2016-10-18



UH-1Y and AH-1Z
by Neville Dawson

The US Marines’ helicopter force is aging at all levels, from banana-shaped CH-46 Sea Knight transports that are far older than their pilots, to the 1980s-era UH-1N Hueys and AH-1W Cobra attack helicopters that make up the Corps’ helicopter assault force. While the tilt-rotor V-22 Osprey program has staggered along for almost 2 decades under accidents, technical delays, and cost issues, replacement of the USMC’s backbone helicopter assets has languished. Given the high-demand scenarios inherent in the current war, other efforts are clearly required.

Enter the H-1 program, the USMC’s plan to remanufacture older helicopters into new and improved UH-1Y utility and AH-1Z attack helicopters. The new versions would discard the signature 2-bladed rotors for modern 4-bladed improvements, redo the aircraft’s electronics, and add improved engines and weapons to offer a new level of performance. It seemed simple, but hasn’t quite worked out that way. The H-1 program has encountered its share of delays and issues, but the program survived its review, and continued on into production and deployment.

DID’s FOCUS articles offer in-depth, updated looks at significant military programs of record. This article covers the H-1 helicopter programs’ rationales and changes, the upgrades involved in each model, program developments and annual budgets, the full timeline of contracts and key program developments, and related research sources.

The H-1 Helicopters



TopOwl
(click to view full)

For pilots, both H-1 helicopters will incorporate a newly designed “Integrated Avionics System” cockpit designed by Northrop Grumman, including dual mission computers, GPS navigation, moving map displays, and other modern aids. Pilot workload will be improved further by using Thales’ TopOwl helmet-mounted display systems (HMDS), to offer flight and targeting data no matter where the pilot looks.



FLIR Systems’ BRITE Star NTIS will handle targeting and surveillance on the UH-1Y Venom. The UH-1Y is currently slated to use only machine guns and 70mm rockets, but a March 2012 decision has added laser-guided APKWS rockets to its arsenal.

The AH-1Z Viper will use the more advanced Lockheed Martin/ Wescam/ Kollsman AN/AAQ-30, which is fully integrated into the AH-1Z fire control system and TopOwl HMD. It provides range and optical line-of-sight data for all weapons, even AIM-9M Sidewinder air-to-air missiles. TSS features a large-aperture, 3rd-generation staring mid-wave FLIR derived from Lockheed’s fighter-borne Sniper targeting pod; a 640 x 512 day/night TV with automatic video tracker and continuous zoom from high magnification to wide field of view; a laser spot tracker; an on-gimbal inertial measurement unit (IMU) for accurate line-of-sight pointing and geolocation of targets; coupled with a Kollsman laser designator/rangefinder with an eyesafe mode. The AAQ-30’s wide Field-of-View (FoV) optics also provide a secondary navigation capability when light levels are low, and night vision goggles are ineffective. All of this is packed into a stabilized L-3 Wescam turret.

Overall, the AH-1Z Viper will have a wider array of weapons to choose from, and it will become the Navy’s initial platform for the dual-mode radar/laser guided JAGM missile if the weapon makes it into production.

Neither helicopter uses extensive armoring for protection, as is the case with the AH-64 Apache, for instance. Instead, efforts like infrared-reducing paint and exhausts, design for low profiles, and some protection to key systems like energy-absorbing landing gear, self-sealing fuel systems and a fuel vapor inerting system are used. Troops riding in the UH-1Y will especially appreciate the energy attenuating seats that reduce the effects of G-forces in the event of a crash, or hard landing; in the UH-1N, they just had to sit on the floor and receive the full shock. Both helicopters will also rely on a common set of advanced defensive systems:

ATK’s AN/AAR-47 missile approach warning system – will become JATAS

BAE’s AN/ALQ-144 infrared (IR) jammer and AN/ALE-47 decoy dispensing system, serves as central ECM hub

Northrop Grumman’s AN/APR-39A(V)2 radar warning receiver

UT Goodrich’s AN/AVR-2A laser warning receiver

A Directed InfraRed CounterMeasures (DIRCM) system of some kind may be added to the AH-1Z in particular

UH-1Y & AH-1Z: Performance Issues

AH-1Z, testing
(click to view full)

Some issues do remain with the helicopters. One is that the 2 engines provide almost 3,660 shp, but the aircraft’s transmission is flat-rated for 2,350 shp. That doesn’t matter as much at altitude or in very hot weather, or above 180 knots airspeed where drag becomes the limiting factor, so it was deemed acceptable.

For the AH-1Z, potential issues include a lack of robust armor – a characteristic it shares with earlier AH-1 models, but not with the Army’s heavily armored AH-64 gunship. The exception is the flight controls and some engine sections, which can withstand cannon fire up to 23mm. This is more of a design choice than a manufacturing flaw, but it does affect the helicopter’s usage.

A second AH-1Z design issue involves communications. Statements by H-1 upgrade program manager USMC Col. Harry Hewson seem to indicate that the older AH-1Ws will initially be more advanced in this area. The AH-1Zs will have secure voice communications only, while the upgraded AH-1W includes the tactical video data link (TVDL) that can broadcast sensor data to a ground controller with a ROVER system, or receive video from other helicopters or Marine aircraft with LITENING pods. As of 2014, a full-motion video project is in the works for the AH-1Z, but hasn’t been fielded yet.

On the manufacturing side, as of December 2010, several rotor components were falling far short of the original 10,000 hour reliability goal. Unfortunately, efforts to redesign the rotor head’s cuff and yoke weren’t going to provide enough improvement to justify the costs. NAVAIR says that current efforts involve improved tooling design and manufacturing processes for the existing design.

The H-1 Upgrade Program

UH-1N, Iraq
(click to view full)

It seemed fairly straightforward: update a pair of old USMC standbys in the UH-1N and AH-1W, creating a transport (UH-1Y Venom) and attack helicopter (AH-1Z Viper) backbone with maximum commonality, and minimum risk.

It hasn’t quite worked out that way.

The H-1 program is designed to resolve existing safety issues in both aircraft, reduce life-cycle costs, significantly enhance combat capability, and achieve 85% commonality between the 2 versions. Bell Helicopter believes this commonality can save up to $3 billion in operating and support costs over a 30-year lifespan, and the stated goal is airframes that will last through 10,000 flight hours of service life. Common components include the tail boom, engines, drive train, rotor blade, software controls, avionics, and displays.

Many of these helicopters will be remanufactured from the Marines’ old UH-1N Hueys and its AH-1W Super Cobra attack helicopters. Major modifications include a new 4-blade rotor system with semi-automatic blade fold, new composite main and four-bladed tail rotor, upgraded drive system and landing gear, and pylon structural modifications. The AH-1Z attach helicopter will also have 2,500 pounds of fuel instead of 1,900 (AH-1W), to extend strike range to over 170 miles. GE’s T700-401C engine will power both helicopters, giving them improved maneuverability, speed and range, and payload when compared to their UH-1N and AH-1W predecessors. The UH-1Y is touted as having 50% better range, a faster maximum speed, and 25% greater payload than its UH-1N predecessor. The AH-1Z is touted as almost doubling effective strike range over the AH-1W, or doubling weapons load carried to the same ranges. Maintainability is also being addressed, using embedded diagnostics that can provide warning of maintenance needs or impending faults.

H-1 Upgrade: Force Size & Structure Shifts

AH-1W, hard left
(click to view full)

The H-1 program has required substantial changes to both cost and schedule 4 times now, while addressing numerous technical issues. The UH-1Y/ AH-1Z upgrades program was originally structured as a remanufacturing effort, converting 180 AH-1W Super Cobras to AH-1Z Vipers, and 100 UH-1N Hueys to UH-1Y Venoms.

It didn’t stay that way.

The initial changes were prompted by 2 factors: effort and time.

The idea of remanufacturing the helicopters didn’t look so great once the true scope and expense of the work involved became clear. Worse, it involved taking each UH-1N Huey out of service for 2 whole years, in the face of ongoing demand from the front lines.

The program tried putting new UH-1Y nose sections into production earlier, and establishing a rotating pool of government-furnished equipment so a UH-1N doesn’t have to be taken out of service until a corresponding UH-1Y Venom is delivered. After the 1st 10 UH-1Y remanufactures, however, the rest were switched to new-build machines.

The next big change was the USMC’s Program Objective Memorandum for 2010, which raised the future fleet to 123 UH-1Ys and 226 AH-1Zs (58 new-build + 168 remanufactured), as part of a plan to grow the Marines by about 20,000 troops. Under this plan, the 58 new-build AH-1Zs would be delivered first, in order to maintain overall fleet availability by keeping existing AH-1Ws in service. Once the overall fleet had grown, AH-1Ws could be taken from the front lines and shifted into the remanufacturing program.

Subsequent shifts have pared back the number of AH-1Zs, and drastically reducing the number of remanufactured AH-1Zs, while increasing the number of UH-1Y Venoms. The legacy model is a USMC squadron of 18 AH-1Ws and 9 UH-1Ns, but the future will involve 15 AH-1Zs and 12 UH-1Ys in each squadron.

So, why the extra Venoms?

The UH-1Y’s extra power proved to be extremely useful in hot and high-altitude conditions, and the planned addition of guided 70mm rockets like APKWS and LOGIR would give them an attack punch comparable to previous AH-1 Cobras. The UH-1Y’s performance in Afghanistan using APKWS guided 70mm rockets has only reinforced these opinions.

The other question is, why did remanufactured AH-1Ws decline so sharply?

Heavy wartime use has increased the wear on existing AH-1Ws, which created a shortage of flyable attack helicopters, and made remanufacturing them more expensive. By FY 2013, cost estimates for new AH-1Z cabins offered an option that was now cheaper over the machines’ service life, while avoiding a critical USMC shortage by leaving AH-1Ws in the fleet.

H-1 Program: Budgets & Industrial Partners

Note that these years do not always correspond fully to Production Lot orders, though they can be used as a general guide. Since American supplemental funding bills are typically passed closer to mid-year, and not in conjunction with the baseline defense spending bills, aircraft appropriated under OCO/supplemental funding as war replacements are sometimes bought with the following year’s contract.

For instance, in 2009, the 11 baseline UH-1Ys, 5 baseline AH-1Zs, and 4 supplemental UH-1Ys were bought as Lot 6 (20 helicopters); but the program office didn’t have priced options for additional AH-1Zs negotiated for Lot 6. That’s why FY 2009’s 4 supplemental AH-1Zs were bought as part of Production Lot 7.

In FY 2010, those 4 Lot 7 supplemental AH-1Zs were added to FY 2010’s 18 UH-1Ys, 5 AH-1Zs, and 2 OCO funded new-build AH-1Zs, growing Lot 7 to 29 helicopters. The “29” total adds the 4 machines from FY 2009, but also omits the FY 2010 supplemental bill’s 1 UH-1Y and 1 AH-1Z. They’re part of Lot 8, because their bill’s timing prevented them from being added to Lot 7. And so it goes…

H-1 Upgrade Program industrial partners include:

Program Problems

UH-1Y & AH-1W,
in Afghanistan
(click to view full)

The original idea of remanufacturing existing helicopters, and adding some new performance enhancements, seemed like a low-risk program. Events have a vote, however, and the actual program has been much more challenging than expected.

In May 2005, the Navy warned Bell that the H-1 program was in serious jeopardy. The Texas-based company was described as failing to meet Navy needs, and the memo reserved the option of killing the program. It demanded “fundamental changes” in Bell Helicopter’s management processes as well as its production processes. Recertification in Earned Value Management, used to track program performance, was high on the list of “to-dos.”

Ultimately, changes were made – including some executive changes at the highest levels of Bell Helicopter Textron.

A May 31/06 Defense Acquisition Board process made the decision to proceed with the program. The UH-1Y and AH-1Z began Phase II of their Operational Evaluation (OpEval) in February 2008, and a full rate production decision was expected in August 2008.

After the management and process issues were sorted out, the UH-1Y did very well. Its Initial Operational Capability (IOC) came a month early, in August 2008, and it received a full production go-ahead in September 2008.

The AH-1Z has fared less well, thanks in part to issues surrounding the AAQ-30 surveillance and targeting system, and the TopOwl helmet-mounted display. Other issues included rocket gas ingestion by the engines, and problems with mission software. IOC for the AH-1Z was pushed back from FY 2008 to FY 2011, but the program is moving toward completion.

Contracts and Key Events

Unless otherwise noted, all contracts are issued by US Naval Air Systems Command (NAVAIR) in Patuxent River, MD to Bell Helicopter Textron, Inc. in Fort Worth, TX.

FY 2015 – 2016

October 18/16: Bell Helicopters is keen to sell its AH-1Z attack helicopter as a solution to Japan’s AH-X program. As part of preparations the company has teamed with engineers from Fuji Heavy Industries on modification work to the helicopter aimed at improving transmission performance. If selected, between 60-70 of the Bell 412EPI-based helicopters would be produced locally in Fuji with the first slated to deliver in 2022. Civilian variants would also be produced in Fuji in an effort to help the production line attain scale.

April 22/16: Protests have arisen by some US lawmakers against the USAF’s UH-1N Huey helicopter replacement program. The helicopters, which protect US supplies of inter-continental ballistic missiles (ICBMs), are to be replaced via a sole-source contract due to a new urgency felt by air force brass in fielding the capability favoring Sikorsky’s UH-60 Black Hawk. This in turn has caused a group in Congress to rail back who now want a fair and open competition for the Huey’s replacement.

March 15/16: The US Navy has awarded Bell Helicopters a $461 million contract to supply the force with 12 Lot 13 UH-1Y and 16 Lot 13 AH-1Z helicopters. The contract includes the provision of 16 auxiliary fuel kits. Completion of the sale is expected by February 2019 as part of the Navy’s H-1 upgrade program. Bell Helicopters has also signed a teaming agreement with BAE Systems Australia to offer the AH-1Z as a potential replacement for the Australian Army’s Tiger fleet.

August 19/15: The H-1 helicopter fleet of both the Navy and Pakistan will receive a boost through a $85.5 million contract to develop weapons systems for the aircraft as part of its system configuration set (SCS). The SCS intends to create prototypes for emerging operational requirements, with the majority of this contract covering acquisitions for the US Navy, with the contract set to run to 2020.

FY 2014

UH-1Y from LHD 4
(click to view full)

Sept 5/14: A $41.8 million firm-fixed-price contract for 3 UH-1Y flight training devices (aka. simulators), 1 AH-1Z flight training device, aircraft and/or trainer driven revisions, aircraft common operational equipment, provisioned device spares, associated technical data required for operational and maintenance support, and 3 months of initial operation evaluation period for each flight training device. All funds are committed immediately, using FY 2012 Navy reserve and FY 2014 aircraft budgets.

Work will be performed at Broken Arrow, OK (46%); Fort Worth, TX (33%); St. Louis, MO (15%); and Austin, TX (6%), and is expected to be complete in June 2018. The contract was not competitively procured pursuant to FAR 6.302.1 by the Naval Air Warfare Center Training Systems Division in Orlando, FL (N61340-14-C-1000).

Aug 4/14: UH-1Ns. The USMC plans to retire the last of its 205 UH-1N Huey helicopters in September 2015. Of that total, 10 were upgraded to UH-1Ys. Another 5 upgraded HH-1Ns will continue to serve at MCAS Yuma, AZ, but they will retire in 2015. Sources: Navy League Seapower, “Marine Corps to Retire UH-1N Helicopters in September; HH-1Ns in 2015”.

June 20/14: Support. A $44.7 million modification, finalizing a previously awarded contract to a cost-plus-fixed-fee price contract to repair various parts for the UH-1Y and AH-1Z Upgrade Helicopters. FY 2014 US Navy budgets will be drawn on as needed.

Work will be performed in Hurst, TX, and work is expected to be complete by January 2017. No funds will be obligated at the time of award and contract funds will not expire at the end of the current fiscal year. This contract was a non-competitive requirement in accordance with 10 USC. 2304 (c)(1), managed by NAVSUP Weapon Systems Support in Philadelphia, PA (N00383-14-D-015N).

May 29/14: Sub-contractors. Northrop Grumman Guidance and Electronics Co. in Woodland Hills, CA receives a $25 million delivery order for 119 H-1 upgrade tech refresh mission computers. Those have been broken out into a separate purchase by the US Navy, as a way to improve costs. $10.9 million in US Navy FY 2013 – 2014 aircraft budgets is committed immediately.

Work will be performed in Woodland Hills, CA (79%); Salt Lake City, UT (13%); and Baltimore, MD (8%); it is expected to be complete in October 2017 (N00019-11-G-0016, DO 0002).

May 16/14: Lot 11. A $337.8 million contract modification finalizes the Lot 11 order for 12 new UH-1Ys and 12 new AH-1Zs, creating a fixed-price-incentive contract for the helicopters and a firm-fixed-price contract for the auxiliary fuel kits. See also May 28/13, which brings the total announced award to $388.4 million – but note that this contract adjusts the previous ratio from 15 UH-1Ys and 10 AH0-1Zs.

All funds are committed immediately, using FY 2013 & 2014 US Navy aircraft budgets, which makes sense. The final FY 2014 budget has cut buys to a base of 11 UH-1Ys and 10 AH-1Zs, and recall that annual contracts also tend to include supplemental funding purchases from the previous fiscal year. Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%), and is expected to be completed in June 2017 (N00019-13-C-0023).

Lot 11 order

April 7/14: HMD. Thales Defense & Security Inc. in Clarksburg, MD received a $38.5 million firm-fixed-price, indefinite-delivery/indefinite-quantity contract for Optimized Top Owl (OTO) Helmet Mounted Sight and Display (HMSD) Sustainment Capability services. They’re replicating the facility, labor, materials, parts, test and tooling equipment from Bordeaux, France to the United States.

$1.8 million in FY 2014 Navy budgets is committed immediately. Work will be performed in Clarksburg, MD, and is expected to be complete in April 2019. This contract was not competitively procured pursuant to FAR 6.302-1 by NAWCAD in Lakehurst, NJ (N68335-14-D-0014).

March 28/14: Lot 12. Bell Helicopter Textron Inc. in Hurst, TX receives a $59.7 million contract modification, buying long-lead items for Lot 12’s 15 new-build UH-1Ys and 11 new-build AH-1Zs.

All funds are committed immediately, using FY 2014 Navy aircraft budgets. Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%), and is expected to be complete in September 2015 (N00019-13-C-0023).

March 28/14: Support. Bell Helicopter Textron Inc. in Hurst, TX receives exercises an $11.4 million firm-fixed-price contract option for H-1 upgrade program systems engineering and program management support.

All funds are committed immediately, using FY 2014 USN aircraft budgets. Work will be performed in Hurst, TX, and is expected to be complete in December 2014 (N00019-12-C-0009).

March 4-11/14: Budgets. The US military slowly files its budget documents, detailing planned spending from FY 2014 – 2019. The numbers are featured in the charts above, and the detailed documents add this:

“FY 2015 Airframe cost increases account for prime contractor’s new Business System Modernization (BSM) accounting structure and increased internal research and development investment, Pension Protection Act pension harmonization and higher medical forecasts, and continued effects of large business base decline. Due to airframe cost increases and USMC priorities, the program… added one year of production. Compared to President’s Budget 2014, unit cost growth is a result of deferred aircraft to FY 2020…. electronics previously harvested from UH-1N and AH-1W aircraft at no-cost were procured new, at cost, for all future lots beginning in FY 2013…: CD-45/ALE-47(V) Chaff/Flare Programmer, ICS Boxes, MT-6711 TACAN Mount, RT-1798 TACAN Receiver, APR39 System, CP-1975/AAR-47(V)2 Central Processor, SU-211/AAR-47(V)2 Optical Sensor, AS-2728 Antennas AT-741B/A Antennas, EGIs, CV-20 Digital Converters. GFE Electronics increase in FY 2014 due to Mission Computer being provided as GFE instead of CFE.

All new engines are factored into the budget formulation for FY 2014 through the FYDP. The program prefers to procure new T-700-401C engines for higher maintainability and reliability, increased time on wing, and ultimately lower life-cycle costs. Refurbished T-700-401C engines are procured as budget constraints warrant and the H-60 B/F sundown schedule permits. An additional determining factor for refurb engine procurement is the repair (refurb) contract ceiling for H-1 with General Electric Engine Services (GEES), currently at sixteen engines per year. Due to funding constraints as a result of sequestration, program reductions, and airframe costs, 16 UH-1Y refurbished engines were procured in FY 2013.”

Jan 28/14: DOT&E Testing Report. The Pentagon releases the FY 2013 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The H-1 upgrade program is included, and as of July 2013, Bell Helicopter has delivered 79/160 UH-1Ys and 32/189 AH-1Zs.

The big issue with the H-1s is software, and to a lesser extent support. The SCS 6.0 software has a critical flaw: if it detects a failure in any electronic warfare component, whether real or a “false positive”, the helicopter loses the entire EW display for all threat detection systems. That cost 2 of 23 missions during testing. This problem was detected during developmental testing, but DOT&E blandly says that “the operational implications of this loss of electronic warfare situational awareness were not apparent until operational testing.” Really?

They’re testing SCS 7.0, which hopes to correct this problem, and DOT&E concludes that “H-1 Upgrades units remain survivable against small arms and automatic weapons fire (up to 12.7 mm) and legacy Man-Portable Air Defense Systems.”

Meanwhile, they note that the test helicopters had problems with readiness rates because of long waits for repair parts. Tail and rotor systems were an especial problem, in part because operational units quite properly have priority. What they don’t say is whether the level of problems encountered are an indicator of larger issues.

Jan 22/14: Support. A $13.5 million cost-plus-fixed-fee delivery order for repair/overhaul work on 5 high priority UH-1Y/AH-1Z items.

$6.7 million in FY 2014 USN funds are committed immediately. Work will be performed in Hurst, TX, and the contract runs until January 2017. US Naval Supply Systems Command Weapon Systems Support in Philadelphia, PA manages the contract (N00383-14-D-015N, DO 0001).

Dec 19/13: Avionics. Northrop Grumman Guidance and Electronic in Woodland Hills, CA receives a $10.6 million firm-fixed-price contract for low rate initial production of 45 improved (“technical refresh”) AH-1Z and UH-1Y helicopters mission computers, which are now being bought direct (q.v. Dec 29/11 entry).

All funds are committed immediately, using FY 2012 USN aircraft procurement budgets, and will expire of Sept 30/14. Work will be performed in Woodland Hills, CA, and is expected to be complete in October 2015. This contract was not competitively procured pursuant to FAR 6.302-1 by the Naval Air Warfare Center Weapons Division in China Lake, CA (N68936-14-C-0020).

Dec 17/13: Sensors. Lockheed Martin Missiles and Fire Control in Orlando, FL receives a $34 million firm-fixed-price contract for the AH-1Z’s AN/AAQ-30(A) Target Sight Systems (TSS) and data. Based on past contracts, that’s about 12.

$31.2 million is committed immediately, using USN FY 2013 and 2014 aircraft procurement budgets. Work will be performed in Orlando, FL (80%), and Ocala, FL (20%), and is expected to be complete by May 2016. This contract was not competitively procured in accordance with 10 U.SC 2304(c)(1), as set forth in FAR 6.302-1(b)(1)(ii). The US Naval Surface Warfare Center in Crane, IN manages the contract (N00164-14-C-JQ65).

FY 2013

Orders; Loss in South Korea; Losing helicopters at program’s end?

AH-1Z, fully armed
(click to view full)

Sept 27/13: Training. Bell Helicopter Textron, Inc., Hurst, TX receives a $23.1 million firm-fixed-price contract modification to perform baseline configuration upgrades for 1 AH-1Z Full Flight Simulator, 1 UH-1Y Full Flight Simulator, and 1 UH-1Y Flight Training Device. All funds are committed immediately.

Work will be performed in Broken Arrow, OK (49%); Fort Worth, TX (35%) and St. Louis, MO (16%), and the larger contract runs until March 2017. The US Naval Air Warfare Center Training Systems Division, Orlando, FL manages this contract (N61340-12-C-0030).

Aug 27/13: Sensors. Lockheed Martin Missiles and Fire Control in Orlando, FL received a $34 million firm-fixed-price contract for the AH-1Z’s AN/AAQ-30 Target Sight Systems (TSS). All funds are committed immediately.

Work will be performed in Orlando, FL (80%), and Ocala, FL (20%), and is expected to complete by November 2015. The US Naval Surface Warfare Center in Crane, IN manages the contract (N00164-13-D-JQ43).

Aug 26/13: Sensors. FLIR Systems Inc. in Wilsonville, OR receives a 5-year sole-source $136.6 million firm-fixed-price, indefinite-delivery/ indefinite-quantity contract for BRITE Star Block II Systems (UH-1Y and MQ-8C), BRITE Star II’s class I engineering change proposal, plus BRITE Star I upgrades, cables, technical data, depot repairs, and engineering services. $4.2 million is committed immediately.

Work will be performed in Wilsonville, OR, and is expected to be complete by August 2018. The work was sole-sourced on the basis of FAR 6.302-1, “only one responsible source…” provision. The Naval Surface Warfare Center in Crane, IN manages the contract (N00164-13-D-JQ08).

July 15/13: Support. A $17.9 million firm-fixed-price, cost-plus-fixed-fee contract to add US Navy depot level maintenance infrastructure. Bell Helicopter will develop, test, and deliver 1 H-1 main rotor gearbox test stand, and 1 H-1 tail rotor/intermediate gearbox test stand. The contract includes logistics support, maintenance efforts, follow-on support, and associated data. This is unsexy, but experience in countries like Pakistan demonstrates that unless this infrastructure is in place and in use, helicopters will remain in place and not in use.

Work will be performed in Hurst, TX using FY 2011 procurement funds, and is expected to be complete in March 2017. All funds expire at the end of FY 2013, on Sept 30/13. This contract was not competitively procured pursuant to FAR 6.302-1. by the US Naval Air Warfare Center Aircraft Division in Lakehurst, NJ (N68335-13-C-0302).

June 18/13: Lot 10. A $38.8 million option order for 2 more new-build AH-1Z Vipers in Lot 10, whose main order was Dec 12/12. All funds are committed immediately, using FY 2013 procurement budgets. This brings that lot’s totals to 15 UH-1Ys and 12 AH-1Zs, with 1 AH-1Z option remaining.

Note that this doesn’t provide the full cost of 2 Vipers, and the USN places average flyaway costs for Lot 10 H-1 machines at over $26 million each. The difference will be made up via previous long-lead buys, and/or additional awards. Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%), and is expected to be complete in September 2013 (N00019-12-C-0009).

June 18/13: Weapons. US NAVAIR touts the work of their PMA-242’s Crew Served Weapons Integration team, who redesigned the UH-1Y’s weapon mount to improve maximum elevation. That’s useful if you’re on or near the ground, being fired on from hills. In effect, the UH-1Y door gunner’s field of fire is now on par with the UH-1N in terms of overall range, azimuth and elevation.

Testing began in May 2013, and will continue at Pax River, MD for another 6 months or so. The USMC expects to deploy the new mounts to Afghanistan by the end of 2013. US NAVAIR.

May 28/13: Lot 11. Bell Helicopter Textron Inc. in Fort Worth, TX receives a $50.6 million advance acquisition contract modification for long-lead parts and components required for 25 Production Lot 11 helicopters: 15 UH-1Ys and 10 AH-1Zs, all new-build. All funds are committed immediately.

Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%), and is expected to be complete in September 2014 (N00019-13-C-0023).

April 17/13: South Korea loss. South Korea announces that the AH-64E Apache Guardian has beaten the AH-1Z Viper and T-129 ATAK helicopters for a 1.8 trillion won ($1.6 billion), 36-machine order. The attack helicopter decision had been due in October 2012, but was put on hold until after the elections. The ROK hopes to have the helicopters between 2016 and 2018.

The AH-1Z would have represented continuity with the existing AH-1S fleet, and a DSCA export request was already approved (vid. Sept 25/12). The Italo-Turkish T-129 would have been a reciprocal deal with a major arms export customer. A DAPA official is quoted as saying that the AH-64E’s superior target acquisition capability, power, and weapons load gave it the edge, and so South Korea will begin the acquisition process. The weapons load issue is debatable, but the Apache is certainly much more heavily armored than its counterparts, and its combination of modernized optics and MMW radar or UAV control does give it an edge in target acquisition. Korea Herald | Reuters.

Loss in South Korea

April 10/13: FY 2014 Budget. The President releases a proposed budget at last, the latest in modern memory. The Senate and House were already working on budgets in his absence, but the Pentagon’s submission is actually important to proceedings going forward. See ongoing DID coverage.

The H-1 program is cut slightly from 26 total helicopters to 25 this year, as part of a longer-term set of slight reductions that will stretch out the program. FY 2014 drops from 26 – 25, FY 2015 drops from 27 – 26, FY 2016 drops from 31 – 27, and FY 2017 drops from 30 – 28. An order of 30 helicopters in FY 2018 leaves just 30 more to close out the program.

The key will be where reductions are focused. The AH-1Z is behind due to delays, so these and other cuts at the end of the program will force the Marines to decide whether they want fewer attack helicopters in the future force, as they contemplate adjustments to the production split. Especially if future budget pressures cut these planned numbers again. The alternative is to stretch production into later years, but that will raise total costs because the fixed costs come due for more years of work.

April 1/13: Lot 11 long-lead. A $13 million advance acquisition contract to provide long-lead parts and components required for Production Lot 11’s 15 UH-1Ys and 10 AH-1Zs. All are new-build helicopters – Lot 9 held the last remanufactured helicopters.

Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%), and is expected to be complete in September 2014. All funds are committed immediately, using the FY 2013 Aircraft Procurement, Navy budget line. This contract was not competitively procured, pursuant to FAR 6.302-1 (N00019-13-C-0023).

Jan 16/13: Milestone. Bell Helicopter delivers the 100th H-1 upgrade helicopter to the US Marine Corps.

Bell Helicopter has since confirmed that it was a UH-1Y. Bell Helicopter | Fort Worth Star-Telegram Sky Talk.

#100

Jan 17/13: DOT&E testing. The Pentagon releases the FY 2012 Annual Report from its Office of the Director, Operational Test & Evaluation (DOT&E). The H-1 program is only included in passing, but it’s an interesting reference:

“The U.S. Army Aviation Applied Technology Directorate led a project to manufacture complex, curved ceramic armor for placement at strategic locations on aircraft, improving survivability with minimal weight impact. These installations protect flight-critical aircraft components that when damaged would lead to catastrophic aircraft loss. Due to their complexity, these structurally integrated panels required development of several cutting-edge material and processing technologies. Two implementations were demonstrated: the OH-58D Kiowa Warrior engine bay door and the AH-1Z Cobra helicopter flight control linkage bell-crank.”

Dec 27/12: Lot 10. A $418.9 million contract related to the FY 2012 order: 15 UH-1Y helicopters and 10 AH-1Zs. All helicopters will be new-build, and there are options for another 3 AH-1Zs. Two of those options were exercised on June 18/13, to make 12 AH-1Zs ordered.

The actual wording is “for the procurement of long lead parts and components required for the manufacture of…”, but NAVAIR has confirmed that this is the main Lot 10 order, covering FY 2013 helicopters for the most part. Work will be performed in Fort Worth, TX (60%) and Amarillo, TX (40%) and is expected to be complete in March 2016. All contract funds are committed immediately (N00019-12-C-0009).

Lot 10 order

Dec 20/12: Support. A $15.3 million firm-fixed-price, cost-plus-fixed-fee advance acquisition contract modification. Bell Helicopter will provide H-1 Upgrade Program systems engineering and program management services.

Work will be performed in Hurst, TX and is expected to be complete in December 2013. All contract funds are committed immediately (N00019-12-C-0009).

Dec 20/12: Support. A $12.3 million to a previously awarded firm-fixed-price, cost-plus-fixed-fee contract modification to support of the H-1 Upgrade effort. Work will include logistics management support, technical material for maintenance planning, design interface, supply/material support; support of support equipment/technical data, distribution and inventory management/packaging; handling, storage and transportation; logistics management information; supportability analysis and technical manuals.

All contract funds are committed immediately. Work will be performed in Fort Worth, TX, and is expected to be complete in December 2013 (N00019-11-C-0023).

Nov 20/12: HUMS. Simmonds Precision Products Inc. (dba Goodrich Sensors and Integrated Systems in Vergennes, VT) receives a $6.9 million modification to a previously awarded firm-fixed-price contract, exercising an option for 28 integrated AH-1Z/UH-1Y mechanical diagnostic and health usage monitoring system kits.

This would appear to cover FY 2013 production: 13 AH-1Zs and 15 UH-1Ys. HUMS systems are undervalued by causal observers, but they pay for themselves very, very quickly via more cost-effective maintenance and higher in-service rates.

Work will be performed in Vergennes, VT, and is expected to be complete in May 2014. All contract funds are committed. US Naval Air Systems Command, Patuxent River, Md., is the contracting activity (N00019-12-F-4003).

Nov 6/12: Mission Computers. Northrop Grumman Guidance and Electronics Co., Inc. in Woodland Hills, CA receives a $9.3 million firm-fixed-price modification for 54 GEN II mission computers and trays, per the new buying arrangements (vid. Dec 29/11 entry). They’ll be used in Production Lot 10, which is mostly FY 2013 buys.

Work will be performed in Salt Lake City, UT, and is expected to be complete in January 2015. US Naval Air Systems Command in Patuxent River, MD (N00019-11-G-0016).

Oct 16/12: Lot 9. A $391.4 million firm-fixed-price contract modification. As we saw on July 25/11, the Pentagon’s turgid language involving “definitization… to provide long lead parts” means that it’s the main Production Lot 9 (mostly FY 2012) buy, which is added to the previous contracts for long lead time components. US NAVAIR places the total Lot 9 contract at $447.8 million, plus any separately bought “government furnished equipment” like the T700 engines, mission computers (vid. Dec 29/11 entry), weapons and mounts, defensive systems, etc. Those “extras” add up.

The contract covers 15 new UH-1Ys (all new) and 10 AH-1Zs (3 remanufactured, 7 new). According to NAVAIR, Lot 9 will be the final production lot that will include remanufactured AH-1Z aircraft.

Work will be performed in Fort Worth, Texas (60%) and Amarillo, TX (40%), and is expected to be completed in July 2015 (N00019-11-C-0023).

Lot 9 order

FY 2012

Orders; AH-1Z competes in South Korea; AH-1Z maiden operational deployment; AH-1W swap to Turkey; UH-1Ys using precision rockets.

UH-1Y & AH-1Z
(click to view full)

Sept 25/12: South Korea. The US Defense Security Cooperation Agency announces [PDF] South Korea’s request to buy up to 36 AH-1Z Viper attack helicopters and associated equipment, parts, training and logistical support. The cost would be up to $2.6 billion, but this isn’t a contract. It doesn’t even mean that the AH-1Z is the ROK’s choice. South Korea is conducting a competition to replace its attack helicopters, and the DSCA request will make sure that everything the ROK wants is available if the AH-1Z is picked.

They appear to have picked the AH-1Z as the American contender, even though the AH-64D Apache Block III’s fuselage is made locally by KAI. That still leaves 2 more strong contenders. EADS Eurocopter is already producing Surion medium helicopters under a Korean Joint Venture, and is offering their EC665 Tiger attack helicopter. It’s in service with France, Germany, Spain, and Australia. The other contender is AgustaWestland/TAI’s T129, which is now a joint Italian/Turkish venture. Turkey is South Korea’s biggest defense export customer by far, and a loss could ruffle some important feathers. As for the AH-1Z, the DSCA request includes:

36 AH-1Z Viper attack helicopters

84 T-700-GE-401C Engines (72 installed and 12 spares)

Integrated missile launchers

288 AGM-114K3 Hellfire laser-guided strike missiles

72 AIM-9M-8 Sidewinder air-air missiles. The missile’s range and performance are superior to weapons carried on other helicopters.

AN/AAQ-30 Target Sighting Systems (TSS)

APX-123 Identify Friend or Foe (IFF) Mode-4

Electronic warfare systems: AN/ALQ-136 Radar Frequency Jammers, AN/AAR-47 Missile Warning System, AN/ALQ-144 Infrared Jammer, AN/ALE-47 Chaff and Flare Decoy Dispenser

Communication and support equipment, spare engine containers, spare and repair parts, tools and test equipment, technical data and publications, personnel training and training equipment, and other US government and contractor support.

The prime contractors will be Bell-Textron Corporation in Amarillo, TX (helicopter), and General Electric in Lynn, MA (engines), though many of the ancillary items will come from firms like Lockheed Martin, Raytheon, BAE, et. al. Implementation will require multiple trips to Korea involving U.S. Government or contractor representatives on a temporary basis for program and technical support, and management oversight.

South Korea request

Sept 25/12: Training. A $44.7 million firm-fixed-price contract to buy 2 UH-1Y Flight Training Devices (simulators) for the US Marine Corps. In addition, this contract provides for the baseline configuration upgrade to create an AH-1Z FTD from the previous AH-1W simulator.

Work will be performed in Fort Worth, TX (46%); Broken Arrow, OK (32.4%); St. Louis, MO (16.2%); and Austin, TX (5.4%), and is expected to be complete in March 2015. $19.8 million will expire at the end of the current fiscal year, on Sept 30/12. This contract was not competitively procured pursuant to 10 U.S.C. 2304c1 by the US Naval Air Warfare Center Training Systems Division in Orlando, FL (N61340-12-C-0030).

April 3/12: Buy direct. US NAVAIR has made a slight acquisition shift, and is now ordering mission computers for the UH-1Y and AH-1Z directly from Northrop Grumman, instead of through prime contractor Bell Helicopter. Under the initial $8.9 million contract, Northrop Grumman will provide Gen II mission computers to the U.S. Marine Corps Light Attack Helicopter Program (PMA-276) directly, reducing the item’s price.

The dual mission computers are the heart of Northrop Grumman’s Integrated Avionics System (IAS) that powers the helicopters’ glass cockpits. Northrop Grumman.

Mission computers direct

March 2012: Laser-guided rockets. The APKWS laser-guided 70mm rocket is cleared for fielding by Marine Corps HQ, and shipped to Afghanistan. The rockets will initially be deployed in existing rocket launchers on USMC AH-1W Super Cobra attack helicopters, and UH-1Y Venom utility helicopters. It will be the UH-1Ys first precision-guided weapon, dramatically increasing its firepower.

BAE cites cite over 100 APKWS firings since 2007, with a 94% success rate, and an average distance from the center of laser spot to the impact point of less than one meter. US NAVAIR | BAE Systems.

Feb 13/12: FY 2013 request. The Pentagon releases its budget. FY 2013 would see it spend up to $851.5 million to buy 15 new-build UH-1Ys, and 13 AH-1Zs (4 remanufactured, 8 new, 1 new combat loss replacement). Over the longer term, the H-1 Upgrades program also escapes budget cuts.

Feb 13/12: A $56.75 million advance acquisition contract to provide long lead parts and components required for the manufacture of H-1 upgrade Lot 10 UH-1Y (15) and AH-1Z (13) helicopters. As noted above, correspondences aren’t exact, but these are mostly FY 2013 helicopters.

Work will be performed in Fort Worth, TX (60%), and Amarillo, TX (40%), and is expected to be complete in September 2013. This contract was not competitively procured pursuant to FAR 6.302-1 (N00019-12-C-0009).

Dec 28/11: A $20.4 million firm-fixed-price, cost-plus-fixed-fee contract modification, exercising an option for H-1 upgrade program logistics management support; distribution and inventory management/packaging, handling, storage & transportation; logistics management information; technical material for maintenance planning; design interface; supply/material support; technical data, support of support equipment; technical data; supportability analysis; technical manuals and logistics/technical liaison support.

Work will be performed in Fort Worth, TX (96%) and Afghanistan (4%) and is expected to be complete in December 2012 (N00019-10-C-0035).

Dec 27/11: Northrop Grumman Guidance and Electronics Co., Inc. in Woodland Hills, CA received an $8.9 million firm-fixed-price delivery order for 52 GEN II mission computers, which will be used in H-1 upgrade production Lot 9 (mostly FY 2012). Work will be performed in Woodland, CA, and is expected to be complete in January 2014 (N00019-11-G-0016).

Dec 13/11: Bell Helicopter Textron, Inc. in Fort Worth, TX received a $13.9 million firm-fixed-price, cost-plus-fixed-fee contract modification for systems engineering and program management work related to AH-1Z and UH-1Y production aircraft. Work will be performed in Fort Worth, TX and will run to December 2012 (N00019-11-C-0023).

Dec 8/11: An $85.2 million cost-plus-fixed-fee, firm-fixed-price, indefinite-delivery/ indefinite-quantity contract for design, development, studies, and implementation of upgrades to existing H-1 software and ancillary hardware, and/or improved functionality and electronics obsolescence management. Since the H-1 upgrades are designed to use the same cockpit electronics, investments in upgrades can benefit the whole fleet. As noted above, Northrop Grumman in the main sub-contractor for all cockpit systems.

Work will be performed in Woodland Hills, CA (70%); Hurst, TX (25%); and China Lake, CA (5%), and will run to December 2014. This contract was not competitively procured pursuant to 10 U.S.C. 2304c1. The US Naval Air Warfare Center Weapons Division at China Lake, CA manages this contract (N68936-12-D-0003).

Dec 5/11: Lockheed Martin announces a pair of AN/AAQ-30 TSS spares and AH-1Z program support contracts from the US Naval Surface Warfare Center. Their release distinguishes these $30.6 million in support contracts for the AH-1Z’s surveillance and targeting turrets, from the TSS production contracts in March 2008, June 2010, and September 2011.

Nov 14/11: When USS Makin Island sailed on her maiden deployment, she sailed with the 1st operational deployment of AH-1Z Viper attack helicopters. The 4 AH-1s and 3 UH-1Ys function as a detachment of Marine Light Attack Helicopter Squadron 367 (HMLA-367). NGC put out the release, to tout the common “Integrated Avionics System” cockpits that equip both helicopters.

AH-1Z deployment

Oct 31/11: Turkish swap. With Turkey’s fleet of serviceable AH-1 Cobra attack helicopters dwindling, demands from the Army for helicopters to use against the Marxist Kurdish PKK in Turkey and Iraq, and no arrival of even its emergency configuration T129 attack helicopters before mid-2012, Turkey launches an official request [PDF] for 3 AH-1W Super Cobra attack helicopters from US Marine Corps stocks. They’ll also get 7 T700-GE-401 engines (6 installed/ 1 spare), plus inspections and modifications, spare and repair parts, personnel training and training equipment, publications and technical documentation, and U.S. Government and contractor support.

The estimated cost is $111 million, and all sale proceeds will be reprogrammed into the USMC’s H-1 helicopter upgrade program. Implementation of this proposed sale will require the assignment of approximately 5 contractor representatives to Turkey for a period of up to 90 days, for differences training between U.S. and Turkish AH-1Ws helicopters.

FY 2011

Orders; AH-1Z achieves IOC, bull Full Operational Capability not until 2020; AH-1Z approved for Full-Rate Production; AH-1Z export strategy.

UH-1Y, Afghanistan
(click to view full)

Sept 27/11: Sensors. Lockheed Martin Missiles and Fire Control in Orlando, FL receives a $16.7 million firm-fixed-price contract for 6 spare AN/AAQ-30 surveillance and targeting turrets for the AH-1Z Viper attack helicopter.

Work will be performed in Orlando, FL (90%), Ocala, FL (10%), and is expected to be complete by December 2014. This contract was not competitively procured by the US Naval Surface Warfare Center, Crane Division in Crane, IN (N00164-11-G-JQ97).

Sept 22/11: Rotor redesign. A $10 million cost-plus-fixed-fee delivery order to develop the H-1 cuff and yoke redesign, but not mass-produce it yet. These important parts of the rotor were falling well short of their expected service life, and this delivery order will include initiating the design-build-buy activities; part/drawing release; support analysis for detailed design, preparation, execution, and follow up for preliminary design review; process development for yoke full-scale process and drive system center; complete tooling conceptual designs and initiate tooling preliminary design; structural qualification; and flight test plans requirements.

Work will be performed in Fort Worth, TX, and is expected to be complete in May 2013 (N00019-11-G-0003). See also March 2/11 entry.

Aug 30/11: Sensors. Lockheed Martin Missiles and Fire Control in Orlando, FL receives a $50 million firm-fixed-price contract for 18 of the AH-1Z’s AN/AAQ-30 target sight systems (TSS). The DefenseLINK release identifies them as being specifically for the AH-1Z program; they are also found on armed C-130s operated by the USMC and US SOCOM.

Work will be performed in Orlando, FL (90%) and Ocala, FL (10%), and is expected to be complete by August 2014. The contract was not competitively procured, in accordance with 10 U.S.C. 2304c1 and FAR 6.203-1b-1-ii. The Naval Surface Warfare Center, Crane Division in Crane, IN manages the contract (N00164-11-C-JQ77).

Aug 25/11: Innovation. USMC Sgt. Zachary Lucas gets a Navy and Marine Corps Achievement Medal and a $5,000 check for inventing the “Lucas Seat” that’s now standard issue on UH-1Ys.

The helicopter’s 3 seats in the center were getting in the way of employing the door guns and tending the packs, so Lucas designed a 2-man bed seat while serving in Afghanistan, in 2009. It passed through some iterations on its way to becoming a Corps-wide issue, and the current configuration allows for a 3-man bench seat or a single seat.

Lucas’ peers are currently developing a hold-down map rack to install in the center area between pilots and the crew, making it easier for the crew to read them while the helicopter is in flight. Pentagon DVIDS.

The Lucas Seat

July 25/11: A $550 million firm-fixed-price modification that lists itself as being “for long lead materials and components associated with” the manufacture and delivery of 35 helicopters: 19 UH-1Y Lot 8 new-build, 8 AH-1Z remanufactured, and 6 AH-1Z Lot 8 new-build helicopters.

In reality, this modification is the “production definitization” of the Lot 8 Advance Acquisition Contract. In English: It’s the main Lot 8/ FY 2011 contract. Now, why couldn’t they just say that? See Feb 5/10 entry for the accompanying partial long lead-time items contract, of $50.4 million. That makes $600.4 million so far for 35 helicopters, not including items like key electronics, sensors, etc. Work will be performed in Fort Worth, TX (60%), and Amarillo, TX (40%), and is expected to be complete in February 2014 (N00019-10-C-0015).

FY 2011 order

June 6/11: FY 2012 lead-in. A $7.2 million contract modification to buy Lot 9 long-lead items for the USMC’s H-1 Upgrades Program. Per notes above, Lot 9 mostly involves FY 2012 purchases. See also March 14/11.

Work will be performed in Fort Worth, TX (60%), and Amarillo, TX (40%), and is expected to be complete in September 2012 (N00019-11-C-0023).

March 16/11: Sub-contractors. Simmonds Precision Products, Inc., dba Goodrich Corp. in Vergennes, VT receives a $7.4 million firm-fixed-price contract for 30 integrated mechanical diagnostic and health usag

Show more