2016-11-18



KC-135: Old as the hills…

(click to view full)

DID’s FOCUS articles cover major weapons acquisition programs – and no program is more important to the USAF than its aerial tanker fleet renewal. In January 2007, the big question was whether there would be a competition for the USA’s KC-X proposal, covering 175 production aircraft and 4 test platforms. The total cost is now estimated at $52 billion, but America’s aerial tanker fleet demands new planes to replace its KC-135s, whose most recent new delivery was in 1965. Otherwise, unpredictable age or fatigue issues, like the ones that grounded its F-15A-D fighters in 2008, could ground its aerial tankers – and with them, a substantial slice of the USA’s total airpower.

KC-Y and KC-Z buys are supposed to follow in subsequent decades, in order to replace 530 (195 active; ANG 251; Reserve 84) active tankers, as well as the USAF’s 59 heavy KC-10 tankers that were delivered from 1979-1987. Then again, fiscal and demographic realities may mean that the 179 plane KC-X buy is “it” for the USAF. Either way, the KC-X stakes were huge for all concerned.

In the end, it was Team Boeing’s KC-767 NexGen/ KC-46A (767 derivative) vs. EADS North America’s KC-45A (Airbus KC-30/A330-200 derivative), both within the Pentagon and in the halls of Congress. The financial and employment stakes guaranteed a huge political fight no matter which side won. After Airbus won in 2008, that fight ended up sinking and restarting the entire program. Three years later, Boeing won the recompete. Now, they have to deliver their KC-46A.

Boeing’s KC-46A, and Its Team



KC-46A concept

(click to view full)

KC-46A Pegasus production takes place in 2 phases: the 767-2C, and then the militarized KC-46A modifications.

There are still a number of things we don’t know, though more details have emerged since Boeing won the competition. The first step is to build a 767 on the commercial production line with a cargo door and freighter floor, an advanced flight deck display borrowed from its new 787, body tanks, and provisions for aerial tanker systems. Initial Boeing graphics featuring upturned winglets on the wingtips are no longer part of the design, but Pratt & Whitney’s 62,000 pound thrust PW4062s remain their engine choice. This is the 767-2C, and it receives an FAA 767 amended Type Certificate.

The 767-2C is militarized in a separate finishing center by adding aerial refueling equipment, an air refueling operator’s station that includes panoramic 3-dimensional displays, and threat detection/ countermeasures systems. The resulting KC-46A receives an FAA 767 Supplemental Type Certificate given to substantially different variants, and must also receive USAF certification that clears the way for full acceptance.

Boeing’s refueling boom is derived from the KC-10’s AARB, but adds 3-D viewing and a slightly higher fuel offload rate of 1,200 gallons/min. The centerline and wing-mounted refueling pods will now come from Cobham plc’s Sargent Fletcher, who was also partnered with Airbus for this feature. Unlike the A330 MRTT’s systems, however, the KC-46A’s wing refueling pods still need to finish testing on the 776-2C. The USAF will buy 46 wing sets for its fleet, which will allow multi-aircraft (multipoint) aerial refueling when installed.

KC-46A cargo capacity lists as 65,000 pounds, in a mix of up to 18 cargo pallets, 114 passengers, and/or 58 medical stretcher slots.



Fielding a tanker built after the 1960s allows the USAF to include a number of new systems, which would be too costly to retrofit into the existing KC-135 fleet. The net effect is to make its KC-46As front-line refuelers. The cockpit and exterior lighting are night-vision compatible for covert rendezvous. Advanced communications and secure datalinks are big steps forward for the fleet, and their classified feeds will be used by specialized ESTAR and TCS systems designed to route the tanker away from threats. NBC (nuclear, biological, chemical) protection will allow the planes to operate in contaminated environments, while EMP hardening reduces the effects of high-frequency radiation bursts on all those new solid-state electronics. On a more prosaic level, radar warning systems, infrared defensive systems, cockpit armor, and fuel tank ballistic protection will all be welcome.

KC-46A Industrial Team

Boeing’s KC-X 1.0 Team

Boeing’s industrial team has slowly announced itself over many months since the award. American KC-46A content has been touted as high as 85%, with British firms picking up much of the balance. Boeing reportedly looked hard for supply chain savings in Round 2, though, in order to lose less money with its under-cost bidding strategy.

That KC-46A design is a big change from KC-X round 1, whose KC-767 Advanced used a 767-200ER fuselage; a 767-300F freighter wing, landing gear, cargo door and floor; and a 767-400ER’s flaps and flight deck (derived in turn from the 777). A new design fly-by-wire boom with remote viewing would expand the tanker’s effective refueling airspace, and offload more fuel. Engines would be 2 Pratt & Whitney PW4062s, with 62,000 pounds of thrust each, instead of the KC-767A/J’s 60,200 pound CF6-80C2s.

Some of the suppliers also changed, as Boeing progressed from the canceled KC-767 lease deal, to KC-X, to its final design in Round 2:

Boeing’s production line had also progressed. Near the end of the KC-X bidding, Boeing added civilian 767 orders to keep its production line going. That was enough to create a cushion if KC-X faced further challenges and issues, but the reality is that civilian 767 production looks set to end soon. The US military will soon become the 767 production line’s sole support.

KC-X: The Program

A March 2012 GAO report summed up the risk driving the KC-46A program, and the current state of the USAF’s tanker fleets:

“According to the Air Force, the national security strategy cannot be executed without aerial refueling… the KC-135 Stratotanker, is over 50 years old on average and costing increasingly more to maintain and support. With… more than 16,000 flight hours on each aircraft, the KC-135s will approach over 80 years of age when the fleet is retired as projected in the 2040 time frame. In 1981, the Air Force began supplementing its fleet of KC-135s with [59] KC-10s… that transport air cargo and provide refueling. Much larger than the KC-135, the KC-10 provides both boom and hose and drogue refueling capabilities[Footnote 4] on the same flight and can conduct transoceanic missions. The KC-10s now average about 27 years of age with more than 26,000 flight hours on each, and their service life is expected to end around 2045.”

The $7.2 billion October 2012 development cost estimate includes $4.9 billion for the aircraft development contract and 4 test aircraft, $0.3 billion for the aircrew and maintenance training systems, and $2 billion for other government costs and some risk funds. The total procurement cost estimate of $40.46 billion in base-year dollars buys 175 production aircraft, initial spares, and other support items as priced in contract options.

Cost estimates as of April 2014 are stable, with an estimated $1.6 billion to cover other government costs like program office support, test and evaluation support, contract performance risk, and other development risks. That includes the cost of test flights, which will sometimes feature operational military aircraft of various kinds to act as receivers.

An accompanying military construction estimate of $4.2 billion includes the projected costs to build aircraft hangars, maintenance and supply shops, and other facilities to house and support the full 175-plane KC-46 fleet at up to 10 main operating bases (McConnell AFB, KS is MOB1), 1 training base at Altus AFB, OK; and the Oklahoma City Air Logistics Complex depot.

The KC-46A Development Phase: Budgets, Splits, & Dates

KC-46 development

The Pentagon’s latest Selected Acquisition Report estimates a total KC-46A development cost of $5.615 billion, which would actually be $1.221 billion over the KC-X EMD phase’s original Target Cost of $4.394 billion. Fortunately for the USAF, they structured the contract so they can’t pay more than $4.7 billion, and the overall bid cost to the US government for development plus production remains below Airbus’ bid.

Here’s how it works:

Up to the $4.898 billion ceiling, the contract split for amounts over the $4.394 billion base price is 60/40. The difference is $504 million, so the government would pay $302.4 million ($4.696 billion total), and Boeing would pay about $201.6 million.

Costs above the $4.898 billion ceiling are all Boeing’s responsibility.

Current estimates show that there’s almost no chance of coming in under the ceiling. Boeing’s current cost estimate is $5.164 billion, which would raise its private liability for the cost increases to $467.5 million (201.6 + all 265.9 over the ceiling). If the government program manager is right, Boeing’s liability rises to $918.6 million (201.6 + all 717.0 over). The difference matters to Boeing, but the Pentagon doesn’t have to care which EMD Phase figure is correct, or how much higher EMD costs go. Their costs are set, at $4.7 billion, though actual dollars will be a bit higher due to inflation etc.

That’s if, and only if, the USAF doesn’t start asking for design changes. If they do, that would trigger a cycle of charges over and above the agreed contract.

As of December 2012, schedule planning looked like this:

Concurrence concerns

The USAF has maintained its Q4 FY 2015 (summer 2015) goal for a successful Operational Assessment and Milestone C decision, and this remains the official target. Success which would clear the way for 2 firm-fixed-price Low-Rate Initial Production (LRIP) lots to deliver the initial 19 aircraft. Full-Rate Production options would follow beginning in FY 2017 as a firm-fixed-price contract with some adjustments for outside circumstances, and a not-to-exceed cap. The USAF will be assessing the possibility of breaking out the engines as a separate government procurement in FRP, instead of having Boeing provide them.

As Airbus predicted when the contract was awarded, however, Boeing has admitted to trouble meeting these development milestones. The schedule will need to be changed, but there’s no official replacement schedule yet.

The schedule may need to incorporate other changes as well. The Pentagon’s own DOT&E testers have doubted proclaimed Initial Operational Test and Evaluation (IOT&E) dates (Q3 FY 2016 – Q1 2017) for some time. Beyond technical issues that have slowed the new design, testing must avoid revealing significant problems.

Initial Operational Capability (IOC) was pegged for August 2017, with Full Operational Capability (FOC) expected by August 2019, but USAF Air Mobility Command is no longer giving official target dates.

The program as a whole is expected to end by 2028.

The KC-46A Production Phase: Risks & Numbers

KC-10 & F/A-18C

The current program calls for Boeing to begin delivering KC-46As to the USAF by 2015. Unfortunately, the KC-46A is too different from previous KC-767A models sold to Japan and Italy, so it will need its own development, testing, and certification time. That’s why Airbus and program skeptics have always doubted that Boeing could deliver 18 certified, fully developed and tested planes by 2017. Boeing disputes this, but the Pentagon’s own DOT&E office added weight to those concerns in its 2011 reports, which declared the KC-46A’s test program “not executable.” That continues to be a concern.

Beyond basic integration and certification considerations, a March 2012 GAO report cites 6 key technical risks to the program:

1. Weight limits. The KC-46A is close to its limit, and any more growth will start to take away fuel capacity, while increasing fuel burn rate. As of December 2013, Boeing remains confident that they will remain under the maximum take-off weight of 204,000 pounds.

2. New wing refueling pods. The KC-46’s pods will be redesigned to reduce buffeting of the aircraft’s wing, and change the way the refueling hose exits the pod. Still a technical risk as of December 2013.

3. 3-D display for the boom operator.

4. Threat Correlation Software. Used to help plot safe routes, along with the…

5. ESTAR software.

6. ALR-69 Radar Warning Receiver integration. Issues like figuring out precise placement, and antenna design, make fitting a large aircraft more challenging than many people expect.

Problems with these or other systems could delay the program further, and some of these issues could also make certification harder or longer. Even so, the actual risk that set the development program back wasn’t any of these. It was the need to redesign certain wiring sections for military-grade shielding requirements and mandatory separation distances.

Meanwhile, the USAF plans to respond to continued budget cuts by removing their existing KC-10 heavy refuelers entirely, adding tremendous risk by removing their inherent boom/hose versatility, and leaving no tanker alternative if the KC-135s develop a serious problem.

Fleet Risks

Over the longer term, plotting even a 3-year production delay against planned deliveries and KC-135 retirements never drops the medium tanker fleet much below present levels. The initial drop is slight, and the same final figure is reached in 2030 instead of 2027. On the other hand, RAND’s 2006 Analysis of Alternatives for KC-X highlighted a very different risk, which needs to be understood:

“The current (December 2005) assessment of the flight-hour life of the KC-135 fleet and the expected future flying-hour programs together imply that these aircraft can operate into the 2040s. It cannot be said with high confidence that this is not the case, although there are risks associated with a fleet whose age is in the 80- to 90-year range. It can also not be said with high confidence that the current fleet can indeed operate into the 2040s without major cost increases or operational shortfalls, up to and including grounding of large parts of the fleet for substantial lengths of time, due to currently unknown technical problems that may arise. The nation does not currently have sufficient knowledge about the state of the KC-135 fleet to project its technical condition over the next several decades with high confidence.”

In English, nobody knows if an airplane fleet that’s already 50 years old will remain safe, or avoid unforeseen mechanical or structural problems, because there’s no previous example of what they’re trying to do. Those kinds of sudden “age-out” problems recently grounded the USAF’s F-15A-D fleet for several months, and led to the unexpected retirement of almost 1/4 of the fleet. If anything similar happens to the KC-135, the USAF’s planned number of aerial tankers may not resemble its actual future fleet.

This risk, and the potential absence of the KC-10, is exactly why the KC-X program has been the USAF’s #1 priority. On the other hand, it’s an equally good reason not to trust the USAF’s own rosy projections for its future fleet size. The graph below shows how this kind of scenario could play out. In DID’s hypothetical example, we used actual data to the present day, plus all planned reductions in the USAF’s 2011 plan. Fleet problems lead to the forced retirement of 1/3 of the remaining fleet in 2021 over safety and cost-to-fix issues, followed by a second mechanical issue or budget crisis that grounds another 55 planes in 2029. The KC-10 fleet is not part of this calculus at all.

The USA’s looming fiscal entitlements crisis will begin to bite in earnest post-2020, and the pattern of cuts in the USA and in other countries shows a marked tendency to simply retire platforms with significant maintenance costs. KC-135 per-hour flight costs are already increasing, and a fleet that also needed expensive refits or fixes would be a prime target for future cuts. Here’s what this scenario looks like:

Finally, DID believes that there will be no KC-Y or KC-Z, so the timing of KC-135 problems and retirements isn’t critical. Any serious problems in the KC-135 fleet could create a similar end-point, even if the drops happened after 2030.

KC-46A Export Prospects

IAI’s KC-767 MMTT

Once the KC-46As do enter service, they will join Italy’s KC-767A (4) and Japan’s KC-767J (4) small KC-767 fleets. Both customers have experienced long delivery delays while Boeing has worked to iron out technical problems, and their KC-767s will have a number of key differences from the KC-46A. Japan’s boom-equipped KC-767s were delivered form 2008-2010, but Italy’s aircraft with hose-and-drogue systems were only accepted in February 2011.

That’s one option, if Boeing will produce the planes.

The KC-46A’s schedule and dwindling civil 767 production are problematic for export orders, because the USAF will be Boeing’s sole focus until the EMD Phase is done in 2017 – or later. Countries that need aerial tankers before 2019-2020 will need to look elsewhere. Boeing declined to bid on India’s aerial tanker RFP, for instance. There’s also a customer commitment issue. Should customers accept the KC-767A, which is certified and in service, or wait for the KC-46A, and hope it’s on time?

Airbus sees this lock-up as an opportunity to add to its A330 MRTT customer list, of course, signing customers like India, Qatar, and Singapore. Ironically, the other big beneficiary may by Israel’s IAI Bedek, whose inexpensive KC-767 MMTT conversion of used Boeing freighters already has customers in Colombia and Brazil.

As of June 2013, Boeing was reportedly pursuing prospects for up to 20 aerial tanker exports. If so, they have been quiet pursuits. The next big opportunity will be in South Korea.

KC-X: Contracts & Key Developments

FY 2016

Boom assembly

November 18/16: Boeing is eager to sell its KC-46A aerial refueling tanker to India. The Indian Air Force has yet to procure a capability to refuel its C-17 and P-8I aircraft, and New Delhi has eyed up the Pegasus to fill such a role. A laborious search has been underway to fill a six multi-role tanker capability soon to be vacated by their aging IL-76 aircraft. Earlier attempts to procure Airbus A 330 MRTT never came to fruition.

September 23/16: The US State Department has cleared the sale of four KC-46A aerial refueling tankers to Japan in what is estimated to be a $1.9 billion deal. All aircraft will come equipped with Northrop Grumman’s AN/AAQ-24(V) Large Aircraft Infrared Countermeasures (LAIRCM) system. Tokyo first announced its intention to purchase the new tankers last October, with the recent approval from the Pentagon moving it closer to becoming the aircraft’s first foreign customer for manufacturer Boeing.

September 22/16: Gen. Carlton Everhart, head of the mobility command of the USAF has said that the number of KC-46 tankers the service is set to procure by 2028 are not enough. 179 units of Boeing’s latest tanker will be delivered; however between 2028 and 2035, no KC-46s are scheduled for delivery, leaving a capability gap. To remedy the issue, Everhart suggested that the flying branch embark on a study this year for a new KC-Z aerial refueling tanker that will enter service in 2035, as well as looking into the possibility of developing a “KC-Y” tanker to fill the procurement gap.

August 22/16: Last week ended on an extremely good note for both Boeing and Lockheed Martin after the companies were awarded major multi-billion contracts by the USAF. For Boeing, an impressive $2.8 billion award was granted on KC-46A following the tanker’s Milestone C decision earlier this month. 19 aircraft will be produced alongside spare parts, engines and refueling pods. However, this was astronomically dwarfed on Friday when Lockheed Martin was handed a $10 billion deal for all future orders of the C-130J Super Hercules production program as well as any foreign military sales for the aircraft.

August 15/16: After a long wait, the KC-46A tanker has been cleared for production. The Milestone C approval was awarded by US Under secretary of defense for acquisition, technology and logistics, Frank Kendall, following a series of stringent refueling tests of various USAF and Navy aircraft. Contracts are expected to be awarded to Boeing within the next 30 days for the first two low rate initial production lots, totaling 19 aircraft.

August 12/16: A long awaited low-rate initial production decision for the KC-46 tanker is to be made by the end of the month. Secretary of the USAF Deborah Lee James informed the media of the upcoming meeting “We believe that the aircraft has met all of the wickets that are required to meet milestone C, but of course that remains to be seen, so I’ll say stay tuned on that.” Flight testing of the aircraft wound up in July following a number of hardware and software fixes to the plane’s boom following aerial refueling problems.

August 9/16: Ground has been broken on the new $44 million KC-46A Pegasus sustainment campus at Tinker Air Force Base in Oklahoma. The facility will be responsible for all the maintenance, repair and overhaul operations required for the tanker. The first KC-46A are expected to roll into Tinker in 2018.

July 25/16: Boeing has announced the latest in an ongoing saga of cost overruns with the company taking a $393 million hit on the KC-46 tanker program. Well published issues such as the fault with the aircraft’s refueling boom have resulted in delays to the aircraft reaching an important program milestone prior to initial production. The charges are to be formally announced on July 27 and brings the total value of penalties to almost $1.9 billion. Don’t worry Boeing, the next round of drinks are on us.

July 20/16: Following the refueling of an A-10 Thunderbolt, the KC-46 has completed the last in a series of in-flight refueling tests necessary before its Milestone C production decision. A selection of Navy, USAF and USMC aircraft were chosen including the C-17, F-16, F/A-18 and AV-8B. The Milestone C decision to begin low-rate initial production is expected in August.

July 15/16: A KC-46A fitted with its brand new modified boom has successfully managed a mid-air refueling of a C-17 with the previous axial loading issues no longer present. The testing was carried out on July 12 and the USAF also refueled an F-16 on July 8. Refueling attempts with the F-16 earlier this year were successful, although a higher than expected axial load on the boom was detected. The higher load was again present during the initial attempt with the C-17 which necessitated installation of hydraulic pressure relief valves in the boom.

July 12/16: “Bypass surgery” has been carried out on the KC-46A to fix problems with the the flying boom on the tanker. A hardware fix has been implemented by adding two bypass valves to lighten the load on the boom. Boeing describing the modification as similar to that used on the US Air Force’s current KC-10 tankers.

June 6/16: Setbacks to the KC-46A tanker program have been compounded as Boeing has admitted that a software solution to fix the load issues on the flying boom was not robust enough and the company will have to modify the hardware itself. The plane was initially aiming to have a low-production order to deliver 18 tankers by next August. Issues arose during refueling trials with larger aircraft such as the C-17 military transporters which caused unacceptable stress loads along the axis of the boom.

May 31/16: Following close on the heals of the F-35’s delay in achieving initial operational capability (IOC), the KC-46A tanker will miss its scheduled Spring 2017 delivery to units. Instead, deliveries have been rescheduled for late summer or early fall of next year. The KC-46 tanker program was already on a tight trialing schedule as part of its Milestone C demonstration in June, but will now be pushed back until August.

May 9/16: Boeing has announced that they have developed a hardware and software fix for the KC-46A aerial tanker, allowing it to pass fuel to C-17 aircraft. The company encountered problems regarding a boom axial load issue during an earlier test to refuel the C-17, causing a setback to the already delayed flight test program. A “milestone C” decision on low rate production by the Pentagon is now expected in June after initially planned for April and now May.

April 29/16: April 29/16: Legislation being considered by the House Armed Services Committee (HASC) could see the last external link of the USAF’s F-117A Nighthawk fleet sent to the scrap yard. Retired since 2007, a fleet of the pioneering stealth aircraft have been kept in special climate controlled storage hangers in the event they were ever needed again. Now, Congress is considering removing those mothballed aircraft and having them scrapped and gutted for hard-to-find parts.

April 28/16: The forth and final test aircraft of Boeing’s KC-46A tanker program has made its maiden flight. While not kitted out for aerial refueling, the 767-2C aircraft will be used to conduct environmental control system testing for the program. The arrival of the latest tanker comes as Boeing scrambles to complete a “milestone C” review by the Office of the Secretary of Defense (OSD). A favorable review will unleash additional funds needed for the program, including a seven tanker production order, which the manufacturer had already begun producing out of its own pocket.

April 13/16: Despite development setbacks and a recent Milestone C demonstration hiccup, Boeing believes that it can deliver 18 operational KC-46 Pegasus tankers within six months instead of the original 14. The plan has been labelled “optimistic” in a new report by the US Government Accountability Office (GAO). While the GAO notes that most of the issues have been amended successfully, the recent problems seen in the aircraft’s centerline drogue system and wing aerial refueling pods may make this optimistic projection nothing but wishful thinking.

April 5/16: The otherwise fast pace of the KC-46A’s aerial refueling demonstration phase has started to run into difficulty. Testing on refueling of Boeing’s C-17 heavy cargo lifter has resulted in higher than expected boom axial loads, caused by two large aircraft flying in line. This bow-wave effect has subsequently caused the system to indicate that the loads were too high to begin passing fuel. Subsequent delays caused by the issues have resulted in scheduled trials of the A-10 attack aircraft being pushed back, and any further issues may impact a low-production rate decision due to be made at the end of May.

March 24/16: The Defense Contract Management Agency has expressed its “low confidence” in Boeing’s ability to deliver the KC-46A on time. Delivery of the tanker to the USAF is expected by August 2017 and is currently in the process of undergoing its Milestone C Demonstrations. Despite this, the agency now believes Boeing can only deliver the 18 KC-46As by March 2018, and there is a possibility that the new date might not be achievable either.

March 7/16: Boeing’s second KC-46A aerial refueling tanker has made its first flight. The aircraft will be used to test mission system avionics and exterior lighting before moving onto sharing the air refueling effort with the first KC-46. With a second fully configured tanker, Boeing can move through “receiver certification” for 18 aircraft types a lot more quickly. At present, the KC-46 has already demonstrated functionality with the Lockheed Martin F-16, Boeing F/A-18 and refueling from a Boeing KC-10.

February 26/16: Despite a successful start to the KC-46 Milestone C demonstrations, Boeing is still under pressure to keep to its tight window to have 46 of the tankers operational by August 2017. The original schedule is at present eight months behind after a number of setbacks, and leaves little room for error until the delivery deadline. While funding of the program and technical difficulties are not a contributing factor, it’s feared that the Air Mobility Command (AMC) won’t have sufficient time for the 767-2C-based tankers to declare initial operational capability on schedule.

February 24/16: The KC-46 is halfway through its six aerial contact tests as part of the program‘s “Milestone C” demonstrations. The tanker has now successfully demonstrated all three of its major fuel systems after being successfully topped up by another KC-10 aircraft. The February 16 test follows the refueling of a F-16 and F/A-18 over the last number of weeks, and keeps the program right on track for a low-rate initial production decision in May. The three remaining tests will involve probe-and-drogue testing with a US Navy AV-8B Harrier II jump jet, followed by boom refueling of a Fairchild Republic A-10 and Boeing C-17.

February 16/16: Testing of the refueling capabilities of the KC-46 tanker has hit another target with the successful refueling of an F/A-18 fighter. This follows its first ever refueling flight on January 24, where it successfully refueled an F-16. While the first test utilized the tanker’s refueling “boom,” a rigid, telescoping tube that an operator on the aircraft extends and inserts into a receptacle on the receiving aircraft for fuel transfer, the F/A-18 test was the program’s first usage of the KC-46’s hose and drogue system. Located on both the plane’s wing and centerline, the hose and drogue system enables the KC-46 to refuel smaller aircraft such as the F/A-18 with up to 400 gallons of fuel per minute. All tests are part of the program’s Milestone C demonstration before a low-rate initial production decision is made later this year.

February 11/16: An Israeli news source has reported that the US government has cleared the sale for two of Boeing’s newest KC-46A Pegasus aerial refueling tankers to Israel via the security assistance package. The Pentagon had originally put a pause on selling new aircraft to Israel, initially offering them older models. However, Israel has been insisting on the latest multi-mission tanker with the deal only approved upon the completion of the nuclear deal with Iran. The tanker sale could have become a point of contention for Tehran as its specs allow for a range of 7,350 miles with in-flight refueling. With an average price tag of $188 million each, the addition of Israeli system modifications will see each aircraft cost a quarter of a billion dollars.

January 26/16: The USAF and Boeing have reached an important milestone in the development of the KC-46 tanker after it successfully carried out a mid-air refueling of an F-16 jet. Prior to the refueling, both had checked a number of test points during the flight, with a successful demonstration necessary before Boeing can enter the plane into low rate production. The USAF has ordered 176 of the tankers to replace their KC-135 Stratotankers with the first eighteen of the tankers needed to be operational and ready to go by August 2017.

October 26/15: In a not unexpected decision, the Japanese Defence Ministry has opted to buy three KC-46A Pegasus tankers, marking the first international sale of the aircraft, which is still in development. The three new aircraft will bolster the JASDF’s fleet of four KC-767s, with each of the new aircraft thought to value $173 million. The KC-46As are slated for fielding in 2020, with the Boeing bid fending off competition from Airbus’ A330 MRTT. Elsewhere in the region, South Korea selected the Airbus design in July, signing a contract for four A330-MRTTs.

October 23/15: The KC-46A Pegasus tanker EMD-1 development aircraft has arrived at Edwards AFB for two weeks of work, including Ground Effects and Fuel Onload Fatigue tests. The latter involves learning more about how the aircraft operates when taking on fuel from another tanker, such as a KC-135 or KC-10, while Ground Effects testing collects data to incorporate into the aircraft’s simulator. The other development aircraft (EMD-2) deployed its refuelling boom for the first time in October, with EMD-1’s maiden flight in September.

October 12/15: The KC-46A Pegasus tanker has deployed its refuelling systems for the first time, including its boom, hose and drogue systems. The tanker performed its first flight in September, following a delay in August. Boeing is working towards an initial operating capability – which will see 18 KC-46A and support available for operations – by August 2017.

October 9/15: Two Air Force pilots have been cleared to fly the KC-46A Pegasus tanker, which performed its first test flight in late September. The pilots will be used for military certification of the aircraft, which is also required to pass FAA regulations. The Air Force is eventually scheduled to receive 179 KC-46A tankers under a contract awarded to Boeing in February 2011; the fixed-cost nature of the contract means that Boeing has been forced twice to absorb development costs, with the Air Force’s costs capped at $4.9 billion.

FY 2015

September 28/15: A fully-configured KC-46A tanker completed its first flight on Friday, a month later than scheduled owing to the chemical mix-up in early August. The program is a year behind schedule, the first flight is a rare positive sign for a program hit by cost spikes and schedule delays, with Boeing scheduled to deliver 18 aircraft in August 2017.

September 18/15: With Airbus walking away from the competition earlier this month, the Japanese Defense Ministry has reportedly selected the Boeing KC-46A to supply the country’s next generation refuelling tanker. Price negotiations are now scheduled, with the number of tankers the Defense Ministry plans to procure not yet determined. Boeing lost out in South Korea to the Airbus A330 MRTT in July.

September 17/15: The first KC-46A tanker is expected to fly on 25 September, following a year-long delay. The trouble-hit tanker has become a headache for Boeing, which has been absorbing increasing development costs through a firm-fixed contract signed in February 2011 which capped Air Force costs at $4.9 billion. The most recent setback resulted from an accident involving the insertion of chemicals into the aircraft’s refuelling system in early August, pushing the tanker’s schedule back by a month.

August 19/15: The mistake earlier this month involving the accidental insertion of chemicals into the fuel system of the KC-46A tanker has officially delayed the aircraft’s first flight by a month. The tanker will now see its first flight in late-September or early October, with the program’s original timetable calling for this flight to have taken place last year, with this pushed back to April and then again to late August, before this latest setback.

July 1/15: South Korea has selected Airbus’ bid to supply the country’s Air Force with four refueling tankers, beating competitors Israel Aerospace Industries and Boeing for the $1.07 billion program. The winning bid – the A330 MRTT – dashed Boeing’s hopes of securing its first export order for the KC-46A, which saw a strong dollar raise its bid price compared with a weakened euro for the European bid. The four tankers are scheduled for delivery in 2019.

June 10/15: NAVAIR has been slamming missiles into the side of its KC-46 tankers as part of Naval Air Warfare Center Weapons Division survivability testing at the Weapons Survivability Laboratory. The tests used – among other sensors – ten high-speed cameras to capture the impact of the test missiles, themselves specifically designed to inflict maximum possible damage to the aircraft. The Air Force intends to buy 179 of the tankers to replace approximately a third of the current tanker fleet, which consists principally of KC-135 Stratotankers.

April 24/15: Tinker Air Force Base (Oklahoma) has been named as one of four potential locations to base the Air Force’s fleet of new KC-46A refueling tankers, alongside Seymour-Johnson Air Force Base (North Carolina), Westover Air Reserve Base (Massachusetts) and Grissom Air Reserve Base (Indiana).

Jan 26/15: Flight test. Boeing conducted a flight test from Payne Field in Everett, Washington. The four-hour flight was uneventful, but well-documented.

Dec 10/14: spares. Boeing is awarded a not to exceed $84.5M undefinitized contract action modification (P00054) to previously awarded contract FA8625-11-C-6600 for 4,880 production support equipment items and 6 production spare parts. Work will be performed at Seattle, WA, and is expected to be completed by June 30, 2016. $9.5M in FY14 aircraft procurement funds and $32.2M in FY15 aircraft procurement funds are being obligated at the time of award.

Dec 03/14: wiring. Boeing Dennis Muilenburg told investors during a conference organized by Credit Suisse that wiring problems that had led to delays and charges (q.v. Sept 17/14) were now “resolved and closed out.”

Dec 01/14: Training. The USAF intends to finalize its Maintenance Training System (MTS) RFP in January 2015. The draft, released back in September, is found under solicitation IDN-KC-46-MTS.

Nov 24/14: Personnel. The Air Force Personnel center announces that the aircrew of 41 officers and enlisted members from the active force, Reserve and National Guard have been selected to staff initial operational test and evaluation (IOT&E).

Nov 19/14: Schedule. The USAF publicly admits what KC-46A program watchers already know: Boeing is essentially out of schedule margin to deliver the 767-based KC-46As on time by 2017. The USAF is still describing the contract as “achievable,” but so many things have to go right that this isn’t a smart bet for outside observers. The USAF won’t really say anything else until disaster is certain, though, because the admission will make the service look bad (q.v. March 4/11). Sources: Reuters, “US Air Force sees challenges on Boeing KC-46 tanker program”.

Oct 16/14: Delays. Boeing finally admits that the KC-46A’s program schedule will have to be changed. They don’t know how many milestones will need adjustment, but they’re still holding to the idea that they’ll have 18 KC-46As delivered by August 2017.

Can they avoid proving Airbus’ March 4/11 prediction that Boeing would deliver late? It’s hard to see how Boeing’s on-time promise adds up now, given significant GAO and DOT&E concerns that the testing program as proposed is too compressed and can’t be executed (q.v. April 11/14, Sept 17/13). Boeing gets to try convincing Pentagon acquisition officials with an official submission early in 2015, and the USAF will then conduct its own “schedule risk assessment” to examine Boeing’s assumptions.

Most ways of speeding up programs involve spending more money, though that tends to have diminishing returns past a certain point. The program’s official cash reserve is expected to run dry in March 2015, but the USAF’s costs are capped, so it’s likely that Boeing will wind up spending more private funds on KC-46A development. Sources: Bloomberg, “Boeing Seeks Revised Schedule for U.S. Aerial Tanker”.

FY 2014

Competition in South Korea? Initial basing decisions; Boeing takes extra costs charge, announces delays.

Workers saluted

Sept 17/14: Flight delay. First flight for the KC-46A is in question due to the same wiring bundle technical issues that forced Boeing to take an additional $272 million Q2/14 charge on the program (q.v. July 23/14). USAF spokesman Ed Gulick:

“We are disappointed with Boeing’s current KC-46 production challenges and their inability to meet internal production milestones, but we do not see anything of great concern and are confident they will overcome the issues,” said Gulick in a statement to Puget Sound Business Journal. “The KC-46 program’s technical and cost performance are on-track; Boeing has met every contractual requirement to date.”

The baseline 767 has about 70 miles of wiring in the design, and the need for redundancy in certain systems pushes the 767-2C to 120 miles, including shielding requirements and mandatory separation distances for safety reasons. The redesign will address these issues, but it sideswipes plans for concurrent installation in the 4 test aircraft currently under construction. Given the program’s known issue with compressed test schedules (q.v. April 11/14), they had better be ready by April 2015. Sources: Aviation Week, “First Flight for KC-46 Tanker Platform Slips Further” | Puget Sound Business Journal, “Air Force ‘disappointed’ in Boeing tanker delays; issues cost Boeing millions”.

Sept 15/14: Training. The USAF issues a Draft Request for Proposal (DRFP) for the KC-46 Maintenance Training System (MTS) Program. It consists of various specific component trainers, e-learning materials, and Training System Support Center build-outs. Sources: FBO.gov, “KC-46 Maintenance Training System, Solicitation Number: IDN-KC-46-MTS”.

Aug 5/14: Basing. The USAF announces that the KC-46A’s MOB2 Air National Guard base will be Pease ANGB, NH, which beat Forbes AGS, KS; Joint-Base McGuire-Dix-Lakehurst, NJ; Pittsburgh International Airport AGS, PA; and Rickenbacker AGS, OH.

Pease has apparently been the preferred alternative since May 2013, owing to its location in a region of high air refueling receiver demand and successful ANG-USAF partnership. This announcement follows the required environmental reviews. Sources: Pentagon NR-409-14, “Pease Air National Guard Base selected to receive KC-46A Pegasus aircraft”.

Basing: MOB2 ANG picked

July 23/14: Cost. During a Q2 analyst conference call, Boeing CEO Jim McNerney says that they’re absorbing a $272 million unexpected charge related to problems with KC-767 wiring harnesses:

“We bid the EMD (engineering manufacturing and development) contract for the tanker aggressively, with zero margin, with planned profitability in the production phase. Despite our disappointment in encountering these challenges, the issues are well understood, and no new technology is needed to solve them…. We have a wet fuel lab, a lighting lab, those have all been put in place to de-risk the program. We have a wet lab where we are running fuel through pumps and valves to validate that on the ground.”

Sources: Boeing, “Boeing Reports Second-Quarter Results and Raises 2014 EPS Guidance” | Puget Sound Business Journal, “Boeing: We can fix Air Force tanker problems without new technology”.

July 14/14: Cost. The KC-46A development phase could end up costing Boeing more than expected. That may concern Boeing executives, but the USAF won’t pay any more and doesn’t care:

“Defense Undersecretary Frank Kendall told reporters late on Sunday that Boeing was performing “satisfactorily” on the KC-46 tanker program, but several events – including water damage caused by a sprinkler malfunction at the company’s Everett, Washington plant – meant costs were higher than expected.”

Boeing says that they’ll be able to cut costs with their testing approach. We’ll see. Sources: Reuters, “AIRSHOW-Boeing may face higher than expected costs on KC-46 tanker”.

June 30/14: South Korea. Boeing confirms that they’ve formally offered South Korea the KC-46A tanker being developed for the USAF, rather than the KC-767 model that’s already in service with Japan and Italy. They tout the KC-46A’s quick-conversion main deck cargo floor, but in the face of North Korea’s WMD arsenal, and ability to target ROKAF bases with missiles, they make a point of mentioning that:

“Unique among tankers, the KC-46 can operate in chemical, biological and nuclear conditions, features cockpit armor for protection from small arms fire, and can also operate from a large variety of smaller airfields and forward-deployed austere bases.”

Sources: Boeing, “Boeing Offers Next-Generation KC-46 Tanker in Republic of Korea Competition”.

June 4/14: Infrastructure. The Ross Group Construction Corp. in Tulsa, OK wins a $17.5 million firm-fixed-price contract with options, to built the KC-46A Fuselage Trainer Flight Training Center and the Fuselage Trainer at Altus AF, OK. Option 4 for sidewalks and landscaping, and Option 5 for additional concrete parking stalls, are exercised at time of contract award. Altus AFB was recently chosen as the KC-46A’s main training base (q.v. April 23/14), and already operates in that capacity for the KC-135 fleet.

The estimated completion date is Oct 5/15. Bids were solicited via the Internet, with 7 received by the US Army Corps of Engineers in Tulsa, OK (W912BV-14-C-0015).

May 29/14: Infrastructure. MEB General Contractors in Chesapeake, VA wins an $8.4 million fi

Show more