In March 2008, the Bell Boeing Joint Project Office in Amarillo, TX received a $10.4 billion modification that converted the previous advance acquisition contract (N00019-07-C-0001) to a fixed-price-incentive-fee, multi-year contract. The new contract now sits at $10.92 billion, and will be used to buy 143 MV-22 (for USMC) and 31 CV-22 (Air Force Special Operations) Osprey aircraft, plus associated manufacturing tooling to move the aircraft into full production. A follow-on MYP-II contract covered another 99 Ospreys (92 MV-22, 7 CV-22) for $6.524 billion.

The V-22 tilt-rotor program has been beset by controversy throughout its 20-year development period. Despite these issues, and the emergence of competitive but more conventional compound helicopter technologies like Piasecki’s X-49 Speedhawk and Sikorsky’s X2, the V-22 program continues to move forward. This DID Spotlight article looks at the V-22′s multi-year purchase contract from 2008-12 and 2013-2017, plus associated contracts for key V-22 systems, program developments, and research sources.

The V-22 Program



The current objective is 458 Osprey tilt-rotors: 360 MV-22 Marine Corps aircraft, 50 CV-22 aircraft for USSOCOM (funded by USSOCOM and the Air Force), and 48 MV-22 Navy aircraft. Initial Operational Capability didn’t begin until 2007, about 24 years after the initial design contract.

MV-22 vs. CV-22



MV-22
(click to view full)

The V-22 comes in 2 variants.

The US Marines operate the MV-22, whose most current configuration is Block C. The current MV-22 Block C’s enhancements (software version C1.01) include forward-mounted AN/ALE-47 defensive systems, move the MV-22?s Ice Detectors, improve dust protection for the engines, and add a redesigned Environmental Control System (ECS) to keep devices and troops from overheating. A “Cabin Situational Awareness Device” displays essential mission information, including access to GPS updates for handheld devices, plus way points, flight plans, location, etc. for troop commanders inside. For the pilots, a Color Weather Radar System provides weather detection, ground mapping to 20 nm, and sea search. Electronic Standby Flight Instruments (ESFI) replace the analog standby instrument cluster, and a Day Heads-up Display (HUD) feeds its data to a helmet-mounted monocle. A Traffic Advisory System (TAS) was intended to warn MV-22 pilots of other aircraft that might hit them, but it doesn’t work properly.

US Air Force Special Operations Command operates the CV-22, which adds more sophisticated surveillance capabilities, beefed-up defensive systems, extra fuel tanks, and useful capabilities like terrain-following flight. Its most current configuration is the CV-22 Block 20.

There was supposed to be an MV-22 for the US Navy, but its expected roles in search and rescue etc. were taken up by the MH-60S Seahawk helicopter. Technically, a buy of 48 HV-22s has always been part of the program. In reality, the US Navy has made no moves to adopt the platform. That may change as of FY 2016, if the V-22 can win a likely competition for the next Carrier Onboard Delivery (COD) platform to replace the fixed-wing C-2A Greyhound. The Osprey won’t be able to compete on price or operating costs against remanufactured C-2s that use technologies from the derivative E-2D Hawkeye production line. Boeing and Textron will have to hope that the Navy values the V-22′s landing versatility and other uses enough to pay a lot more per plane.

V-22 Budgets & Buys

Excel
download

Initial Operational Capability in 2007 was followed by a big Multi-Year Procurement contract in FY 2008, which ended up buying 175 V-22s (143 MV-22s, 32 CV-22s) for about $14.416 billion.

The US fiscal situation is almost certain to lead to serious defense budget cuts, so the V-22′s manufacturers responded by trying to lock the government into a 2nd multi-year contract, creating cancellation penalties that would make the Osprey too expensive to kill, and impossible to seriously reduce. Enough contracts like that will end up gutting other USMC investments when cuts do hit, and could lead to even more serious problems if V-22 fleet operations and maintenance costs don’t start dropping very quickly (vid. Nov. 29/11 entry).

That isn’t the manufacturers’ concern, however, and it wasn’t the Navy’s, either. The FY 2013 budget included a submission to buy 98 more V-22 aircraft (91 MV-22s, 7 CV-22s) under a 2nd fixed-price multi-year contract, between FY 2013 – FY 2017. The MV-22s will be bought by the Navy for the Marines, while the CV-22s aircraft are a joint buy involving the USAF and SOCOM. To get approval for a multi-year buy, they had to demonstrate at least 10% cost savings over the same buys placed year by year. Their proposal hoped to save $852.4 million, or 11.6% of the total, at the price of less flexibility in the number bought through FY 2017:

Proposed V-22 follow-on MYP 2013-17

Year

Qty

Net Proc.
($M)

Savings

FY13

21

1,693

38

FY14

21

1,741

185

FY15

19

1,541

226

FY16

19

1,468

229

FY17

18

1,430

225

Total

98

7,922

852

Source: US Navy, FY13 PB [large PDF].
Totals may not add up due to rounding up and FY12 Advance Procurement (incl. $50M for cost reduction initiatives).

The actual contract and budget plans ended up being a bit different, per the June 12/13 entry and the data and graphs above. Instead of 98 Ospreys (91 MV-22, 7 CV-22) for $6.5 billion, the actual MYP-II contract adds up to 99 tilt-rotors for $6.524 billion.

Contracts & Key Events

AFSOC CV-22
(click to view full)

Unless otherwise noted, US Naval Air Systems Command in Patuxent River, MD issues the contracts, and the Bell-Boeing Joint Program tiltrotor team in Amarillo, TX is the contractor.

Note that “low power repairs” are triggered when an AE1107 engine’s Power Assurance Check (PAC) reads below 96%. It’s normal for aircraft engine performance to drop somewhat over time, and the fix involves engine removal for maintenance and tune-up.

FY 2014

Israel confirmed.

ANVIS/HUD-24
click for video

Jan 15/14: Support. A $26.7 million cost-plus-fixed-fee, cost reimbursable delivery order for on-site V-22 flight test management, flight test engineering, design engineering, and related efforts to support the US Navy’s Rotary Wing Aircraft Test Squadron.

ALl funds are committed immediately, using USN FY 2013 procurement and FY 2014 R&D dollars. Work will be performed at Patuxent River Naval Air Station, Patuxent River, MD (53%); Philadelphia, PA (32%); and Fort Worth, TX (15%), and is expected to be complete in December 2014 (N00019-12-G-0006, DO 0067).

Jan 15/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives a $13.6 million firm-fixed-price contract modification to provide 17,226 MV-22 engine flight hours. The maintenance and work required to keep the fleet in shape for that is their problem.

All funds are committed immediately, using FT 2014 Navy O&M funds. Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and the Pentagon days that it “is expected to be complete in November 2013″. Looks like they’re paying for a past period? (N00019-10-C-0020).

Jan 14/14: Israel. The US DSCA announces Israel’s official request for up to 6 “V-22B Block C Aircraft” for search and rescue and special operations roles. MV-22B Block Cs are the USMC’s most modern variant, though the notice carefully avoids specifying either USMC MV-22s or SOCOM CV-22s. The request could be worth up to $1.3 billion, and includes:

16 Rolls Royce AE1107C Engines (12 + 4 spares)

6 AN/APR-39 Radar Warning Receiver Systems

6 AN/ALE-47 Countermeasure Dispenser Systems

6 AN/AAR-47 Missile Warning Systems

6 AN/APX-123 Identification Friend or Foe Systems

6 AN/ARN-153 Tactical Airborne Navigation Systems

6 AN/ARN-147 Very High Frequency (VHF) Omni-directional Range (VOR) Instrument Landing System (ILS) Beacon Navigation Systems

6 AN/APN-194 Radar Altimeters

6 Multi-Band Radios

6 AN/ASN-163 Miniature Airborne Global Positioning System (GPS) Receivers (MAGR)

36 AN/AVS-9 Night Vision Goggles

Plus a Joint Mission Planning System, support and test equipment, software, repair and return, aircraft ferry services and tanker support, spare and repair parts, technical documentation, personnel training and training equipment, and other forms of US Government and contractor support.

The principal contractors involved with this proposed sale will be the Bell and Boeing joint venture in California, MD, with final aircraft assembly occurring in Amarillo, TX. Implementation of this proposed sale will require up to 30 US Government or contractor representatives in Israel on a temporary basis for program technical support and management oversight. Sources: US DSCA #13-73.

DSCA request: Israel (6)

Dec 23/13: Upgrades. An $9 million cost-plus-fixed-fee, firm-fixed-price contract exercises an option for 2 V-22 Block A to Block B 50-69 series upgrade kits.

All funds are committed immediately, using FY 2014 Navy procurement budgets. Work will be performed in Philadelphia, PA (60%) and Fort Worth, TX (40%), and is expected to be complete in November 2015 (N00019-13-C-0021).

Dec 17/13: Infrastructure. The Watts Contrack joint venture in Honolulu, HI receives a $57.1 million firm-fixed-price contract to build an MV-22 hangar, infrastructure and aircraft staging area for one MV-22 squadron at Marine Corps Base Hawaii. Work includes a multi-story type II modified high bay aircraft maintenance hangar that uses a steel frame and metal roof, along with a 2nd story administrative space. Other primary and supporting facilities include an aircraft taxiway with shoulders, a 12-plane staging area, a Substation No. 3 feeder upgrade, and utility infrastructure. This will require earthwork in advance, and paving and site improvements include site storm drainage systems and taxiway shoulders. An unexercised option could raise the cumulative contract value to $59 million.

All funds are committed immediately, using 2010, 2011 & 2013 construction. This contract was competitively procured via Navy Electronic Commerce Online, with 9 proposals received by NAVFAC Pacific in Pearl Harbor, Hawaii (N62742-14-C-1327).

Dec 6/13: ECP – HMD. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded a $15.6 million firm-fixed-price delivery order for additional engineering and technical support. They need to forward fit/retrofit Engineering Change Proposal #1007 into the V-22, and the contract also includes 8 helmet mounted display retrofit kits, spares, support equipment, tooling, and training devices. All finding is committed immediately, using FY 2013 US SOCOM budgets.

The V-22 uses Elbit Systems’ ANVIS/HUD helmet mounted displays, and SOCOM’s CV-22s use a new variant with color symbology (q.v. Sept 6/11). Work will be performed at Ridley Park, PA (99.9%), and Fort Worth, TX (0.1%), and is expected to be complete in March 2015 (N00019-12-G-0006, DO 0075).

Oct 31/13: Israel. US Secretary of Defense Chuck Hagel confirms (see April 22/13 entry):

“Tonight, I am pleased to announce that we are working with the Israeli government to provide them with six new V-22s. I have directed the Marine Corps to make sure that this order is expedited. That means Israel will get six V-22s out of the next order to go on the assembly line, and they will be compatible with other IDF capabilities.”

From Hagel’s speech it can be inferred that these are MV-22s in the process of being modified for integration with Israeli systems. Israel had shown increasing interest in the rotorcraft during the last 2 years, so this 1st export is not surprising. Japan will be a tougher sell. Sources: US DoD.

FY 2013

RO-RO tanker test.

CV-22 washing
(click to view full)

Sept 25/13: Training. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded $20.5 million for cost-plus-fixed-fee delivery order to upgrade the existing 15 Marine Corps MV-22 and 8 USAF CV-22 training devices; they’ll be upgraded to MV-22 Block C2.02 and CV-22 Block 20.2.01 configuration.

All funds are committed immediately, using FY 2012 & 2013 budgets. Work will be performed at the Amarillo, TX (63.5%), Chantilly, VA (29%), and Broken Arrow, OK (7.5%), and is expected to be complete in September 2016. The Naval Air Warfare Center’s Training Systems Division in Orlando, FL manages the contract (N00019-12-G-0006, #0026).

Sept 25/13: ECM. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded a $9.5 million cost-plus-fixed-fee modification, for non-recurring engineering and flight test aircraft modifications to incorporate the Joint Allied Threat Awareness System (JTAS) and the APR-39D(V)2 radar warning receiver into the MV-22 Osprey aircraft. JATAS detects lasers and incoming fire, and is a standard for modern Navy rotorcraft. The APR-39 detects radar emissions, and is used on a wide range of US military planes.

$5.2 million in FY 2012 & 2013 RDT&E funds are committed immediately. Work will be performed in Ridley Park, PA (98.7%); St. Louis, MO (1.1%); and El Paso, TX (0.2%), and is expected to be completed in March 2016. US Naval Air Systems Command in Patuxent River, MD manages the contract (N00019-07-G-0008). See also ATK JATAS page | DID re: APR-39.

Sept 5/13: RO-RO Aerial Tanker. The Bell Boeing V-22 Program announces a successful initial test of a roll-on aerial tanker system for the V-22 Osprey. Once it’s loaded in, it extends the refueling hose out a partially-open back ramp to refuel helicopter and aircraft. That kind of system has obvious uses for Special Forces CV-22s, and the US Marines will find a ship-based aerial refueling capability extremely useful. So would the US Navy, which has allowed this capability to shrink with the retirement of its A-6 Intruder and S-3 Viking aircraft fleets. Success could create another argument in favor of the HV-22 as the next naval cargo aircraft (COD, q.v. June 20/13), but serious refueling capability for fighter jets may require more capacity and range than the V-22 can usefully provide.

The August 2013 demonstration over north Texas used F/A-18C and F/A-18D Hornet fighters, and only tested the V-22 system’s ability to perform on command and maintain stable hose positions. Future tests will involve graduated stages, leading to connections with receiver aircraft and then active refueling. Sources: Boeing and Bell Helicopter’s Sept 5/13 releases.

Aug 22/13: Support. Rolls-Royce in Indianapolis, IN receives a $10.8 million to a previously awarded firm-fixed-price contract modification for 11 low power repairs (see above) to AE1107 turboshaft engines, and 2 months of mission care site support, for the HMX-1 VH-22s in Quantico, VA.

Those are the new Presidential V-22s, which received so many headlines recently for being used to take the President’s dog Bo on vacation. Not to mention 2 bags of basketballs. They aren’t used to carry the President, so if you ever get a ride on one, just remember that they’re carrying you instead of basketballs.

All funds are committed immediately. Work will be performed in Oakland, CA (70%); Indianapolis, IN (20%); and Quantico, VA (10%), and is expected to be complete in February 2014. US Naval Air Systems Command in Patuxent River, MD manages the contract (N00019-10-C-0020). Sources: Boston Globe, “Obamas arrived on Martha’s Vineyard” | Washington Times, “Dog days of summer: Bo Obama flies on Osprey to Martha’s Vineyard vacation”.

Aug 21/13: Japan. Japan is looking to create a small force of Marines to protect its outlying islands, in an expansion of the Western Army’s Infantry Regiment. A preparatory force is being set up, and Japan reportedly plans to equip the final force with MV-22 Ospreys.

The MV-22B has been very controversial in Okinawa (q.v. September 2012 entry), which isn’t happy to have the Marines in general. A role in the defense of Japan’s outlying Islands will help change the V-22′s perception in Japan as a whole, and Japan plans to buy early. It will take a while for the new unit to learn how to fly and use the Ospreys, and they’ll want to be ready by the time the unit is officially activated. A sharp jump in the YEN 8 million ($80,000) budget to research V-22 integration into the JSDF will be the 1st step. Sources: Asahi Shinbun, “Defense Ministry preparing Japanese version of U.S. Marines”.

Aug 16/13: Support. The Bell-Boeing Joint Project Office in Amarillo, TX receives a maximum $43 million delivery order for prop rotor gearboxes, under a firm-fixed-price, sole-source Navy contract.

There was 1 solicitation with 1 response. Work will be performed until December 2017. The US Defense Logistics Agency Aviation in Philadelphia, PA manages the contract (SPRPA1-09-G-004Y, DO 6125)

June 24/13: Engines. Rolls-Royce in Indianapolis, IN receives a $7.1 million firm-fixed-price contract modification for “additional engineering services for up to 9,253 [engine] flight hours for the MV-22 fleet aircraft in support of Operation Enduring Freedom and the east and west coast Marine Expeditionary Units deployments.”

Work will be performed in Oakland, CA (70%), and Indianapolis, IN (30%), and is expected to be complete in November 2013. All funds are committed immediately from a combination of regular and OCO war supplemental budgets, and it will all expire on Sept 30/13 (N00019-10-C-0020).

June 27/13: +1 MV-22. A $60.2 million modification adds 1 MV-22 to the fixed-price-incentive-fee Lot 17 – 21 multiyear contract, using the FY 2013 funds under the Variation in Quantity clause. All funds are committed immediately.

Work will be performed in Fort Worth, TX (24.6%); Ridley Park, PA (19.2%); Amarillo, TX (10.4%); Dallas, TX (4.3%); East Aurora, NY (2.5%); Park City, UT (1.7%); El Segundo, CA (1.3%); Endicott, NY (1%); Ontario, Canada (0.9%); Tempe, AZ (0.8%); Rome, NY (0.7%); Torrance, CA (0.7%); Luton, United Kingdom (0.6%); Clifton, NJ (0.6%); Salisbury, MD (0.6%); Los Angeles, CA (0.6%); Cobham, United Kingdom (0.6%); Irvine, CA (0.6%); San Diego, CA (0.5%); Yakima, WA (0.5%); Brea, CA (0.5%); Rockmart, GA (0.5%); McKinney, TX (0.4%); Albuquerque, NM (0.4%); Whitehall, MI (0.4%); Wolverhampton, United Kingdom (0.4%); Tucson, AZ (0.4%); Erie, PA (0.3%); Vergennes, Vt. (0.3%); Kilgore, TX (0.3%); Shelby, NC (0.3%); Avon, OH (0.2%); Santa Clarita, CA (0.2%); Garden City, NY (0.2%); El Cajon, CA (0.2%); Corinth, TX (0.2%); Sylmar, CA (0.2%); Westbury, NY (0.1%); and various other locations inside and outside the United States (21.8%). The contract runs until November 2016 (N00019-12-C-2001).

1 extra MV-22

June 20/13: HV-22? The US Navy’s Analysis of Alternatives for the Carrier Onboard Delivery (COD) fleet cargo role will lead to an RFP in late 2014, with a contract award planned for FY 2016. The V-22 reportedly did better than the Navy had expected in the initial AoA analysis, and is now expected to be a strong competitor.

Northrop Grumman will be offering a much cheaper option: remanufacture and upgrade the existing 35-plane C-2 fleet, incorporating technologies from the derivative E-2D Hawkeye AWACS plane that’s just beginning to roll off Florida production lines. The new C-2s would have remanufactured fuselages and wings, with the E-2D’s improved engines and propellers, cockpit, and avionics. The goal would be a service life extension from 2028 to 2048, for much less than the $78 million average flyaway cost of a V-22, and lower operating costs.

The original V-22 program had the Navy ordering 48 “HV-22″ Ospreys for duties like search and rescue, but heavy downwash, technical problems, and high costs led them to assign HV-22 roles to the MH-60S Seahawk helicopter instead. The COD competition offers the V-22 a second crack at a Navy contract, and they’ll be touting an HV-22′s ability to deliver to each ship in the fleet, instead of offloading onto a carrier for helicopter delivery to individual ships. NDIA National Defense.

June 12/13: MYP-II. A $4.894 billion modification finalizes the previously Lot 17 contract (q.v. Dec 12/12) into a fixed-price-incentive-fee, multi-year contract. It covers the manufacture and delivery of 92 MV-22s for the US Marine Corps, and 7 CV-22s for AFSOCOM. $326.7 million is committed immediately, using FY 2013 Navy, USAF, and SOCOM budgets.

The proposal in the FY 2013 budget involved 98 Ospreys (91 MV-22, 7 CV-22), and priced the overall outlay at $6.5 billion, in order to create an $852.4 million savings over individual annual buys. When the Dec 21/12 contract is added to this announcement, the actual MYP-II contract adds up to $6.524 billion for 99 tilt-rotors.

Work will be performed in Fort Worth, TX, (23%); Ridley Park, PA (18%); Amarillo, TX (10%); Dallas, TX (4%); East Aurora, NY (3%); Park City, UT (2%); El Segundo, CA (1%); Endicott, NY (1%); Tempe, AZ (1%); and other locations (37%), and is expected to be complete in September 2019. (N00019-12-C-2001).

US NAVAIR also announced the deal, while setting the current fleet at 214 V-22s in operation worldwide, with more deliveries to come in fulfillment of past orders. That serving fleet has amassed nearly 200,000 flight hours, with more than half of those logged in the past 3 years.

MYP-II:
92 MV-22s,
7 CV-22s

June 10/13: Reuters reports that the U.S. Navy plans to sign the V-22′s second multi-year procurement deal this week, and buy 99 more V-22s. The deal was supposed to begin in FY 2013, and that contract has already been issued. On the other hand, as we’ve seen with the Super Hornet program, it’s possible for multi-year deals to reach back a year and incorporate existing commitments.

USMC Col. Gregory Masiello says the decision underscores the government’s confidence in the V-22. Alternative and possibly co-existing explanation: it underscores the USMC’s desire to make the program untouchable, helping to shield the overall force from budget cuts by making the depth of cuts needed elsewhere too unpalatable to think about.

June 7/13: Engines. Rolls-Royce Corp. in Indianapolis, IN received a $6.9 million firm-fixed-price contract modification for 10 “low power repairs” of the CV-22′s AE1107 turboshafts.

Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and is expected to be complete in February 2014. All funds are committed immediately, using USAF FY 2013 Operations and Maintenance dollars that will expire on Sept 30/13 (N00019-10-C-0020).

May 16/13: Lot 18. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded a $40 million contract modification for long-lead components associated with the manufacture and delivery of 19 USMC MV-22Bs in Production Lot 18 (FY 2014). Which is 1 more than the budget stated, but there are also OCO supplemental requests for wartime replacement. All funds are committed immediately.

Work will be performed in Fort Worth, TX (24.6%); Ridley Park, PA (19.2%), Amarillo, TX (10.4%), Dallas, TX (4.3%); East Aurora, NY (2.5%); Park City, Utah (1.7%); El Segundo, CA (1.3%); Endicott, NY (1.0%); Ontario, Canada (0.9%); Tempe, AZ (.8%); Rome, NY (0.7%); Torrance, CA (0.7%); Luton, United Kingdom (0.6%); Clifton, NJ (0.6%); Salisbury, MD (0.6%); Los Angeles, CA (0.6%); Cobham, United Kingdom (0.6%); Irvine, CA (0.6%); San Diego, CA (0.5%); Yakima, WA (0.5%); Brea, CA (0.5%); Rockmart, GA (0.5%); McKinney, TX (0.4%); Albuquerque, NM (0.4%); Whitehall, Mich. (0.4%); Wolverhampton, United Kingdom (0.4%); Tucson, AZ (0.4%); Erie, PA (0.3%); Vergennes, VT (0.3%); Kilgore, TX (0.3%); Shelby, NC (0.3%); Avon, Ohio (0.2%); Santa Clarita, CA (0.2%); Garden City, NY (0.2%); El Cajon, CA (0.2%); Corinth, TX (0.2%); Sylmar, CA (0.2%); Westbury, NY (0.1%); and other locations (21.8%). Work is expected to be complete in September 2016 (N00019-12-C-2001).

April 22/13: Israel. Secretary of Defense Hagel announces that Israel will order V-22s, as part of a package that includes KC-135 aerial tankers, AESA radars for their fighter jets, and radar-killing missiles:

“Minister Yaalon and I agreed that the United States will make available to Israel a set of advanced new military capabilities,… including antiradiation missiles and advanced radars for its fleet of fighter jets, KC-135 refueling aircraft, and most significantly, the V-22 Osprey, which the U.S. has not released to any other nation,” Hagel said…. Introducing the V-22 into the Israeli air force, he added, will give that service long-range, high-speed maritime search-and rescue-capabilities to deal with a range of threats and contingencies.”

“Has not released” is a nice way of saying that Israel was the 1st country to take its request to this level. Based on previous reports (q.v. Aug 2/11, June 8/11), it seems likely that Israel will either order CV-22s, or modify MV-22Bs on its own for special forces roles. Pentagon | Israel Defense | yNet.

April 10/13: FY 2014 Budget. The President releases a proposed budget at last, the latest in modern memory. The Senate and House were already working on budgets in his absence, but the Pentagon’s submission is actually important to proceedings going forward. See ongoing DID coverage.

The FY 2014 request is $1.867 billion to buy 21 aircraft: 18 MV-22Bs and 3 CV-22s. It represents the 2nd year of the V-22′s 2nd multi-year contract.

April 10/13: Ro-Ro Kits. Flight International reports that Boeing is working on a roll-on/roll-off kit for the V-22. The concept could apply to functions like surveillance, via kits designed for ground or even aerial surveillance. Their main focus, however, is reportedly an aerial refueller kit that would extend a hose out the back ramp. Customers like the USMC and SOCOM can use C-130 Hercules turboprops for that, but a V-22 kit would trade less fuel capacity for a refueller that could deploy from ships. There are many situations in which that’s a very useful trade. Flight International.

March 11/13: Support. A $73 million cost-plus-fixed-fee, indefinite-delivery/ indefinite-quantity contract to repair 142 V-22 component types. Funding for this contract will be release through individual task orders.

Work will be performed in Fort Worth, TX (80%) and Ridley Park, PA (20%) until Sept 8/15. This contract was not competitively procured in accordance with 10 USC 2304 (c)(1) by US NAVSUP Weapon Systems Support in Philadelphia, PA (N00383-13-D-017N).

Jan 31/13: Engines. Rolls-Royce Corp. in Indianapolis, IN receives an $83.7 million firm-fixed-price contract modification, exercise an option for 38 AE1107C turboshaft engines (34 USN @ $74.9 million & 4 USAF @ $8.8 million).

This is part of the multi-year engine deal described on March 30/12, and it would equip most of Lot XVII: 17 MV-22s and 2 CV-22s. Work will be performed in Indianapolis, IN and is expected to be complete in December 2014. All contract funds are committed immediately from USN FY 2012 Aircraft Procurement, and USAF FY 2013 Aircraft Procurement budget lines (N00019-12-C-0007).

MV-22 functional check flight
click for video

Jan 17/13: DOT&E testing. The Pentagon releases the FY 2012 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The V-22 is included, and critics are sure to take note of this paragraph:

“No additional flight testing or engineering analysis have been done indicating a change would be appropriate to DOT&E’s September 2005 assessment that the MV-22 cannot perform autorotation to a survivable landing.”

V-22 pilots seem to prefer glides instead, vid. the April 11/10 crash. DOT&E also confirms that the engine nacelles’ integrated wiring systems fail too often, due to internal chafing and wire insulation breakdown. PMA-275 has funded a program to try and fix it by replacing 13 wiring bundles, but this is another issue that’s closely connected to a tilt-rotor’s fundamental design.

Overall, MV-22 Block C upgrades have been helpful to the platform, improving reliability, availability, and maintainability. Some things aren’t quite 100%, though. The weather radar works, but only the right-hand pilot can use it, by sacrificing 1 of the plane’s 2 multi-colored displays. Electronic Standby Flight Instruments have a 1 – 5 second lag in the Vertical Velocity Indicator, which makes it hard to handle aircraft altitude. The Traffic Advisory System (TAS) was a complete fail, triggering warnings when the V-22 entered formation flight.

Dec 28/12: Lot 17. A $1,405.7 million contract modification, covering 21 FRP Lot 17 (FY 2013) tilt-rotors: 17 MV-22s and 4 CV-22s. With long-lead contracts added, the total comes to $1,629.5 million including engines. Even this may not reflect full costs, given other government furnished equipment.

The contract modification also includes long-lead items for another 21 FRP Lot 18 (FY 2014) aircraft: 18 MV-22s and 3 CV-22s. These are the first big buys under the new multi-year contract, and $1,043.6 million is committed immediately.

Work will be performed in Fort Worth, TX (24.6%); Ridley Park, PA (19.2%); Amarillo, TX (10.4%); Dallas, TX (4.3%); East Aurora, NY (2.5%); Park City, UT (1.7%); El Segundo, CA (1.3%); Endicott, NY (1.0%); Ontario, Canada (0.9%); Tempe, AZ (.8%); Rome, NY (0.7%); Torrance, CA (0.7%); Luton, United Kingdom (0.6%); Clifton, NJ (0.6%); Salisbury, MD (0.6%); Los Angeles, CA (0.6%); Cobham, United Kingdom (0.6%); Irvine, CA (0.6%); San Diego, CA (0.5%); Yakima, Wash. (0.5%); Brea, CA (0.5%); Rockmart, GA (0.5%); McKinney, TX (0.4%); Albuquerque, N.M. (0.4%); Whitehall, Mich. (0.4%); Wolverhampton, United Kingdom (0.4%); Tuczon, AZ (0.4%); Erie, PA (0.3%); Vergennes, Vt. (0.3%); Kilgore, TX (0.3%); Shelby, N.C. (0.3%); Avon, OH (0.2%); Santa Clarita, CA (0.2%); Garden City, NY (0.2%); El Cajon, CA (0.2%); Corinth, TX (0.2%); Sylmar, CA (0.2%); Westbury, NY (0.1%); and other locations, each below 0.25% (21.8% total), and is expected to be complete in September 2016. US Naval Air Systems Command, Patuxent River, MD, is the contracting activity (N00019-12-C-2001).

FY 2013 buy & FY 2014 long-lead items

Jan 3/13: Japan. Despite a steady stream of anti-Osprey protests on Okinawa through 2012, Japan is reportedly becoming interested in buying the V-22 for itself. The idea was actually proposed in October 2012 by ousted Prime Minister Noda’s administration, but the new Abe government’s push for more defense capabilities is expected to boost the Osprey’s odds. Sources: Defense Update, “Japan Looking At Procuring Controversial V-22 Osprey”.

Dec 28/12: Avionics. A $33.6 million cost-plus-fixed-fee delivery order for engineering and technical support for V-22 flight control system and on-aircraft avionics software; flight test planning and coordination of changed avionics and flight control configurations; upgrade planning of avionics and flight controls, including performance of qualification testing; and integration testing on software.

Work will be performed in Philadelphia, PA, (90%) and Fort Worth, TX (10%), and is expected to be complete in December 2013. All contract funds are committed immediately, but $10.9 million will expire at the end of the current fiscal year, on Sept 30/13 (N00019-12-G-0006).

Dec 21/12: MV-22 upgrades. A $19.6 million firm-fixed-price contract modification exercises an option for 2 MV-22 Block A to B 50 – 69 series upgrade installs, and 3 MV-22 Block A to B kits.

Work will be performed in Philadelphia, PA (60%); Havelock, NC (20%); and Fort Worth, TX (20%), and is expected to be complete in June 2016. All contract funds are committed immediately (N00019-12-C-0091).

Nov 27/12: Engine support. Rolls-Royce Corp. in Indianapolis, IN receives a $52.3 million firm-fixed-price contract option for AE1107C engine sustainment services, on behalf of the USMC and the USAF. It covers “low power repairs”, turboshaft engine support and fleet site support until November 2013.

Work will be performed in Indianapolis, IN (80%), and Oakland, CA (20%), and is expected to be complete in November 2013. “Contract funds in the amount of $52,267,510 will be obligated on this award of which $50,378,962 will expire at the end of the current fiscal year.” (N00019-10-C-0020).

Nov 5/12: De-icing. A $9.5 million firm-fixed-price contract modification to buy 51 V-22 central de-icing Distributor retrofit kits and 29 engine nacelle ice protection controller unit retrofit kits. Icing up has been a recurring issue for the V-22, due to its structure and the altitudes it flies at. Work will be performed in Fort Worth, TX and is expected to be complete in December 2014 (N00019-07-G-0008).

Oct 4/12: Crash whitewash? Brig. Gen. Don Harvel (ret.), who led the investigation into the April 9/10 CV-22 crash in Afghanistan, discusses the USAF’s efforts to whitewash his investigation, and prevent publication of a report that pointed to engine failure as the cause of the crash. WIRED Danger Room.

Oct 4/12: Support. A $204.9 million cost-plus incentive-fee delivery order for supply chain management of 170 components, over slightly more than 4 additional years, in support of the V-22 aircraft.

Work under the performance based logistics contract will be performed in Fort Worth, TX (80%), and Ridley Park, PA, (20%) and is expected to be complete by Dec 31/16. This contract was not competitively procured by NAVSUP Weapon Systems Support in Philadelphia, PA, in accordance with 10 U.S.C. 2304c1a (N00019-09-D-0008, #0006). See also US Navy.

FY 2012

MV-22, landing
(click to view full)

Sept 26/12: Paint me. An $8.8 million modification to a previously awarded fixed-price-incentive-fee, firm-target V-22 multi-year production contract, to add the HMX-1 paint scheme to 14 MV-22s: 7 Lot 15 and 7 Lot 16 aircraft.

Work will be performed in Fort Worth, TX (98%), and Philadelphia, PA (2%), and is expected to be complete in November 2014. Contract funds will not expire at the end of the current fiscal year (N00019-07-C-0001).

Sept 25/12: Training. A $74.1 million firm-fixed-price contract for 7 MV-22 Block C Containerized Flight Training Devices (CFTD – simulators) including spares and a support period.

Work will be performed in Amarillo, Texas (39%); Chantilly, VA (30%); Salt Lake City, UH (13%); Clearwater, FL (11%); Orlando, FL (3%); Lutz, Fla. (2%); Huntsville, AL (1%) and Ann Arbor, MI (1%), and is expected to be complete in October 2016. NAWCTSD received one other bid. The Bell-Boeing team delivered a first batch of 6 CFTDs (q.v. Aug 16/10 entry) between 2007 and 2010 (N61340-12-C-0033). See also FBO #N61340-12-C-0033, initiated in December 2011.

Sept 25/12: Sub-contractors. Raytheon in Mckinney, TX receives a maximum $14.7 million firm-fixed-price, sole-source contract for CV-22 support. The firm does a lot of V-22 avionics work, and there was one solicitation with one response.

Work will use FY 2012 Navy Working Capital Funds, and continue to August 2014. The US Defense Logistics Agency Aviation in Philadelphia, PA manages this contract (SPRPA1-09-G-001X-1058).

Sept 21/12: Sub-contractors. US NAVAIR announces a $3 million cost-plus fixed fee award to Mound Laser & Photonics Center, Inc. in Miamisburg, OH for “Operational Readiness Improvement of V-22 Osprey via Wear Mitigation of Key Engine Components.” It’s a backhanded acknowledgement of a problem. FBO.gov.

September 2012: Japan. In press conference after press conference, the Japanese Ministry of Defense is hounded by journalists seeking to see who will get the last word, as local opposition to the Osprey deployment continued unabated (see July 2012 entries below). The mayors of Iwakuni and Ginowan continue to express their disapproval with ongoing, though smaller, protests going on for 3 months now, despite the authorities granting official safety clearance to the aircraft on September 18.

Aug 14/12: MV-22 post-crash. The USMC releases publicly a redacted report [PDF] on the April 2012 crash in Morocco. It concludes that the co-pilot lacked proper understanding of true wind speed during take off then made errors that led to losing and failing to regain control of the aircraft. The report also regrets that the two marines who lost their lives in the accident were not strapped to their seats.

Among recommendations, they want additions to NATOPS manuals to cover the type of tailwind circumstances under which the accident occurred. USMC Deputy Commandant for Aviation Lt. Gen. Schmidle Jr. subsequently said during a press conference that other pilots will be briefed on what happened, and training and simulators will be updated.

July 26/12: Infrastructure. Barnhart-Balfour Beatty, Inc. in San Diego, CA receives a $35.5 million firm-fixed-price task order to demolish an existing aircraft hangar at Marine Corps Air Station Camp Pendleton, CA, and build a new 2-bay MV-22 hangar with adequate space to support maintenance. The contract also funds interior furniture, fixtures, and equipment, and contains options that could raise its value to $35.7 million.

Work will be performed in Oceanside, CA, and is expected to be complete by August 2015. Nine proposals were received for this task order, under a multiple-award contract managed by US Naval Facilities Engineering Command, Southwest in San Diego, CA (N62473-10-D-5407, #0004).

July 25/12: CV-22 SATCOM. A $22.2 million cost-plus-fixed-fee contract modification for engineering design, integration and testing of an improved CV-22 Block 20 communications system for “trans-oceanic air traffic control and tactical communications”.

Work will be performed in Philadelphia, PA (99%), and Amarillo, TX (1%), and is expected to be complete in December 2015. $79,188 will expire at the end of the current fiscal year, on Sept 30/12 (N00019-08-C-0025).

July 23/12: Japan. Twelve MV-22 Osprey tiltrotor aircraft are off-loaded from the civilian cargo ship Green Ridge at Marine Corps Air Station Iwakuni, Japan, which features both an airfield and a port facility. This marks the first deployment of the MV-22 to Japan. With their range and in-flight refueling capability, MV-22s would be able to transfer marines to disputed regions included the Pinnacle Islands, Taiwan and the South China Sea.

MCAS Iwakuni Marines will prepare the 12 aircraft for flight, but they won’t conduct functional check flights until the Government of Japan confirms the safety of flight operations. After their check-out flights, the Ospreys will fly to their new home at MCAS Futenma in Okinawa, Japan, as part of Marine Medium Helicopter Squadron 265 (HMM-265).

A 2nd squadron of 12 aircraft is scheduled to arrive at MCAS Futenma during the summer of 2013. However arrival of the aircraft has proven contentions with protests to its deployment making evening TV news in Japan. USMC | US Embassy in Japan | Want China Times | The Economist.

July 21/12: Japan. At a press conference in Tokyo, Deputy US Defense Secretary Ashton B. Carter answered questions and described the compromise reached with the Japanese government concerning MV-22 deployment in Japan.

“…we are committed to providing your airworthiness experts with all of the data and all of the information about the entire flight history of the V-22, including the two recent incidents, and allowing them to analyze that data and take every step they need to make to reconfirm the airworthiness of that airplane… This is a process, a technical process of assessing airworthiness. I think you have to let the experts do their work…”

The U.S. and Japanese governments have agreed that flight operations will not begin until that reconfirmation has taken place. Let’s just say that it would be unlikely for the answer to be “no” at the end of this process. US DoD.

July 19/12: Japan. Fourteen governors whose prefectures host U.S. bases issued a statement criticizing the delivery of MV-22 Ospreys at MCAS Iwakuni in Yamaguchi Prefecture. They plan to ask the central government to take responsibility for explaining to prefectural authorities the impact on residents of the Osprey training flights that are to be conducted through many parts of the country, and to respect local opinions. There has also been talk of extending the inquiry to include Class-B (partial disability or $500,000+ damage) and Class-C ($50-500 thousand, recovered injury) V-22 accidents, but:

“The U.S. military regards Class-A mishaps as the major accidents,” a Defense Ministry official said. “There would be no end to the procedure if you began taking up Class-B and Class-C incidents.”

See: Asashi Shimbun | Japan Times.

V-22 onto CVN 77
click for video

July 19/12: CVN landing. A V-22 Osprey from Marine Tiltrotor Operational Test and Evaluation Squadron (VMX) 22 lands for the first time on USS Harry S. Truman (CVN 75) to contribute to that carrier’s flight deck certification. V-22s had already landed on aircraft carriers CVN 77 and 72 earlier during the year, says NAVAIR.

Concepts of employment for the Navy’s V-22s published as early as 2004 [PDF] included landing on carriers for search & rescue missions and for logistics done so far with C-2As. Whether the Navy will procure its own V-22s as carrier on-board delivery planes (COD) has been discussed for years (see also Aug 11/10 entry).

July 12/12: Infrastructure. Pave-Tech Inc. in Carlsbad, CA receives $8.3 million for firm-fixed-price task order to design and build the MV-22 Aviation Pavement Project at Marine Corps Air Station, Camp Pendleton, CA. All contract funds are obligated immediately, and the firm will install or rehabilitate Pendleton’s aircraft pavement to accommodate MV-22 squadrons.

Work will be performed in Oceanside, CA, and is expected to be complete by January 2014. Four proposals were received for this task order, under a multiple-award contract managed by US Naval Facilities Engineering Command, Southwest in San Diego, CA (N62473-09-D-1605, #0012).

June 22/12: CV-22. A $74.4 million option under the fixed-price-incentive-fee V-22 multi-year production contract, to provide 1 CV-22 combat loss replacement aircraft for the Air Force.

Work will be performed in Philadelphia, PA (56%); Amarillo, TX (43%); and El Paso, TX (1%), and is expected to be complete in November 2014 (N00019-07-C-0001).

CV-22 loss replacement

June 16/12: Japan. USMC MV-22s were supposed to deploy to MCAS Futenma in Okinawa, but recent crashes (vid. April 11/12, June 13/12 entries) led Japan’s government to halt those plans. Chief Cabinet Secretary Osamu Fujimura says that Tokyo has asked the United States to investigate the details of the crash as quickly as possible, adding that the “Japanese government will take no further action [on the Osprey deployment] unless details [of the crash] are shared…”

The Osprey deployment has also turned into a lightning rod among local politicians, who cite safety fears. On the one hand, this is a pretext, as many of these politicians are simply hostile to the base in general. On the other hand, Okinawa is densely populated enough that crashes are a legitimate civilian concern, and a crash that killed civilians there could set off a serious political crisis. Even mainland locals in MCAS Iwakuni, where USMC MV-22s were temporarily deployed in July 2012, are restive. Daily Yomiuri.

June 15/12: Support. A firm-fixed-price, sole-source $6.5 million contract for MV-22 rudder assemblies. Work will be performed in Texas and Pennsylvania, using FY 2012-2015 Navy Working Capital Funds until Sept 30/15. The Defense Logistics Agency Aviation in Philadelphia, PA manages this contract (SPRPA1-09-G-004Y-5948).

June 13/12: Crash. Hurlburt Field announces that 5 aircrew members were injured when their CV-22 crashed north of Navarre, FL on the Eglin Range, during a routine gunnery training mission. The cause of the crash is unknown, as the lead ship didn’t see them go down. The CV-22 came to rest upside down, and there were fires in the area that had to be fought afterward. It may not be salvageable.

At a June 14/12 press conference, Col. Slife says that CV-22 flights will resume while the Safety Board and Accident Board complete their work. He adds that mission requests from SOCOM currently exceed the CV-22 fleet’s capacity to fill them. As of June 15/12, 3 of the 5 crew remain hospitalized, in stable condition.

CV-22 Crash

June 4/12: Engine support. Rolls-Royce Corp. in Indianapolis, IN received a $10.8 million firm-fixed-price contract modification for 18 CV-22 “low power repairs” to their AE1107C turboshaft engines.

Work will be performed in Oakland, CA (70%), and Indianapolis, IN (30%), and is expected to be complete in February 2013. All contract funds will expire at the end of the current fiscal year, on Sept 30/12 (N00019-10-C-0020)

April 11/12: Fatal Crash. A USMC MV-22B crashes in a training area southwest of Agadir, Morocco, during a the African Lion 2012 military exercise. The Marine Corps Times reported that it had just unloaded a group of Marines at a training camp and was returning to the amphibious assault ship USS Iwo Jima when it crashed. That probably prevented a lot of fatalities, as the crash killed 2 Marines and injured the other 2 on board. USMC | Fort Worth Star-Telegram | POGO’s program crashes timeline.

MV-22 crashes

March 30/12: Multi-year Engine Contract. Rolls-Royce Corp., Indianapolis, IN receives a $150.9 million 1st year installment on a 5-year firm-fixed-price contract, to buy 70 AE1107C turboshaft engines for the US Navy ($129.4 million) and US AFSOC ($21.6 million).

An April 23/12 Rolls-Royce release clarifies the total award as a $598 Million contract for up to 268 installed and spare engines, to equip USMC MV-22s (232) and AFSOC CV-22s (33). The contract has 4 more option years left, and will run to October 2017. Work will be performed in Indianapolis, IN. This contract was not competitively procured pursuant to FAR 6.302-1. US Naval Air Systems Command in Patuxent River, MD manages this contract (N00019-12-C-0007).

Multi-year engine buy

March 30/12: GAO Report. The US GAO tables its “Assessments of Selected Weapon Programs” for 2012. The V-22 program is included only in passing, as GAO notes the fleet’s current expected total purchase cost of $57.211 billion. That’s a hefty jump from even the “first full estimate” baseline, but the last 5 years have seen a change of just 5.2%.

On the other hand, most of a platform’s costs lie in Operations & Maintenance budgets, and here the V-22 remains a question mark – vid. Nov 29/11 reports that the fleet’s cost would break $100 billion.

March 30/12: Guns. A $31.3 million cost-plus-fixed-fee modification to a delivery order will design and develop improvements to BAE’s Interim Defensive Weapon System (IDWS) turret, retrofit the IDWS to incorporate these improvements, provide IDWS logistical support, and perform aero model and software updates.

Work will be performed in Johnson City, NY (95%), and Philadelphia, PA (5%), and is expected to be complete in December 2015 (N00019-07-G-0008).

March 30/12: Testing. A $28,846,120 fixed-price-incentive, cost-plus-fixed-fee delivery order to provide a new V-22 instrumented aircraft (NVIA) for testing. The NVIA will support V-22 structural tests, and replace an existing test aircraft which is “increasingly difficult and expensive to support and not representative of current production configuration.” They also expect the new NVIA bird to support the V-22 development roadmap with better flight test data, and better reliability than the existing test aircraft.

Work will be performed in Amarillo, TX (35%); Arlington, TX (35%); Fort Worth, TX (21%); Philadelphia, PA (8%); and Seattle, WA (1%), and is expected to be complete in December 2014 (N00019-12-G-0006).

March 6/12: V-22 flight costs. Loren B. Thompson of the Lexington Institute think tank fires a piece strongly in favor of the MV-22, arguing that detractors are not applying the right metrics to properly assess its value, saying they:

“…complain it costs about $10,000 per flight hour to operate the MV-22 compared with about $3,000 per flight hour for the MH-60, the Marine helicopter most closely resembling what the Air Force uses for combat search-and-rescue. However, this ignores the superior speed, range and carrying capacity of the MV-22. When the metric is changed to cost per mile flown, the MV-22 only looks about 60 percent more expensive, and when the metric is passenger seat miles, the MV-22 looks twice as efficient ($1.53 versus $3.21).”

Of course, passenger seat miles assume full capacity. Airlines know that isn’t always true, and the variety inherent in military missions makes it a poor choice of statistic. Thompson does add one point that’s more reasonable, when he says that:

“It is also worth noting that the MV-22′s computerized reporting system depresses apparent readiness rates compared with the older, manual system used for the legacy CH-46s it will replace.”

Feb 26/12: Media are picking up on previous reports of interest from Canada, Israel, and the United Arab Emirates, and have added India as a potential export prospect. Most of this involves trade show visits, which don’t mean much, though some cases have involved formal requests for technical information (Israel) and even limited demonstrations (Canada).

This comes as the US military operates more than 160 CV/MV-22s, and has flown more than 130,000 hours with the aircraft. Reuters | Flightglobal. See also Aug 2/11 and Dec 1/11 entries.

Feb 17/12: Hostile in HASC. Congresswoman Jackie Speier (D-CA-12, south San Francisco) joins the House Armed Services Committee. Her position statement on defense makes it clear that she’s no fan of the V-22, or of missile defense.

Feb 14/12: MV-22 Block C The first MV-22 Block C is delivered, with enhanced displays in the cockpit and in the cabin. See also Nov 24/09 entry. Boeing.

Feb 13/12: MYP-II? FY13 Budget Request. The Navy proposes a follow-on multiyear procurement (MYP) to buy 98 V-22 aircraft (91 MV-22, 7 CV-22) under a single fixed-price contract, between FY 2013 – FY 2017. The MV-22s will be bought by the Navy for the Marines, while the CV-22s aircraft are a joint buy involving the USAF and SOCOM. Their hope is to save $852.4 million, or 11.6% of the total.

Feb 9/12: T-AKE ship landing. A USMC MV-22 Osprey tilt-rotor aircraft from VMM-266 makes the 1st landing aboard a T-AKE ship, on USNS Robert E. Peary [T-AKE 5]. The Osprey landed aboard Robert E. Peary while conducting an experimental resupply of Marines during exercise Bold Alligator 2012.

If the USMC can turn this test into a standard operating procedure, it would let the Marines lift ammunition directly from a T-AKE shuttle ship to shore, rather than using further transfer to other ships. U