I-75 to Cygnet Road (Exit 171) and from Cygnet Road to northbound I-75.
Through December, the ramp from southbound I-75 to westbound I-475 is reduced to one lane. The ramp from eastbound I-475 to northbound I-75 is permanently reduced to one lane.
Local Routes:
Through November, Jerry City Road at I-75 is closed for bridge work. Detour: SR 25; SR 281; Solether Road.
Through December, Township Road 101 in Hancock County, between CR 220 and TR 142, is closed for bridge work over I-75. Project complete: October 2017. All work is weather permitting.
2. Interstate 75: Widening *UPDATE*
Lucas County (485-14, 536-14): Effective Monday, July 27 from 10pm, until Tuesday, July 28 at 6am, the ramp from eastbound I-475 to southbound I-75 may be closed for pavement marking. Detour: northbound I-75; Berdan Avenue (Exit 205B); Detroit Avenue; Phillips Avenue; Haverhill Drive. Following this closure, through Tuesday, July 28 at 6am, the ramp from eastbound I-475 to northbound I-75 may be closed for pavement marking. Detour: southbound I-75; Washington Street (Exit 202A).
Through July 2018, overnight, 7pm through 6am, single lane restrictions are possible on I-75, from I-475 in Toledo to I-280 for bridge work. Through fall 2016, one lane of I-75 traffic is maintained in the current northbound lane and one lane of traffic is relocated to southbound I-75 and separated by barrier wall.
The following ramps are closed:
· Through November 2016, the ramp from northbound I-75 to Phillips Avenue (Exit 206). Detour: south Expressway Drive (Exit 207); Stickney Avenue; North Expressway Drive.
· Through June 2016, the ramp from southbound I-75 to Phillips Avenue (Exit 206). Detour: North Expressway Drive (Exit 207); Stickney Avenue; South Expressway Drive.
· Through June 2016, the ramp from Phillips Avenue to northbound I-75. Detour: Manhattan Boulevard; Lagrange Street; South Expressway Drive.
· Through July 2016, the ramp from northbound I-75 to Jeep Parkway (Exit 205A). Detour: Berdan Avenue (Exit 205B); Detroit Avenue.
· Through July 2018, the ramp from Jeep Parkway to southbound I-75. Detour: Berdan Avenue.
· Through July 2018, the ramp from Willys Parkway to northbound I-75. Detour: Berdan Avenue; Detroit Avenue; Phillips Avenue.
· Through July 2018, the ramp from southbound I-75 to Willys Parkway (Exit 205A). Detour: Detroit Avenue (Exit 203B).
Local Streets:
Through November 2016, the ramp from northbound I-75 to Berdan Avenue is restricted to right turn only movements. Suggested alternate route: Berdan Avenue; Detroit Avenue; Phillips Avenue; Haverhill Drive.
Through May 2017, the Polish Village Overpass is closed for bridge work. Detour: North Expressway Drive; Stickney Avenue; South Expressway Drive.
Through July, expect lane restrictions on Phillips Avenue at I-75, on Lagrange Street at I-75, and on Stickney Avenue at I-75 for bridge work.
Through October, South Expressway Drive is restricted to a single lane between Stickney Avenue and Lagrange Street.
Through June 2016, Jeep Parkway from Central Avenue to Berdan Avenue is closed. Central Avenue; Detroit Avenue; Berdan Avenue.
Through July 2018, Willys Parkway from Pioneer Lane to Jeep Parkway is closed.
Project complete: July 2018. All work is weather permitting.
3. Interstate 75: Pavement Rehabilitation
Lucas County (268-14): Through July, I-75, from the I-75/475 split in Toledo to the Anthony Wayne Trail, is reduced to two lanes. Overnight, 10pm through 6am, single lane restrictions are possible in this work zone.
Ramp closures:
• Through August, the ramp from northbound I-75 to Bancroft Street is closed. Detour: Berdan Ave (Exit 205B); Detroit Avenue.
• Through August, the ramp from Collingwood Boulevard to northbound I-75 is closed. Detour: Dorr Street; Washington Street; 14th Street.
Through August 2016, the following ramps are restricted or closed:
· The interchange ramp from eastbound I-475 to southbound I-75 is reduced to one lane.
· The interchange ramp from northbound I-75 to westbound I-475 is reduced to one lane.
· The ramp from Detroit Avenue to southbound I-75 is closed. Detour: Monroe Street; Michigan Avenue; SR 25.
· The ramp from Detroit Avenue to northbound I-75 is closed. Detour: Monroe Street; 14th Street.
Through May 2016, Oakwood Avenue, between Wells Street and Grove Place, is closed for bridge work. Seek alternate route. Project complete: August 2016. All work is weather permitting.
4. Interstate 75: Pavement Repair *NEW WORK*
Lucas County: Effective Sunday, July 26, through Thursday, July 30, nightly from 9pm to 5am, lane restrictions are possible on I-75, between South Avenue and Miami Street, for pavement repair. Additionally at this time, intermittent short-term ramp closures are possible in this zone. All work is weather permitting.
5. Interstate 475: ProMedica Parkway Ramp
Lucas County: Through 2016, the ramp from ProMedica Parkway to eastbound I-475 is closed for traffic control. Detour: westbound I-475; Douglas Road. All work is weather permitting.
6. Interstate 475/U.S. Route 23: Interchange Upgrade
Lucas County (184-14 & 210-15): Overnight lane restrictions are possible at the interchange of I-475/US 23 from Central Avenue to N. Holland Sylvania Road. Through July, lane restrictions are possible on Blossman Road, between Moffet Road and Plainview Drive for bridge work. Traffic will be maintained by flaggers. Project complete: December. All work is weather permitting.
7. Interstate 475: Bridge Widening
Lucas County (251-13 & 235-14): Through October, the ramp from westbound Airport Highway to northbound I-475 is closed. Detour: southbound I-475; Salisbury Road/Dussel Drive (Exit 6).
Through May 2016, overnight from 8pm until 6am, lane restrictions are possible on I-475, between Angola Road and Salisbury Road/Dussel Drive. 11-foot lane width restrictions are in place on I-475, between Angola Road and Salisbury Road/Dussel Drive. Through June 2016, lane and shoulder restrictions are possible on the Ohio Turnpike (I-80/I-90) at the I-475 bridge. Through July, Manley Road at the Ohio Turnpike Bridge is closed. Project complete: August 2016. All work is weather permitting.
8. Interstate 475: Noise Wall Installation *UPDATE*
Lucas County (314-14): Through October, overnight, 9pm through 6am, lane restrictions are possible on I-475 from Corey Road to Woodley Road for noise wall installation. Additional daytime lane and shoulder restrictions will be announced. Project complete: October. All work is weather permitting.
9. Interstate 475: Bridge Deck Replacement
Lucas County (480-14): Through August, overnight from 9pm until 6am, single lane restrictions are possible on I-475 at Bancroft Street for bridge replacement. Through August, expect shoulder restrictions on I-475 at Bancroft Street for bridge repair. Through August, expect lane restrictions on Bancroft Street at I-475 for finish work. Project complete: August. All work is weather permitting.
10. Interstate 475: Pavement Work *UPDATE*
Wood County: Through August, overnight from 7pm to 6am, single lane restrictions are possible on I-475 in both directions between SR 25 and US 24 for pavement work. Weekend work will be announced. All ramps will remain open. All work is weather permitting.
11. Interstate Maintenance Work
Lucas and Wood Counties: Through December, intermittent overnight lane restrictions are possible on I-75, I-280 and I-475 in Lucas and Wood counties for maintenance work. Project complete: December. All work is weather permitting.
12. U.S. Route 20: Holland Sylvania Road & Reynolds Road Intersection Improvements
Lucas County (145-14 & 252-14): Through August, lane restrictions are possible on Central Avenue from Fairbanks Avenue to Reynolds Road for median installation. Additionally, through August, expect lane restrictions on Holland-Sylvania Road, between Huntingfield Boulevard to Bonsels Parkway for median installation. Through August, intermittent lane restrictions are possible at the intersection of Central Avenue and Reynolds Road for safety improvements. Project complete: August. All work is weather permitting.
13. U.S. Route 20: Central Avenue Interchange Project *NEW PROJECT*
Lucas County (210-15): Effective Monday, August 3 through September 2017, overnight from 9pm until 6am, lane restrictions are possible on I-475/US 23 between Dorr Street and the I-475/US 23 interchange. 11-foot lane width restrictions will be in place within the work zone. Additional restrictions will be announced. Project complete: September 2017. All work is weather permitting.
14. U.S. Route 20A: Eber Road Roundabout Project *NEW PROJECT*
Lucas County (184-15): Effective Monday, August 3, through September, US 20A, between Weckerly Road and Eber Road, will be closed for culvert repair. A 45-day closure of US 20A at Eber Road will follow in September. Project complete: November. All work is weather permitting.
15. State Route 2: Anthony Wayne Bridge Project
Lucas County (58-13): Miami Street, between Nevada Street and Greenwood Avenue, is open. Additional short-term, intermittent closures on Miami Street, between Nevada Street and Greenwood Avenue, will be announced. Through October, short-term intermittent, closures are possible on Yondota Street, Utah Street, Morris Street and Ottawa Street for bridge work. Through November, the Anthony Wayne Bridge is closed to vehicular and pedestrian traffic. Detour: Oak Street; Fassett Street; Miami Street; I-75; Anthony Wayne Trail (Exit 201B); Monroe Street; Summit Street. Project complete: December. All work is weather permitting.
16. State Route 25: Safety Project
Lucas County (299-15): Through November 2016, the Anthony Wayne Trail, between Hippo Way and City Park Boulevard, is reduced to two lanes for intersection safety improvements and pavement replacement. Effective Friday, July 31, through Monday, August 3, South Avenue at the Anthony Wayne Trail will be closed to through traffic, with only right turn movements permitted. Additional closures will be announced. Project complete: November 2016. All work is weather permitting.
17. State Route 64: Roundabout and Realignment *UPDATE*
Lucas County (143-15): Through August, SR 64, at Finzel Road is closed for roundabout construction. Detour: SR 295; US 24. Additionally, through Thursday, July 30, Finzel Road south of SR 64 is closed. Finzel Road north of SR 64 is open through Thursday, July 30. Effective Thursday, July 30, Finzel Road north of SR 64 will be closed. Local access to businesses will be maintained. Effective Thursday, July 30,Finzel Road south of SR 64 will be open to traffic through the new roundabout. Project complete: October. All work is weather permitting.
18. McCord Road: Underpass Construction
Lucas County (236-14): Through August, North Mall Drive/Hall Street at McCord Road is closed. Local business access is maintained. Through September 2016, McCord Road between North Mall Drive/Hall Road and Spectrum Drive is closed to vehicular and pedestrian traffic. Detour: Airport Highway; Holland Sylvania; Angola Road. Project complete: November 2016. All work is weather permitting.
19. Various Routes: Bridge Painting *UPDATE*
Lucas County (8027-14): Through July, overnight 6pm through 6am, lane restrictions are possible on US 24 at Fallen Timbers Lane for bridge painting. Through July, the right turn lane from Summit Street to Oliver Street in Toledo will be restricted for bridge painting. Project complete: December. All work is weather permitting.
20. U.S. Route 6: Pavement Reconstruction and Bridge Work
Wood County (170-14): Through October, the ramp from southbound I-75 to eastbound US 6 is closed. Detour: westbound US 6; SR 25; Cygnet Road; I-75. Through October, US 6, between SR 25 and Dunbridge road, is reduced to one lane in each direction. Lane widths are restricted to 11ft in this work zone. Work complete: October. All work is weather permitting.
21. U.S. Route 6: Resurfacing and Bridge Work
Wood County (434-14): Through August, the ramp from SR 25 to eastbound US 6 is closed for bridge repair. Detour: Cygnet Road; I-75. Through July, intermittent lane restrictions are possible on US 6, between County Home Road and SR 199 for resurfacing. Traffic is maintained by flaggers. Through August, US 6, between Rudolph Road and Klopfenstein Road is reduced to one lane in each direction for bridge repair. Project complete: September. All work is weather permitting.
22. U.S. Route 20: Culvert Replacement
Wood County (8002-15): Through July, US 20, between SR 163 and SR 420 is closed for culvert replacement. Detour: SR 420; SR 163. Project complete: August. All work is weather permitting.
23. State Route 64: Slide Repair
Wood County (155-15): Through August, a temporary traffic signal will be used to maintain one lane of traffic through the work area. Through September, intermittent lane restrictions are possible on SR 64, between Reitz Road and SR 64/65 Waterville Bridge for slide repair. Project complete: November. All work is weather permitting.
24. State Route 65: Slope Repair
Wood County (119-15): Through September, SR 65, between Weston Road through Benschoter Road, is closed for slope repair. Detour: SR 235; US 6; SR 65. Project complete: September. All work is weather permitting.
25. State Route 105: Resurfacing *NEW PROJECT*
Wood County (99-15): Effective Monday, August 3, through September, intermittent lane restrictions are possible on SR 105, between Pemberville Road and US 23, for resurfacing. Traffic will be maintained by flaggers. Project complete: September. All work is weather permitting.
26. State Route 420: Safety Improvements *UPDATE*
Wood County (423-14): The ramp from the Ohio Turnpike to northbound I-280 is now open. Effective Friday, July 24, through July, southbound I-280, between SR 795 and Libbey Road, will be reduced to one lane for barrier wall and guardrail work. Through July, intermittent lane restrictions and delays are possible on SR 420, between SR 163 and I-80/I-90, for pavement work. The left turn lane from southbound SR 420 to Libbey Road is permanently closed. Motorists should use the newly built turnaround. 11-foot lane width restrictions are in place on northbound SR 420. Project complete: August. All work is weather permitting.
27. State Route 582: Bridge Rehabilitation
Wood County (154-15): Through August, SR 582, between Stony Ridge Road and Layman Road is closed for bridge rehabilitation. Detour: SR 199; SR 105; US 23. Project complete: September. All work is weather permitting.
28. Gypsy Lane Road: Bridge Repair
Wood County (1093-14): Through July, Gypsy Lane Road over I-75 is reduced to one lane for bridge repair. Traffic is maintained by automated signal. Project complete: July. All work is weather permitting.
29. Park Avenue: Bridge Replacement
Wood County (3028-15): Through August, Park Avenue in Fostoria, between Lincoln Avenue and Kennedy Lane is closed for bridge replacement. Detour: North County Line Road (US 23/SR 199); Summit Street; Vine Street. Project complete: August. All work is weather permitting.
Ottawa/Sandusky/Seneca Counties
30. State Route 2: Lightner Road Bridge Widening *NEW PROJECT*
Ottawa County (232-15): Effective Tuesday, July 28, through August 2016, intermittent lane restrictions are possible on SR 2, between SR 53/SE Catawba Road and SR 269, for bridge work. Additionally, Lightner Road, between Kirk Road and East State Road, may be reduced to one lane for temporary pavement construction. Traffic will be maintained by flaggers. Additional restrictions will be announced. Project complete: September 2016. All work is weather permitting.
31. State Route 53: Bridge Repair
Ottawa County: Through July, lane restrictions are possible on the ramp from SR 53/West Fremont Road to eastbound SR 2 for pavement work. Ramp access is maintained. All work is weather permitting.
32. U.S. Route 6: Roundabout Construction
Sandusky County (8018-15): Through August, shoulder restrictions are possible on US 6/SR 53, between Napoleon Road to W. State Street, for roundabout construction. The closure of Muskellunge Creek Road will be announced. Project complete: November. All work is weather permitting.
33. State Route 12: Bridge Rehabilitation *PROJECT COMPLETE*
Sandusky and Seneca Counties (433-14): Lane restrictions on SR 12, between SR 53 and Franklin Street in Bettsville are now complete.
34. State Route 412: Culvert Replacement *ROAD OPEN*
Sandusky County (324-14): SR 412, between N. County Road 198 and Karbler Road, is now open. Through July, intermittent lane restrictions are possible on SR 412, between TR 274 and SR 101 for chip sealing. Traffic is maintained by flaggers. Project complete: July. All work is weather permitted.
35. State Route 590: Bridge Replacement
Sandusky County (534-14): Through July, SR 590, between Burgoon Road and Kenan-Hite Road, is closed for bridge replacement. Detour: US 6; SR 635; SR 12; SR 53. Project complete: August. All work is weather permitting.
36. State Route 18: Resurfacing
Seneca County (97-15): Through August, intermittent lane restrictions are possible on SR 18, between TR 159 and SR 67/SR 18 for resurfacing. Project complete: September. All work is weather permitting.
37. State Route 53: Railroad Repair
Seneca County: Through July, SR 53, between CR 40 and CR 51, will be closed for railroad repair. Detour: SR 18; SR 635; SR 12. All work is weather permitting.
38. State Route 100: Culvert Replacement
Seneca County (236-15): Through August, SR 100, between SR 67 and TR 44, is closed for culvert replacement. Detour: SR 67; SR 100. Project complete: August. All work is weather permitting.
39. U.S. Route 224: Resurfacing
Seneca County (50-15): Through July, intermittent lane restrictions are possible on US 224, between Miller Drive and Township Road 197, for finish work. Traffic is maintained by flaggers. Project complete: July. All work is weather permitting.
40. State Route 587: Culvert Replacement
Seneca County (281-15 & 55-15): Through August, SR 587, between TR 90/Sauber Road and TR 56/Arendt Road, is closed for culvert replacement. Through August, SR 587 between CR 18 and TR 112, is closed for culvert replacement. Detour: SR 53; US 224; SR 18. Project complete: October. All work is weather permitting.
Williams/Fulton/Henry Counties
41. U.S. Route 6: Culvert Replacement
Williams County (534-14): Through July, US 6, between CR 5.5 and CR 7, is closed for culvert replacement. Detour: SR 49, SR 249, SR 2. All work is weather permitting.
42. State Route 15: Culvert Replacement *PROJECT COMPLETE*
Williams County: SR 15, between CR S and Kexon Drive, is now open. The culvert replacement is complete.
43. State Route 107: Bridge Rehabilitation
Williams County (153-15): Through August, SR 107, between CR 8 and CR 9, is closed for bridge rehabilitation. Detour: SR 49; US 20; SR 576. Project complete: September. All work is weather permitting.
44. U.S. Route 6: Pavement Repair *NEW WORK*
Henry County: On Saturday, August 1, and on Saturday, August 8, from 6:30am to 6:30pm, US 6, between CR 7 and SR 65, will be closed for pavement repair. Detour: SR 65; SR 110. All work is weather permitting.
45. State Route 65: Culvert Replacement
Henry County: Through August, SR 65, between CR K and CR N, is closed for culvert replacement. Detour: US 6; SR 109; SR 281. All work is weather permitting.
46. State Route 65: Culvert Replacement *CLOSURE BEGINS MONDAY*
Henry County (67-15): Effective Monday, July 27, through August, SR 65, between CR J and CR K, is closed for culvert replacement. Detour: US 6; SR 109; SR 281. All work is weather permitting.
47. State Route 65: Culvert Replacement *NEW WORK*
Henry County: Effective Monday, August 3, through Friday, August 7, SR 65, between CR P and CR Q, is closed for culvert replacement. Detour: US 6; SR 109; SR 110. All work is weather permitting.
48. State Route 109: Damascus Bridge: Bridge Replacement
Henry County (1-15): Through October 2017, motorists should watch for additional truck traffic near SR 109 at the Damascus bridge for bridge work. Work impacting traffic will be announced. Project complete: October 2017. All work is weather permitting.
49. State Route 281: Culvert Replacement
Henry County (179-15): Through August, SR 281, between CR 17 and CR 19 is closed for culvert replacement. Detour: SR 108; SR 18. Additionally, CR 18 is closed one mile north and one mile south of SR 281. Project complete: August. All work is weather permitting.
50. Various Routes: Bridge Inspection *NEW*
Henry County: On Monday, July 27, from 8:30am until 10:30am, SR 109, between CR 424 and SR 110, may be reduced to one lane for bridge inspection. Traffic will be maintained by flaggers. On Monday, July 27, from 12:30pm until 2:30pm, US 6, between CR 424 and SR 110, may be reduced to one lane for bridge inspection. All work is weather permitting.
District Wide
51. Various Routes: Guardrail & Electrical Maintenance
District Wide (1071-14 & 1076-14): Through December, intermittent lane restrictions are possible district wide for guardrail and electrical maintenance. Project complete: December. All work is weather permitting.