In March 2008, the Bell Boeing Joint Project Office in Amarillo, TX received a $10.4 billion modification that converted the previous N00019-07-C-0001 advance acquisition contract to a fixed-price-incentive-fee, multi-year contract. The new contract rose to $10.92 billion, and was used to buy 143 MV-22 (for USMC) and 31 CV-22 (Air Force Special Operations) Osprey aircraft, plus associated manufacturing tooling to move the aircraft into full production. A follow-on MYP-II contract covered another 99 Ospreys (92 MV-22, 7 CV-22) for $6.524 billion. Totals: $17.444 billion for 235 MV-22s and 38 CV-22s, an average of $63.9 million each.

The V-22 tilt-rotor program has been beset by controversy throughout its 20-year development period. Despite these issues, and the emergence of competitive but more conventional compound helicopter technologies like Piasecki’s X-49 Speedhawk and Sikorsky’s X2, the V-22 program continues to move forward. This DID Spotlight article looks at the V-22’s multi-year purchase contract from 2008-12 and 2013-2017, plus associated contracts for key V-22 systems, program developments, and research sources.

The V-22 Program



Documentary

V-22 Initial Operational Capability didn’t begin until 2007, about 24 years after the initial design contract. A long series of design issues and mass-fatality crashes almost got the program canceled, but Congressional industrial lobbying preserved it.

The current objective is 472 Osprey tilt-rotors: 360 MV-22 Marine Corps aircraft, 14 VH-22 Presidential squadron, 50 CV-22 aircraft for USSOCOM (funded by USSOCOM and the Air Force), and 48 HV-22 Navy aircraft.

USMC. The Marine Corps plans to field:

18 active squadrons x 12 MV-22B

2 reserve squadrons x 12 MV-22B

1 fleet replacement squadron x 20 MV-22B

A requirements-based analysis is underway to increase the program of record to 388, which would involve the introduction of VMM-362 and VMM-212 in FY 2018 – 2019.

As of November 2014, the USMC says that they’re 65% through its transition from CH-46E Sea Knight helicopters, with 13 full operational capability squadrons. Remaining switchovers will involve the West Coast, Hawaii, and the reserves, with some basing shifts, and the last CH-46E retiring from HMM-774 in early FY 2015.

Presidential. Beyond the USMC’s combat and training units, a squadron of 12 USMC VH-22s now serves in the Presidential squadron, effectively replacing past CH-46E and CH-53E helicopters. The President never rides in them, though – they’re solely for supplies, aides, etc. By FY 2016, the squadron will be full at 14 planes.

Navy. There was supposed to be an V-22 for the US Navy, but its expected roles in search and rescue etc. were taken up by the MH-60S Seahawk helicopter. Technically, a buy of 48 HV-22s has always been part of the program. In reality, the US Navy has made no moves to adopt the platform. That may change as of FY 2016, if the V-22 can win a likely competition for the next Carrier Onboard Delivery (COD) platform to replace the fixed-wing C-2A Greyhound. The Osprey won’t be able to compete on price or operating costs against remanufactured C-2s that use technologies from the derivative E-2D Hawkeye production line, while Lockheed Martin’s refurbished and modified C-3 Viking offers jet speeds and the unique ability to carry whole F135 jet engines inside. Boeing and Textron will have to hope that the Navy values the V-22’s commonality, and ability to land on more of the carrier group’s ships, enough to pay a lot more for less internal capacity.

To date, there have been no exports of the V-22. Israel is mulling over an offer for an expedited buy of 6 MV-22s, and Japan is contemplating 20-40 MV-22s to equip their new Marines, but neither has signed a contract. As of October 2014, formal briefings have also been given to Australia, Brazil, Canada, Colombia, Italy, Qatar, Saudi Arabia, Singapore, and the UAE.

MV-22 vs. CV-22



MV-22 & M777
(click to view full)

The V-22 comes in 2 variants.

MV-22. The US Marines operate the MV-22, whose most current configuration is Block C. A subtype of the MV-22 serves in the Presidential squadrons, as the VH-22.

The current MV-22 Block C’s enhancements (software version C1.01) include forward-mounted AN/ALE-47 defensive systems, move the MV-22’s Ice Detectors, improve dust protection for the engines, and add a redesigned Environmental Control System (ECS) to keep devices and troops from overheating. A “Cabin Situational Awareness Device” displays essential mission information, including access to GPS updates for handheld devices, plus way points, flight plans, location, etc. for troop commanders inside. For the pilots, a Color Weather Radar System provides weather detection, ground mapping to 20 nm, and sea search. Electronic Standby Flight Instruments (ESFI) replace the analog standby instrument cluster, and a Day Heads-up Display (HUD) feeds its data to a helmet-mounted monocle. A Traffic Advisory System (TAS) was intended to warn MV-22 pilots of other aircraft that might hit them, but it doesn’t work properly.

As of October 2014, operational USMC squadrons mostly fly the MV-22B Block B. This mix is expected to shift in the near future: from 8 MV-22B Block B and 4 MV-22B Block C per squadron, to an even 8:8 ratio. The VMMT-204 training squadron is different, and will contain Block A and Block B aircraft until Block As are fully phased out FY 2018.

The USMC currently has a real problem escorting MV-22s, with AH-1Z Viper helicopters not really fast enough, and AV-8B Harrier jets a bit too fast. Future plans include more jamming and warning devices, as well as offensive upgrades. Weapons haven’t been very successful on the V-22 yet, thanks to the huge position arc of the tilting rotors. Fixing that requires significant changes like BAE’s IDWS cut-in belly turret, but many pilots prefer to just use the craft’s speed as a defense. Future USMC concepts of operations may not always give them that luxury, so the USMC plans to add an Advanced Targeting Sensor with full laser targeting. It would be accompanied by some kind of precision strike weapon, type undetermined. Those kinds of weapons wouldn’t suffer from the same arc-of-fire problems, but wide turbulence variations could make release testing fun and exciting.

At present, MV-22B Block D is only in the initial planning stage. Block D will serve as a mid-life upgrade, with a partial but much-needed focus on reliability, maintainability, and operating costs. We won’t see an MV-22C until the mid-2030s.

Afghan mission

CV-22. US Air Force Special Operations Command operates the CV-22, which adds more sophisticated surveillance capabilities, beefed-up defensive systems that include the AN/ALQ-211v2, extra fuel tanks, and useful capabilities like terrain-following flight. Its most current configuration is the CV-22 Block 20.

A 2013 incident in South Sudan led to several operators being injured by small arms fire that punched up through the CV-22’s belly. AFSOCOM is looking at lightweight armoring modifications to try to improve that situation.

V-22 Budgets & Buys

Excel
download

Initial Operational Capability in 2007 was followed by a big Multi-Year Procurement contract in FY 2008, which ended up buying 175 V-22s (143 MV-22s, 32 CV-22s) for about $14.416 billion.

The US fiscal situation is almost certain to lead to serious defense budget cuts, so the V-22’s manufacturers responded by trying to lock the government into a 2nd multi-year contract, creating cancellation penalties that would make the Osprey too expensive to kill, and impossible to seriously reduce. Enough contracts like that will end up gutting other USMC investments when cuts do hit, and could lead to even more serious problems if V-22 fleet operations and maintenance costs don’t start dropping very quickly (vid. Nov. 29/11 entry).

That wasn’t the manufacturers’ concern, however, and it wasn’t the Navy’s, either. The FY 2013 budget included a submission to buy 98 more V-22 aircraft (91 MV-22s, 7 CV-22s) under a 2nd fixed-price multi-year contract, between FY 2013 – FY 2017. The MV-22s will be bought by the Navy for the Marines, while the CV-22s aircraft are a joint buy involving the USAF and SOCOM. To get approval for a multi-year buy, they had to demonstrate at least 10% cost savings over the same buys placed year by year. Their proposal hoped to save $852.4 million, or 11.6% of the total, at the price of less flexibility in the number bought through FY 2017:

Proposed V-22 follow-on MYP 2013-17

Year

Qty

Net Proc.
($M)

Savings

FY13

21

1,693

38

FY14

21

1,741

185

FY15

19

1,541

226

FY16

19

1,468

229

FY17

18

1,430

225

Total

98

7,922

852

Source: US Navy, FY13 PB [large PDF].
Totals may not add up due to rounding up and FY12 Advance Procurement (incl. $50M for cost reduction initiatives).

The actual contract and budget plans ended up being a bit different, per the June 12/13 entry and the data and graphs above. Instead of 98 Ospreys (91 MV-22, 7 CV-22) for $6.5 billion, the actual MYP-II contract adds up to 99 tilt-rotors for $6.524 billion.

Contracts & Key Events

AFSOC CV-22
(click to view full)

Unless otherwise noted, US Naval Air Systems Command in Patuxent River, MD issues the contracts, and the Bell-Boeing Joint Program tiltrotor team in Amarillo, TX is the contractor.

Note that “low power repairs” are triggered when an AE1107 engine’s Power Assurance Check (PAC) reads below 96%. It’s normal for aircraft engine performance to drop somewhat over time, and the fix involves engine removal for maintenance and tune-up.

FY 2015

Export prospects. Firing forward.

Rocket test

November 2014: rocket tests. Bell Helicopter announces on Dec. 8 that forward-firing capability was successfully tested during the previous month at the US Army Proving Ground in Yuma, AZ. V-22s refuel and reload from Forward Arming and Refueling Points (FARPs), and Bell hopes that the installation of forward-firing weapons will reduce reliance on them. This may also reduce the need for V-22s to be escorted by slower attack helicopters, and the absence of a forward-facing gun was among the trade-offs that mired the program’s early years in controversy. Back during the program’s prehistory planners had considered turret-mounting a GAU-19 gatling gun in the aircraft’s undernose [GDAS PDF, 2002].

FARP Ops

Nov 3/14: USMC Plan. The USMC’s Aviation Plan to 2030 has a number of sections that are relevant to the V-22. The V-22 Aerial Refueling System (VARS) roll-on capability is being developed to field with the F-35B’s West Pacific deployment in summer 2017, as a near-ship aerial tanker for large-deck amphibious assault ships. Follow-on certifications would aim to refuel other V-22s and helicopters.

The MV-22’s own ability to refuel in the air currently has flight clearance for USMC KC-130s and USAF KC-10s. The next certifications will involve Omega Air Tanker’s private K-707s, and the USAF’s forthcoming 767-based KC-46s. Deployment dates aren’t given for those.

The V-22 fleet is scheduled to get LAIRCM defenses against infrared-guided missiles in 2016, and radar-related defenses are in the Survivability Upgrade Roadmap, but not extra armor (q.v. May 22/14). The Interoperability Upgrade Roadmap makes the MV-22 the lead platform for the the Software Reprogrammable Payload communications package, with integration beginning at the end of FY 15. It’s eventually expected to include full voice/ data/ video compatibility, datalinks like Link-16 and TTNT, and even full airborne communications gateway capabilities. The other future IUR item of especial interest is integrated RFID for cargo and personnel.

Finally, plans exist to beef up MV-22 weapons and “increase all-axis, stand-off, and precision capabilities.” This will include an upgraded Advanced Targeting Sensor with full laser targeting. The huge position arc of the tilting rotors makes guns very difficult to use, absent significant changes like BAE’s IDWS cut-in belly turret. But there’s no issue for small precision gravity weapons like ATK’s Hatchet or MBDA’s Viper-E, small missiles like Raytheon’s Griffin, or well-understood weapons like 7-rocket pods with APKWS laser-guided 70mm rockets, or (less likely) the future JAGM missile.

Weight and complexity are always worth considering before making these kinds of weapon modifications, especially in light of evidence that V-22s already need more belly armor. The V-22’s wide turbulence variations could also make weapon release testing fun and exciting. On the other hand, the USMC currently has a real problem escorting MV-22s, with AH-1Z Viper helicopters not really fast enough, and AV-8B Harrier jets a bit too fast. If the weight trade-off works, a precision weapons option may help solve some operational gaps. Sources: USMC, Marine Aviation Plan 2015 [PDF].

USMC Aviation Plan

MV-22 landing

Nov 2-5/14: Israel. Israeli defense minister Moshe Ya’alon is recommending the cancellation of several deals with the USA, including the V-22. A potential purchase of more F-35s has survived, but the V-22, more KC-135 aerial tankers, radar-killing missiles, and radar upgrades for Israel’s F-15s have not. Instead, recent fighting in Gaza, and developments in Lebanon and Syria, are pushing him toward more buys of precision weapons and ground forces equipment. The weak protection of Israeli M113s has come in for particular criticism.

The decision isn’t final, and the IDF and Mossad were both lobbying to keep the V-22s, in advance of a planned Nov 5/14 meeting of high-level ministers. That meeting showed weakened F-35 support, which may open a door for the V-22s. The USA’s Letter of Offer and Acceptance, which will expire on Dec 10/14, reportedly allows Israel to buy 6 V-22s and initial infrastructure for about $900 million, instead of the $1.3 billion mentioned in the DSCA announcement. The arrangement with the USMC would also ensure delivery by 2016, and funding arrangements involve commercial bridge loans that would be repaid with future American military grant aid. Those are fine terms, and there is both commercial and strategic value in securing Israel as the V-22’s 1st export customer. Now that Japan is also stepping up, however (q.v. Oct 16/14), this isn’t an offer that’s likely to be repeated. Then again, with new technology like Sikorsky’s S-97 Raider emerging, Israel may be field lower-cost, fully-armed options with similar flight performance by 2019 or so. Sources: Defense News, “Israeli Brass Urge MoD To Stick With V-22 Deal” | Times of Israel, “Ya’alon said to cancel aircraft purchase from US” | Times of Israel, “Ministers may look to shoot down F-35 jet deal”.

Oct 23/14: ECM. Northrop Grumman in Rolling Meadows, IL receives a $7.9 million task order for 1-time engineering in support of the MV-22’s Integrated Aircraft Survivability Equipment Suite upgrade, including integration of the AN/AAQ-24(V)25 software with an electronic warfare controller and the MV-22 mission computer. All funds are committed, using FY 2014 US Navy aircraft budgets.

Work will be performed in Rolling Meadows, IL, and is expected to be complete in April 2016. Fiscal 2014 aircraft procurement (Navy) funds in the amount of $7,926,639 will be obligated at time of award, none of which will expire at the end of the current fiscal year. The Naval Air Systems Command, Patuxent River, Maryland, is the contracting activity (N00019-10-G-0004, #00506).

Oct 16/14: Exports. Marine Corps Commandant General James Amos says that he’s pleased with the V-22 (not he’d say anything else), and specifically mentions the roll-on/roll-off aerial tanker capability as something that’s going well. He adds that a 2nd second foreign country is expected to announce plans to buy the V-22 Osprey within the next 6 months, joining Israel (q.v. Jan 14/14) as an export customer.

That country is almost certainly Japan; they have said as much (q.v. Dec 14/13), and supposedly want 20-40 tilt-rotors overall. The article adds that formal V-22 briefings have been given to Australia, Brazil, Canada, Colombia, (Israel), Italy, Qatar, Saudi Arabia, Singapore, and the UAE. Sources: Reuters, “US sees second foreign buyer for V-22 Osprey in six months”.

FY 2014

Israel confirmed for 6; Japan to buy at least 17; Prep & orders for new ECM systems; Lots of support contracts; Still looking for an engine alternative?

MV-22
(click to view full)

Sept 25/14: Training. A $24 million firm-fixed-price delivery order against a previously issued Basic Ordering Agreement to upgrade the MV-22 Consolidated V-22 Electronics Maintenance Trainer, V-22 Sponson Part Task Trainer, V-22 Aircraft Maintenance Trainer, and Power Plants Training Article Trainers to the Block C configuration, to keep them in sync with serving tilt-rotors. All funds are committed immediately, using FY 2013 and 2014 Navy aircraft budgets.

Work will be performed in Philadelphia, PA (35%); Fort Worth, TX (34%); St. Louis, MO (14%); Ozark, AL (11%); Jacksonville, NC (5%); and Mesa, AZ (1%), and is expected to be complete in December 2016 (N00019-12-G-0006, DO 0092).

Sept 25/14: Training. A $10 million firm-fixed-price delivery order for upgrades to 13 Marine Corps MV-22 training devices to the MV-22 Block C-2.01 configuration. All funds are committed immediately, using FY 2013 Navy aircraft budgets.

Work will be performed in New River, NC (86%), and Miramar, CA (14%), and is expected to be complete in September 2016. The Naval Air Warfare Center Training Systems Division in Orlando, FL manages the contract (N00019-12-G-0006, DO 0026).

Sept 23/14: Support. A $36.6 million contract modification for the repair of various V-22 parts, including the Prop-Rotor Gearbox and HUB Assembly. Funds will be committed as required, using FY 2014 Navy budgets.

Work will be performed in Hurst, TX, and is expected to be complete no later than Sept 30/15. One company was solicited for this non-competitive requirement in accordance with 10 U.S.C.2304 (c)(1), and 1 offer was received by NAVSUP Weapon Systems Support in Philadelphia, PA (N00383-14-D-039N, PO 0001).

Sept 11/14: Support. A $9.6 million firm-fixed-price, cost-plus-fixed-fee delivery order for one-time engineering involving the MV-22’s variable frequency generator-generator control unit update. All funds are committed immediately, using FY 2013 US Navy budgets.

Work will be performed in Tucson, AZ (56%); Philadelphia, PA (43%); and Amarillo, TX (1%), and is expected to be complete in March 2017 (N00019-12-G-0006, DO 0109).

Sept 9/14: Support. A $9.5 million cost-plus-fixed-fee delivery order buys spare V-22 flight display components, building up a stock of components that are no longer easily available due to production closeouts and material shortages. All funds are committed immediately, using FY 2013 Navy budgets.

Work will be performed in Philadelphia, PA, and is expected to be complete in December 2016 (N00019-12-G-0006, DO 0061).

Sept 17/14: Engines. Rolls Royce seems to be taking the threat of an engine switch (q.v. Sept 1/14) seriously. Their latest release touts modifications that improve performance 17% at the US military’s standard challenge limit of 6,000 foot hover out of ground effect in lift-sapping 95F degree temperatures.

They also tout $90 million in ongoing investments under their MissionCare support costs by the hour deal. Reducing maintenance costs per flight hour by 34% since 2009 is very good for the firm’s bottom line under that scenario. Whether it’s at a level the US military would call good, of course, depends on its absolute price. As a hedge, Rolls Royce can also point to 730 AE-1107C engines delivered, ground tests that have demonstrated potential upgrades to over 8,800 shp, and the MT7 engine derivative’s role in the US Navy’s forthcoming SSC hovercraft. Sources: Rolls Royce, “V-22 flight tests validate ‘hot and high’ capability for Rolls-Royce AE 1107C engines”.

Sept 3/14: Engine support. Rolls-Royce Corp. in Indianapolis, IN receives a $10.1 million firm-fixed-price contract modification for AE1107C MissionCareTM support, including “lower power engine removals and repairs.” All funds are committed immediately, using FY 2014 US Navy O&M budgets.

Work will be performed in Oakland, CA (70%), and Indianapolis, IN (30%), and is expected to be complete in February 2015. US Navy NAVAIR in Patuxent River, MD manages the contract (N00019-10-C-0020).

Sept 1/14: Engine alternative? The Pentagon is still looking into alternatives to the V-22’s Liberty engine, but that has been true for years (q.v. March 8/10). The Wall Street Journal:

“The V-22 Program is continually investigating ways to reduce the life cycle costs of the aircraft,” the U.S. Navy, which manages the program, said in an email. “Knowing that more than 90% of the operational use of the V-22 is in the future, coupled with budget pressures, it is prudent to investigate alternatives to existing systems and the engine is no exception.”

The catch? The engine has to be fully retrofittable into the V-22, with minimal to no impact on the V-22’s physical characteristics, and equal or better performance, without costing more. One imagines that the Pentagon would have a candidate already, if that combination was easy to find. Lesson: if you need non-standard power output levels, for a totally different airframe concept, it’s going to be tough to replace. Sources: WSJ, “Rolls-Royce Under Threat for Osprey Engine Deal” [subscription].

Aug 28/14: MV-22 ECM. A $21.4 million cost-plus-fixed-fee delivery order for non-recurring engineering in support of the “MV-22 Integrated Aircraft Survivability Equipment Universal Urgent Needs Statement Effort.” This order helps fund initial steps toward replacing the missile warning system and radar warning receiver system, and upgrades the capabilities of the countermeasures control system and associated software. All funds are committed immediately, using FY 2014 US Navy procurement budgets.

AFSOC is already rolling with something like that for its CV-22s (q.v. Aug 1/14).

Work will be performed in Ridley Park, PA (86%); Fort Walton Beach, FL (4%); Hurst, TX (2%); Salisbury, MD (2%); and various locations throughout the United States (6%), and is expected to be complete in April 2016 (N00019-12-G-0006, #0096).

Aug 1/14: CV-22 ECM. Exelis, Inc. in Clifton, NJ receives a $190 million indefinite-delivery/ indefinite-quantity contract to provide AN/ALQ-211 Suite of Integrated Radio Frequency Countermeasure components and related services, on behalf of the Technology Applications program office and CV-22 program office. The contract has a 5-year base period and a 3-year incentive award period, with $8.6 million committed immediately for the 1st task order from FY 2014 US SOCOM O&M funds.

The CV-22 uses the ALQ-211v2 variant; US SOCOM also uses this system in its MH-60 (ALQ-211v7) and MH-47 (ALQ-211v6) helicopters, and each platform has a slightly different mix of components and capabilities. The V-22 has slightly weaker jamming, for instance.

Work on the base contract will continue until July 30/19, and individual task orders will be funded with operations and maintenance or procurement appropriations under the appropriate fiscal year. This contract was a not competitively procured by US Special Operations Command in Tampa, FL, in accordance with FAR 6.302-1 (H92241-14-D-0006). See also: Exelis, AN/ALQ-211 brochure [PDF].

July 29/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives a $29.1 million firm-fixed-price contract modification, buying Mission Care support by the hour for the V-22’s AE1107C engine, including flight hours, and lower power engine removals and repairs. All funds are committed immediately, using FY 2014 Navy, USAF, and SOCOM O&M budgets.

Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and is expected to be complete in February 2015 (N00019-10-C-0020).

July 22/14: Upgrades. A $69.7 million cost-plus-fixed-fee delivery order covers Phase II non-recurring engineering of the V-22’s Improved Inlet Solution (IIS). It includes completion of preliminary and critical design reviews; installation of an IIS retrofit kit for installation on a CV-22 aircraft for demonstration and operation; installation of aircraft instrumentation to support flight test analysis; flight and qualification testing of the IIS design; and removal of the instrumentation from the test aircraft following flight testing. $31.3 million un FY 2014 USAF and US Navy RDT&E funds is committed immediately.

Work will be performed Amarillo, TX (73%), and Philadelphia, PA (27%), and is expected to be complete in December 2018. This delivery order combines purchases for the USAF ($41.8 million / 60%) and the U.S. Navy ($27.9 million / 40%). US NAVAIR in Patuxent River, MD manages the contract (N00019-12-G-0006, 0073).

July 21/14: Japan. Defense Minister Itsunori Onodera confirms that the 17 MV-22s Japan plans to buy over the next 5 years (q.v. Dec 14/13) will be stationed at Saga city’s commercial airport in northwestern Kyushu. This keeps the Ospreys close to Sasebo in Nagasaki Prefecture, which will hold Japan’s planned amphibious force. Saga will also be usable by the US Marines when the MV-22s from MCAS Futenma conduct training, exercises, or operations in mainland Japan. Sources: Asahi Simbun, “SDF to deploy 17 Osprey aircraft at Saga Airport”.

July 8/14: Upgrades. A $14.6 million cost-plus-fixed-fee delivery order for research, engineering and technical analysis “of new capabilities of the V-22 aircraft.” It combines USAF ($8.8 million / 60%) and US Navy ($5.9 million / 40%), and $2.1 million in FY 2014 R&D funding is committed immediately.

Work will be performed at Ridley Park, PA (55%) and Fort Worth, TX (45%), and is expected to be complete in June 2019 (N00019-12-G-0006, DO 0089).

June 12/14: Support. Small business qualifiers Form Fit and Function, LLC in Patterson, NJ wins a $9.8 million firm-fixed price, indefinite-delivery/ indefinite-quantity contract to manufacture “peculiar support equipment” for the V-22: hub and blade stands, blade trailer adapters, restraint tools, and actuators. $1.8 million in FY 2012 and FY 2013 USAF/ US Navy aircraft procurement budgets is committed immediately.

Work will be performed in Patterson, NJ, and is expected to be complete in June 2017. This contract was competitively procured via a HUB Zone set-aside electronic RFP, and 4 offers were received by the US Naval Air Warfare Center Aircraft Division in Lakehurst, NJ (N68335-14-D-0024).

June 4/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives a $9.5 million firm-fixed-price contract modification to a previously awarded for 13 MV-22 “low power engine repairs” under the Mission Care contract. All funds are committed immediately, using FY 2014 O&M budgets.

Work will be performed in Oakland, CA, and is expected to be complete in February 2015 (N00019-10-C-0020).

May 22/14: Mods. Briefings at the annual SOFIC conference indicate that SOCOM is looking at a limited set of new options for its CV-22s. SOCOM’s V-22/C-130 program director Lt. Col. John DiSebastian says that they can’t afford $50 million to refit 50 CV-22s, but “if you’ve got a $100,000 or a $50,000 widget that can improve the sustainment, capability, or ops of the aircraft, then bring that to us.”

Some CV-22s got shot up during a mission over South Sudan (q.v. Dec 21/13), prompting SOCOM to start adding additional armoring. They’re also looking at a forward-firing gun that would be simpler than the retractable 7.62mm IDWS, and pack more punch. Sources: Gannett’s Air Force Times, “SOCOM soon getting more capable, deadlier Ospreys and C-130s”.

May 6/14: ECM. Northrop Grumman Systems Corp. in Rolling Meadows, IL receives $18 million for cost-plus-fixed-fee delivery order for one-time engineering in support of the MV-22 Integrated Aircraft Survivability Equipment Suite upgrade. This includes integration of AN/AAQ-24(V)25 LAIRCM software with an electronic warfare controller and with the MV-22 mission computer.

$7.8 million in FY 2014 Navy aircraft procurement funds are committed immediately. Work will be performed in Rolling Meadows, IL and is expected to be completed in April 2016. US NAVAIR in Patuxent River, MD manages the contract (N00019-10-G-0004, 0506).

May 5/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives an $8 million firm-fixed-price contract modification for CV-22 Mission Care engine support, including AE1107C lower power engine removals.

All funds are committed, using FY 2014 O&M budgets, all of which will expire on Sept 30/14. Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and is expected to be complete in February 2015. US NAVAIR in Patuxent River, MD manages the contract (N00019-10-C-0020).

April 8/14: Israel. Israel is opting for a deferred payment plan (DPP) to purchase a range of new military equipment, including its V-22s (q.v. Jan 14/14).

“The Defense News report quotes US and Israeli officials saying Israel would only pay interest and fees until the current military aid package expires in September 2018, while the principal on the loan would be covered by a new aid package promised by President Barack Obama, which would extend the annual foreign military financing (FMF) aid until 2028.”

Sources: yNet News, “New deal to purchase V-22s relies on future US aid”

April 1/14: Support. Hamilton Sundstrand Corp. in Rockford, IL receives a $7.4 million firm-fixed-price delivery order for repairs of the V-22 Osprey’s aircraft constant frequency generator, which is part of the electrical power system.

All funds are committed immediately, using FY 2014 Navy budgets. Work will be performed in Rockville, IL, and is expected to be complete in September 2016. US Naval Supply Systems Command Weapon Systems Support in Philadelphia, PA manages the contract (N00383-12-D-011N, DO 7006).

March 26/14: Engines support. Rolls-Royce in Indianapolis, IN receives a $39.6 million firm-fixed-price contract modification for 26,495 V-22 flight hours and 26 low power MV-22 repairs under the existing Mission Care contract.

All funds are committed immediately, and expire on Sept 30/14. Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and is expected to be complete in February 2015. US Naval Air Systems Command, Patuxent River, MD, is the contracting activity (N00019-10-C-0020).

March 4-11/14: FY15 Budget. The US military slowly files its budget documents, detailing planned spending from FY 2014 – 2019. Bell and Boeing worked hard to get a multi-year deal signed before sequestration, so that their orders would be locked in. That is holding true, see charts in this article.

AFSOC appears to be set to stop 2 CV-22s short of its planned 52, however, ordering just 51 including 1 loss replacement. The USMC will continue buying another 15 or so from FY 2020 onward, but the V-22 needs to win the US Navy Carrier On-board Delivery plane competition to keep things going much longer after that. Sources: USN, PB15 Press Briefing [PDF] | USAF, Fiscal Year 2015 Budget Overview.

March 7/14: A $76.1 million modification to Lot 17-21’s fixed-price-incentive-fee multiyear contract exercises an option for 1 USAF CV-22 tiltrotor aircraft.

All funds are committed immediately, using FY14 USAF & SOCOM budgets. Work will be performed in Fort Worth, TX (24.6%); Ridley Park, PA (19.2%), Amarillo, TX (10.4%), Dallas, TX (4.3%); East Aurora, NY (2.5%); Park City, Utah (1.7%); El Segundo, CA (1.3%); Endicott, NY (1%); Ontario, Canada (0.9%); Tempe, AZ (0.8%); Rome, NY (0.7%); Torrance, CA (0.7%); Luton, United Kingdom (0.6%); Clifton, N.J. (0.6%); Salisbury, MD (0.6%); Los Angeles, CA (0.6%); Cobham, United Kingdom (0.6%); Irvine, CA (0.6%); San Diego, CA (0.5%); Yakima, WA (0.5%); Brea, CA (0.5%); Rockmart, GA (0.5%); McKinney, TX (0.4%); Albuquerque, NM (0.4%); Whitehall, MI (0.4%); Wolverhampton, United Kingdom (0.4%); Tucson, AZ (0.4%); Erie, PA (0.3%); Vergennes, VT (0.3%); Kilgore, TX (0.3%); Shelby, NC (0.3%); Avon, OH (0.2%); Santa Clarita, CA (0.2%); Garden City, NY (0.2%); El Cajon, CA (0.2%); Corinth, TX (0.2%); Sylmar, CA (0.2%); Westbury, NY (0.1%); and various other locations inside and outside the United States (21.8%), and is expected to be complete in December 2016 (N00019-12-C-2001).

1 CV-22

March 4/14: FY15 Budget. The USAF and USN unveil their preliminary budget request briefings. They aren’t precise, but they do offer planned purchase numbers for key programs between FY 2014 – 2019.

Total V-22 buys will be unaffected, even as key programs like the P-8 sea control aircraft and its MQ-4C Triton UAV companion are cut back and delayed. This is to be expected, given the reality of an existing multi-year contract. The only real savings would have involved cutting the 4 MV-22s per year in FY 2018 and 2019. That doesn’t help in 2015, and applies to the Marines rather than the Navy. Source: USN, PB15 Press Briefing [PDF] | USAF, Fiscal Year 2015 Budget Overview.

Feb 28/14: Support. A $351 million cost-plus-incentive, fixed-price incentive-fee contract modification for V-22 Joint Performance Based Logistics support.

Funds will be committed as individual delivery orders are issued. Work will be performed in Fort Worth, TX (40%); Ridley Park, PA (40%); various locations within the continental United States (15%) and locations outside the continental United States (5%), and is expected to be complete in November 2016 (N00019-09-D-0008).

Feb 28/14: Engines. Rolls-Royce in Indianapolis, IN receives an $8 million firm-fixed-price contract modification for 11 low power CV-22 repairs under the Mission Care? engine contract.

All funds are committed, using USAF FY 2014 O&M budgets. Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and is expected to be complete in February 2015 (N00019-10-C-0020).

Feb 25/14: Support. Raytheon Co. in McKinney, TX receives $14.3 million for firm-fixed-price delivery order under a previously awarded Basic Ordering Agreement for various quantities of repair parts to support the H-53 and V-22 aircraft.

All funds are committed immediately. Work will be performed in Jacksonville, FL, and is expected to be complete by Feb 28/16. The contract was not competitively procured in accordance with FAR 6.302-1, and is managed by US NAVSUP Weapon Systems Support in Philadelphia, PA (N00383-11-G-003D, 7008).

Feb 12/14: HV-22 COD? Vice Adm. David Buss, commander Naval Air Forces, says that the service is about a year away from picking their replacement Carrier Onboard Delivery aircraft to replace the C-2 Greyhounds. “We’re still culling through all the data and very much in the [analysis of alternatives] process.” The problem of what to do with the F-35B/C fleet’s F135 engines is especially vexing, as the V-22 can’t carry a whole engine, and it isn;t likely that a C-2D could, either. Yet the F-35’s status as the Navy’s future fighter makes that a critical piece of cargo. Sources: USNI, “WEST: Decision on New Carrier Supply Plane ‘About a Year Away'”.

Jan 30/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives a $90.2 million contract modification from the USMC, exercising an option for 40 AE1107C engines on the production line (20 MV-22s).

All funds are committed immediately, using USN FY 2013-2014 aircraft budgets. Work will be performed in Indianapolis, IN, and is expected to be complete in November 2015 (N00019-12-C-0007).

Jan 30/14: Support. A $10.3 million cost-plus-incentive-fee contract modification for more MV-22 and CV-22 Joint Performance Based Logistics support.

All funds are committed immediately, using SOCOM, USAf, and Navy budgets. Work will be performed in Amarillo, TX (50%) and Philadelphia, PA (50%), and is expected to be complete in February 2014. The Naval Air Systems Command, Patuxent River, Md., is the contracting activity (N00019-09-D-0008).

Jan 28/14: DOT&E Testing Report. The Pentagon releases the FY 2013 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The Special Forces CV-22 is their focus this year. As of Aug 13/13, 34 of 50 CV-22 aircraft have been fielded, but it has a serious issue to address.

2008 had revealed serious shortfalls in the Block 5 Suite of Integrated Radio Frequency Countermeasures (SIFRC) defensive system. They included serious reliability issues, inaccurate and late threat awareness, and limited countermeasure effectiveness against some threats. That won’t do, so the USAF modified SIRFC with new, higher-power transmitters, cabling, radio-frequency switches, antennas, and Block 7 operational flight software.

SIFRC Block 7 improves awareness, and offers some reliability improvements, but the other issues remain. Electronic countermeasures are no better than Block 5. The decoy countermeasures dispenser has to be triggered manually, because the automatic mode doesn’t work. The system also persists in “blue screen of death” computer system crashes, which require reboots. You’d rather not be shot at just then. The DOT&E’s overall verdict was that the CV-22 is survivable with the SIFRC Block 7 system, if correct tactics and procedures are used, but they’d still like to see these things fixed.

AFSOC also switched the GAU-21 (FN M3M) .50 caliber machine gun for the lightweight GAU-18 M2 variant on the rear ramp, which improved reliability. Antennas were also switched about, after 2008 tests showed radio communications limits that were unreliable even within 0.5 nmi of ground troops. FY 2013 testing went better, and radio communication with ground troops extended to 25 nmi, and aircraft extended from 5 nmi to 120 nmi.

DOT&E report

Jan 15/14: Support. A $26.7 million cost-plus-fixed-fee, cost reimbursable delivery order for on-site V-22 flight test management, flight test engineering, design engineering, and related efforts to support the US Navy’s Rotary Wing Aircraft Test Squadron.

All funds are committed immediately, using USN FY 2013 procurement and FY 2014 R&D dollars. Work will be performed at Patuxent River Naval Air Station, Patuxent River, MD (53%); Philadelphia, PA (32%); and Fort Worth, TX (15%), and is expected to be complete in December 2014 (N00019-12-G-0006, DO 0067).

Jan 15/14: Engines. Rolls-Royce Corp. in Indianapolis, IN receives a $13.6 million firm-fixed-price contract modification to provide 17,226 MV-22 engine flight hours. The maintenance and work required to keep the fleet in shape for that is their problem.

All funds are committed immediately, using FT 2014 Navy O&M funds. Work will be performed in Oakland, CA (70%) and Indianapolis, IN (30%), and the Pentagon days that it “is expected to be complete in November 2013″. Looks like they’re paying for a past period? (N00019-10-C-0020).

Jan 14/14: Israel. The US DSCA announces Israel’s official request for up to 6 “V-22B Block C Aircraft” for search and rescue and special operations roles. MV-22B Block Cs are the USMC’s most modern variant, though the notice carefully avoids specifying either USMC MV-22s or SOCOM CV-22s. The request could be worth up to $1.3 billion, and includes:

16 Rolls Royce AE1107C Engines (12 + 4 spares)

6 AN/APR-39 Radar Warning Receiver Systems

6 AN/ALE-47 Countermeasure Dispenser Systems

6 AN/AAR-47 Missile Warning Systems

6 AN/APX-123 Identification Friend or Foe Systems

6 AN/ARN-153 Tactical Airborne Navigation Systems

6 AN/ARN-147 Very High Frequency (VHF) Omni-directional Range (VOR) Instrument Landing System (ILS) Beacon Navigation Systems

6 AN/APN-194 Radar Altimeters

6 Multi-Band Radios

6 AN/ASN-163 Miniature Airborne Global Positioning System (GPS) Receivers (MAGR)

36 AN/AVS-9 Night Vision Goggles

Plus a Joint Mission Planning System, support and test equipment, software, repair and return, aircraft ferry services and tanker support, spare and repair parts, technical documentation, personnel training and training equipment, and other forms of US Government and contractor support.

Previous assurances (q.v. Oct 31/13) mean that Israel will receive 6 V-22 Block Cs out of the next order lot, pushing out USMC acquisitions. Israel eventually chooses to finance this and other purchases with a Deferred Payment Plan (q.v. April 8/14).

The principal contractors involved with this proposed sale will be the Bell and Boeing joint venture in California, MD, with final aircraft assembly occurring in Amarillo, TX. Implementation of this proposed sale will require up to 30 US Government or contractor representatives in Israel on a temporary basis for program technical support and management oversight. Sources: US DSCA #13-73 | Defense News, “Pentagon Advances V-22 Sale to Israel” | Motely Fool, “Pentagon Swipes V-22 Ospreys From U.S. Marines, Sells Them to Israel Instead” (refers to Oct 31/13 entry info).

DSCA request: Israel (6)

Dec 23/13: Upgrades. An $9 million cost-plus-fixed-fee, firm-fixed-price contract exercises an option for 2 V-22 Block A to Block B 50-69 series upgrade kits.

All funds are committed immediately, using FY 2014 Navy procurement budgets. Work will be performed in Philadelphia, PA (60%) and Fort Worth, TX (40%), and is expected to be complete in November 2015 (N00019-13-C-0021).

Dec 21/13: Operations. Defense News reports:

“US aircraft flown into South Sudan to help with evacuation efforts on Saturday came under fire, wounding four US servicemen…. US and Ugandan officials said three US military aircraft that were trying to land at Bor, a rebel-held city in Jonglei state [South Sudan], were fired on and forced to return to neighboring Uganda with one of the aircraft hit and leaking fuel.”

The sources that said the planes were CV-22s turn out to be right, and SOCOM later decides that some additional armoring might be a good idea. Sources: Defense News, “US Aircraft Attacked, Fighting Escalates In South Sudan”.

Dec 17/13: Infrastructure. The Watts Contrack joint venture in Honolulu, HI receives a $57.1 million firm-fixed-price contract to build an MV-22 hangar, infrastructure and aircraft staging area for one MV-22 squadron at Marine Corps Base Hawaii. Work includes a multi-story type II modified high bay aircraft maintenance hangar that uses a steel frame and metal roof, along with a 2nd story administrative space. Other primary and supporting facilities include an aircraft taxiway with shoulders, a 12-plane staging area, a Substation No. 3 feeder upgrade, and utility infrastructure. This will require earthwork in advance, and paving and site improvements include site storm drainage systems and taxiway shoulders. An unexercised option could raise the cumulative contract value to $59 million.

All funds are committed immediately, using 2010, 2011 & 2013 construction. This contract was competitively procured via Navy Electronic Commerce Online, with 9 proposals received by NAVFAC Pacific in Pearl Harbor, Hawaii (N62742-14-C-1327).

Dec 14/13: Japan. Japan’s new 5-year FY 2014-2019 defense plan includes 17 MV-22s, as well as 3 Global Hawks. All will be bought outside the USA’s multi-year procurement term, pending Japanese cabinet approval and certain American export clearance.

This is somewhat amusing after the protests over American stationing of MV-22s in Japan, but Chinese aggressiveness around some of Japan’s more remote territories is pushed the Japanese to set up a force of Marines. The MV-22s are meant to offer them rapid mobility. Sources: Asahi Shimbun, “A lot of new equipment purchases in latest 5-year defense plan” | FY11-15 MTDP [PDF].

ANVIS/HUD-24
click for video

Dec 6/13: ECP – HMD. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded a $15.6 million firm-fixed-price delivery order for additional engineering and technical support. They need to forward fit/retrofit Engineering Change Proposal #1007 into the V-22, and the contract also includes 8 helmet mounted display retrofit kits, spares, support equipment, tooling, and training devices. All finding is committed immediately, using FY 2013 US SOCOM budgets.

The V-22 uses Elbit Systems’ ANVIS/HUD helmet mounted displays, and SOCOM’s CV-22s use a new variant with color symbology (q.v. Sept 6/11). Work will be performed at Ridley Park, PA (99.9%), and Fort Worth, TX (0.1%), and is expected to be complete in March 2015 (N00019-12-G-0006, DO 0075).

Oct 31/13: Israel. US Secretary of Defense Chuck Hagel confirms (see April 22/13 entry):

“Tonight, I am pleased to announce that we are working with the Israeli government to provide them with six new V-22s. I have directed the Marine Corps to make sure that this order is expedited. That means Israel will get six V-22s out of the next order to go on the assembly line, and they will be compatible with other IDF capabilities.”

From Hagel’s speech it can be inferred that these are MV-22s in the process of being modified for integration with Israeli systems. Israel had shown increasing interest in the rotorcraft during the last 2 years, so this 1st export is not surprising. Japan will be a tougher sell. Sources: US DoD.

FY 2013

RO-RO tanker test.

CV-22 washing
(click to view full)

Sept 25/13: Training. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded $20.5 million for cost-plus-fixed-fee delivery order to upgrade the existing 15 Marine Corps MV-22 and 8 USAF CV-22 training devices; they’ll be upgraded to MV-22 Block C2.02 and CV-22 Block 20.2.01 configuration.

All funds are committed immediately, using FY 2012 & 2013 budgets. Work will be performed at the Amarillo, TX (63.5%), Chantilly, VA (29%), and Broken Arrow, OK (7.5%), and is expected to be complete in September 2016. The Naval Air Warfare Center’s Training Systems Division in Orlando, FL manages the contract (N00019-12-G-0006, #0026).

Sept 25/13: ECM. Bell-Boeing Joint Project Office, Amarillo, TX, is being awarded a $9.5 million cost-plus-fixed-fee modification, for non-recurring engineering and flight test aircraft modifications to incorporate the Joint Allied Threat Awareness System (JTAS) and the APR-39D(V)2 radar warning receiver into the MV-22 Osprey aircraft. JATAS detects lasers and incoming fire, and is a standard for modern Navy rotorcraft. The APR-39 detects radar emissions, and is used on a wide range of US military planes.

$5.2 million in FY 2012 & 2013 RDT&E funds are committed immediately. Work will be performed in Ridley Park, PA (98.7%); St. Louis, MO (1.1%); and El Paso, TX (0.2%), and is expected to be completed in March 2016. US Naval Air Systems Command in Patuxent River, MD manages the contract (N00019-07-G-0008). See also ATK JATAS page | DID re: APR-39.

Sept 5/13: RO-RO Aerial Tanker. The Bell Boeing V-22 Program announces a successful initial test of a roll-on aerial tanker system for the V-22 Osprey. Once it’s loaded in, it extends the refueling hose out a partially-open back ramp to refuel helicopter and aircraft. That kind of system has obvious uses for Special Forces CV-22s, and the US Marines will find a ship-based aerial refueling capability extremely useful. So would the US Navy, which has allowed this capability to shrink with the retirement of its A-6 Intruder and S-3 Viking aircraft fleets. Success could create another argument in favor of the HV-22 as the next naval cargo aircraft (COD, q.v. June 20/13), but it would be used in place of Super Hornets for refueling aircraft near the carrier. Serious refueling capability for fighter jets may require more capacity and range than the V-22 can usefully provide.

The August 2013 demonstration over north Texas used F/A-18C and F/A-18D Hornet fighters, and only tested the V-22 system’s ability to perform on command and maintain stable hose positions. Future tests will involve graduated stages, leading to connections with receiver aircraft and then active refueling. Sources: Boeing and Bell Helicopter’s Sept 5/13 releases.

Aug 22/13: Support. Rolls-Royce in Indianapolis, IN receives a $10.8 million to a previously awarded firm-fixed-price contract modification for 11 low power repairs (see above) to AE1107 turboshaft engines, and 2 months of mission care site support, for the HMX-1 VH-22s in Quantico, VA.

Those are the new Presidential V-22s, which received so many headlines recently for being used to take the President’s dog Bo on vacation. Not to mention 2 bags of basketballs. They aren’t used to carry the President, so if you ever get a ride on one, just remember that they’re carrying you instead of basketballs.

All funds are committed immediately. Work will be performed in Oakland, CA (70%); Indianapolis, IN (20%); and Quantico, VA (10%), and is expected to be complete in February 2014. US Naval Air Systems Command in Patuxent River, MD manages the contract (N00019-10-C-0020). Sources: Boston Globe, “Obamas arrived on Martha’s Vineyard” | Washington Times, “Dog days of summer: Bo Obama flies on Osprey to Martha’s Vineyard vacation”.

Aug 21/13: Japan. Japan is looking to create a small force of Marines to protect its outlying islands, in an expansion of the Western Army’s Infantry Regiment. A preparatory force is being set up, and Japan reportedly plans to equip the final force with MV-22 Ospreys.

The MV-22B has been very controversial in Okinawa (q.v. September 2012 entry), which isn’t happy to have the Marines in general. A role in the defense of Japan’s outlying Islands will help change the V-22’s perception in Japan as a whole, and Japan plans to buy early. It will take a while for the new unit to learn how to fly and use the Ospreys, and they’ll want to be ready by the time the unit is officially activated. A sharp jump in the YEN 8 million ($80,000) budget to research V-22 integration into the JSDF will be the 1st step. Sources: Asahi Shinbun, “Defense Ministry preparing Japanese version of U.S. Marines”.

Aug 16/13: Support. The Bell-Boeing Joint Project Office in Amarillo, TX receives a maximum $43 million delivery order for prop rotor gearboxes, under a firm-fixed-price, sole-source Navy contract.

There was 1 solicitation with 1 response. Work will be performed until December 2017. The US Defense Logistics Agency Aviation in Philadelphia, PA manages the contract (SPRPA1-09-G-004Y, DO 6125)

June 24/13: Engines. Rolls-Royce in Indianapolis, IN receives a $7.1 million firm-fixed-price contract modification for “additional engineering services for up to 9,253 [engine] flight hours for the MV-22 fleet aircraft in support of Operation Enduring Freedom and the east and west coast Marine Expeditionary Units deployments.”

Work will be performed in Oakland, CA (70%), and Indianapolis, IN (30%), and is expected to be complete in November 2013. All funds are committed immediately from a combination of regular and OCO war supplemental budgets, and it will all expire on Sept 30/13 (N00019-10-C-0020).

June 27/13: +1 MV-22. A $60.2 million modification adds 1 MV-22 to the fixed-price-incentive-fee Lot 17 – 21 multiyear contract, using the FY 2013 funds under the Variation in Quantity clause. All funds are committed immediately.

Work will be performed in Fort Worth, TX (24.6%); Ridley Park, PA (19.2%); Amarillo, TX (10.4%); Dallas, TX (4.3%); East Aurora, NY (2.5%); Park City, UT (1.7%); El Segundo, CA (1.3%); Endicott, NY (1%); Ontario, Canada (0.9%); Tempe, AZ (0.8%); Rome, NY (0.7%); Torrance, CA (0.7%); Luton, United Kingdom (0.6%); Clifton, NJ (0.6%); Salisbury, MD (0.6%); Los Angeles, CA (0.6%); Cobham, United Kingdom (0.6%); Irvine, CA (0.6%); San Diego, CA (0.5%); Yakima, WA (0.5%); Brea, CA (0.5%); Rockmart, GA (0.5%); McKinney, TX (0.4%); Albuquerque, NM (0.4%); Whitehall, MI (0.4%); Wolverhampton, United Kingdom (0.4%); Tucson, AZ (0.4%); Erie, PA (0.3%); Vergennes, Vt. (0.3%); Kilgore, TX (0.3%); Shelby, NC (0.3%); Avon, OH (0.2%); Santa Clarita, CA (0.2%); Garden City, NY (0.2%); El Cajon, CA (0.2%); Corinth, TX (0.2%); Sylmar, CA (0.2%); Westbury, NY (0.1%); and various other locations inside and outside the United States (21.8%). The contract runs until November 2016 (N00019-12-C-2001).

1 extra MV-22

June 20/13: HV-22? The US Navy’s Analysis of Alternatives for the Carrier Onboard Delivery (COD) fleet cargo role will lead to an RFP in late 2014, with a contract award planned for FY 2016. The V-22 reportedly did better than the Navy had expected in the initial AoA analysis, and is now expected to be a strong competitor.

Northrop Grumman will be offering a much cheaper option: remanufacture and upgrade the existing 35-plane C-2 fleet, incorporating technologies from the derivative E-2D Hawkeye AWACS plane that’s just beginning to roll off Florida production lines. The new C-2s would have remanufactured fuselages and wings, with the E-2D’s improved engines and propellers, cockpit, and avionics. The goal would be a service life extension from 2028 to 2048, for much less than the $78 million average flyaway cost of a V-22, and lower operating costs.

The original V-22 program had the Navy ordering 48 “HV-22″ Ospreys for duties like search and rescue, but heavy downwash, technical problems, and high costs led them to assign HV-22 roles to the MH-60S Seahawk helicopter instead. The COD competition offers the V-22 a second crack at a Navy contract, and they’ll be touting an HV-22’s ability to deliver to each ship in the fleet, instead of offloading onto a carrier for helicopter delivery to individual ships. NDIA National Defense.

<di