NH90: TTH & NFH
(click to view full)
The NH90 emerged from a requirement that created a NATO helicopter development and procurement agency in 1992 and, at almost the same time, established NH Industries (62.5% EADS Eurocopter, 32.5% AgustaWestland, and 5% Stork Fokker) to build the hardware. The NATO Frigate Helicopter was originally developed to fit between light naval helicopters like AW’s Lynx or Eurocopter’s Panther, and medium-heavy naval helicopters like the European EH101. A quick look at the NFH design showed definite possibilities as a troop transport helicopter, however, and soon the NH90 project had branched into 2 versions, with more to follow.
The nearest equivalent would be Sikorsky’s popular H-60 Seahawk/ Black Hawk family, but the NH90 includes a set of innovative features that give it some distinguishing selling points. Its combination of corrosion-proofing, lower maintenance, greater troop or load capacity, and the flexibility offered by that rear ramp have made the NH90 a popular global competitor.
As many business people discover the hard way, however, success can be almost as dangerous as failure. NH Industries has had great difficulty ramping up production fast enough to meet promised deliveries, which has left several buyers upset. Certification and acceptance have also been slow, with very few NH90s in service over a decade after the first contracts were signed. Booked orders have actually been sliding backward over the last year, and currently stand at around 500 machines, on behalf of 14 nations.
Program Summary
NH90: TTH & NFH
The NH90 began life as a leap-ahead competitor that would create a compelling alternative to Sikorsky’s 1980-era H-60 family airframe designs, as a European joint venture involving Airbus, AgustaWestland, and Stork Fokker. Their design has achieved respectable sales success, especially in Europe, but a bevy of technical and industrial issues have blunted its potential.
Orders as of late 2014 stood at 513 machines, in an array of structural and equipment customizations that reach beyond the simple division of naval NFH vs. army TTH. Customers to date include Australia, Belgium, Finland, France, Germany, Greece, Italy, New Zealand, Netherlands, Oman, Norway, Portugal, Qatar, Spain, and Sweden. Customer charts and timelines can be found below.
On the flip side, the NH90 has lost competitions in existing customer countries (Australia naval, Norway SAR, Sweden CSAR), and has received several cancellation threats to go with Portugal’s withdrawal from the program in 2012. Orders and certifications have often been years behind promises, full functionality wasn’t always present in delivered helicopters, and a number of performance complaints trace back to the helicopter’s specifications, which makes them hard to fix. Experience in the field has added engine issues, the TopOwl helmet-mounted display, and unexpected corrosion to the list of concerns. The NH Industries consortium needs to address these issues, and rack up convincing customer testimonials. Otherwise, the NH90 will struggle in the export marketplace against America’s Sikorsky, Russian Helicopters Company, and rival offerings from some NHI member firms.
The NH90 Platform(s)
NH90 cockpit
(click to view full)
NH Industries’ design makes extensive use of composite materials instead of riveted metal alloy plates, which makes the helicopter lighter and was supposed to reduce routine maintenance and corrosion issues. On the other hand, it also creates potential issues with damage in the field, and with durability. Germany in particular has complained that the composite body is essentially too flimsy for normal infantry use, or the carriage of heavy items. Time will tell if these issues can be fixed.
Electronic fly-by-wire systems also contribute to the NH0’s lift capacity, by saving the weight of heavy power-boosted hydraulic control systems. This allows the NH90 to remain within the 10-tonne weight class, while carrying about 50% more troops or stretchers than its American UH-60 counterpart. A pair of Rolls-Royce Turbomeca RTM322 engines delivering 2,412 – 2,544 shp, GE T700-T6Es delivering 2,269 – 2,380 shp, or GE CT7-8F5s delivering up to 2,520 shp at sea level, power the aircraft. At present, RTM322-powered NH90s have been sold to Australia, Belgium, Finland, France, Germany, Greece, the Netherlands, Norway, New Zealand, Portugal and Sweden; Oman uses a special RTM322 variant certified for very hot and high altitude conditions, where engine power must compensate for thinner air. Spain (CT7-8F5) and Italy (T700-T6E) use GE’s engines instead.
The NH90’s physical dimensions were intended to take advantage of that extra power. Removal of the C-130 air-portability requirement that constrained the H-60 family’s height let NH Industries expand the NH90’s cargo area size. Features like dual-side exits and an optional rear ramp let the 10-tonne helicopter carry light vehicles or small boats internally, load MEDEVAC stretchers smoothly, drop search-and-rescue swimmers out back, etc.
Built for what NH Industrie calls “extreme adverse weather” operations, the NH90 can start up and fly, land, and shut down in winds gusting up to around 110 km/h without losing rotor control, flying day and night in heavy icing conditions down to temperatures of -30 C/ -22 F. Normal maximum range is approximately 200 nautical miles/ 370 km, or up to 300 nm/ 555 km using internal and/or external auxiliary tanks.
Advanced avionics and other standard features round out these helicopters, with frequent local customization in the electronics area. Accompanying surveillance and/or targeting turrets are standard features, and Thales’ TopOwl helmet-mounted display helps pilots take full advantage, though some complaints have been reported about its weight. An EADS Defence Electronics/Thales partnership will deliver a standard Electronic Warfare Suite comprising a missile approach warning system, laser warning receiver, radar warner, central processing unit, and chaff/flare dispenser. This EWS has been selected by Australia, Finland, France, Germany, Italy, and Portugal, at minimum. Sweden is known to have their own Saab suite instead, and Norway uses ITT’s popular AN/ALQ-211.
NH90 Variants
NH90 NFH
(click to view full)
The NH90 is produced in 2 main variants: Tactical Transport Helicopter for troops (NH90 TTH), and the NATO Frigate Helicopter for naval utility and anti-submarine (NH90 NFH). One problem for NHI is that national customizations have created a tremendous number of sub-variants, impacting production and modernization. This article will only look at the broad variants and major kits.
NH90 TTH. The base variant for land and air forces. It can carry 12-20 troops (depending on equipment level), and normal load is up to 2.5 tonnes/ 5,500 pounds inside.
An optional High Cabin Version (HCV) raises the cabin height from 1.58m to 1.82m, increasing volume from 15 to 17.5 cubic meters. The high cabin is especially helpful for long search and rescue operations, or MEDEVAC flights where medical personnel need to be able to stand up and move freely.
Equipment can be added to create the NH90 Special Operations configuration (NH90 SOF, generally based on NH90 TTH), and MEDEVAC and CSAR (combat search and rescue) fit-out kits are also available. The NH90 FAME MEDEVAC variant adds 2 intensive care bays for treating wounded personnel, on-board equipment, and seats for the medical team. Options for the NH90 CSAR kit include up to 3 machine guns (each side door and the tail ramp), extra ballistic protection, a rappel system, a double rescue hoist, an emergency flotation system, sand filters, an obstacle warning system, and improved self-protection electronics.
The NH90 NFH. The naval variant can be used as a utility helicopter like the TTH, or as an anti-submarine helicopter, depending on how they’re built. ASW helicopters will add a naval radar (Thales ENR or Telephonics Ocean Eye), a dipping sonar (Thales FLASH or L-3’s HELRAS), sonobuoys, a magnetic anomaly detector, and up to 2 MBDA Marte Mk.2/S light anti-ship missiles or torpedoes (Eurotorp MU90, Raytheon Mk.46, or BAE Stingray) on side pylons. The Franco-British Sea Venom/ ANL light anti-ship missile may join the Marte around 2020, and work is already underway to add MBDA’s longer-range Marte-ER anti-ship missile as a nearer-term addition.
NH90: The Competition
UH-60, Iraq
(click to view full)
The NH90’s nearest comparable serving helicopter is probably the American H-60 Black Hawk/ Seahawk family, a 10-tonne helicopter flying since 1979 that remains America’s current and future mainstay helicopter for its Army (UH-60M, S-70i) and Navy (MH-60R/S, S-70B). Within its 10 tonnes of maximum takeoff weight, the Black Hawk normally carries 11 equipped troops to a normal maximum range of around 550 km/ 330 miles. Unlike the NH90, the H-60 family has no rear ramp, which means vehicles must be attached using a hook and sling system that sharply cuts the helicopter’s range, maneuverability, and maximum speed.
While the H-60 family remains popular, Sikorsky has felt the pressure of the implicit comparisons. Their new UH-60 derived H-92 Superhawk, a heavier aircraft that makes heavy use of composite materials, features a rear ramp, and has a higher cargo capacity than the smaller H-60 series. It has been selected by Canada’s Navy (28 helicopters), and is in use a civilian and VIP transport helicopter.
Mi-17
(click to view full)
Even within the NH Industries consortium, competition is emerging for the NH90. Airbus Helicopters’ EC725 offers a slightly larger machine with links to existing fleets of AS332 and AS552 Puma Family machines in service around the world. Meanwhile, AgustaWestland has several customers for its medium-heavy AW101, including NH90 customer Norway’s new search-and-rescue fleet.
Beyond the West, Russia Helicopter Company competes all over the world, and its Mi-17 family remains very popular in the NH90-TTH’s market class.
The NH90 Production Program
NH90 manufacture
(click to view full)
The first NH90 series production helicopter made its maiden flight in May 2004, but the first acceptance by a customer didn’t take place until 3 NH90 TTH were accepted by Germany on Dec 13/06. Even so, it would be many years before Germany could declare Full Operational Capability, and other countries that ordered early have been faced with even longer waits. Portugal ordered NH90s in 2001, and canceled in 2012 without a single machine delivered. Customer acceptances for the NH90 NFH naval variant were expected to begin in the second half of 2009, but actually began in mid-2010, and Final Operational Capability wasn’t present until late 2013.
The NH90’s NAHEMO international program organization consists of 5 countries: France, Germany, Italy, The Netherlands, and Belgium (2007). Portugal dropped out in 2012. Others may be customers, but they aren’t full program partners. Other key players include:
NAHEMA. NATO Helicopter Management Agency represents the national customers, just as NAHEMO represents the national producers. NAHEMA acts as the single contact with NH Industries for the negotiation, attribution and execution of the primary contracts. They also handle qualification of all weapon systems.
NHIndustries. The Eurocopter/ AgustaWestland/ Stork Fokker joint venture. It acts as the prime contractor, responsible for the design, development, industrialization and production of the NH90, including program management, order sub-contracting, marketing, sales, and support for helicopters in service worldwide. It’s also the owner of the helicopter’s type certification. The NH90’s 3 main assembly lines, and their general work share items, are:
Base workshare
(click to view full)
Eurocopter France in Marignane, France: Powerplant & section, rotors, electrical systems, flight controls, central avionics.
Eurocopter Deutschland GmbH in Donauworth, Germany: Central sections, fuel, communications, avionics control. Lead for TTH tactical transport, and makes nose sections until Spain’s plant reaches full production.
AgustaWestland in Cascina Costa, Italy: Tail cone and drive shaft, main gearbox, automatic flight control, hydraulics, electric system, rear ramp, rear fuselage, installation monitoring systems. They are alternates for engine installation, and the lead for NFH mission packages & installation and the construction and flight testing of the naval prototype. AgustaWestland has final assembly line responsibility for all TTH and NFH helicopters to be procured by the Italian Army and Navy, and for the Dutch and Norwegian NH90 NFH helicopters as well, for a grand total of 150 helicopters so far.
Stork Fokker, the Netherlands: This isn’t a main assembly line, but they’re a founding partner with responsibility for the tail boom, doors, flotation boxes, landing gear, and intermediate tail gearbox.
The Nordic countries ordered 52 NH90 helicopters with an option for 17, and Patria Oyj runs the final assembly line in Halli, Jamsa, Finland as a subcontractor to Airbus Helicopters in Marignane. The Finnish assembly line was the 4th operational assembling line for the NH90, handling final assembly for all Finnish and Swedish NH90s. Per subsequent agreements, there have also been assembly lines in Albacete, Spain (Eurocopter Espana, will manufacture nose sections for all NH90s) and Brisbane, Australia (Eurocopter subsidiary Australian Aerospace), fir a total of 6.
At present, NH Industries’ orders total 513, with around 40 live options available as possible future orders. The breakdown is:
Over the past year or so, Portugal has canceled its buy of 10 helicopters, Germany cut its orders by 40 machines, and Spain decided to reduce its contract by half to 22. Greece’s contract for 20 has also been in question, with just 4 helicopters delivered nearly 9 years after the order was placed. On the bright side, Qatar became the first new customer in a long time, with a mixed order for 22 in 2014.
A timeline of NH90 customers and their key decisions follows:
Contracts & Key Events
2015 – 2016
New order to Germany; Belgium fleet achieves IOC
January 11/16: After extensive use in operations in Mali, France is to procure seven more NH90 military helicopters. The latest addition brings their total order to seventy-four. Two variants of the helicopter are to be used; the Tactical Transport Helicopter (TTH), for use by the French Army, and the navalized NATO Frigate Helicopter (NFH) for the French Navy. Forty-four TTH and twenty-seven NFH will be delivered and operational by 2019. At $31 million per chopper, the latest to be ordered will all see service across five partner nations in Africa’s Sahel region.
December 21/15: The first of Sweden’s NHIndustries’ NH-90 Anti-Submarine Warfare (ASW) variant helicopter has been delivered. The Swedish Air Force hopes to have nine out of a total eighteen NH-90s ordered to have ASW capabilities. The delivery coincides with the the Swedish procurement agency, FMW, signing an agreement with NHI to convert four existing NH-90 Search and Rescue variants to have ASW capabilities.
October 7/15: Egypt and France are reportedly engaged in talks over a potential acquisition of NH90 helicopters. With Egypt recently purchasing a significant quantity of French naval hardware with Saudi funding – including Gowind corvettes and a FREMM frigate – with which the NH90 would be compatible, the precise model being discussed could be the naval NFH variant, or a mix of NFH and TTH troop transport variants. Egypt signed a contract to buy the two Mistral LHDs formerly destined for Russia, with reports indicating that the country had also ordered Ka-52 navalized attack helicopters from Russia to equip the new vessels; however, these reports now appear to have been erroneous, with Russian officials now denying that an order has been placed.
August 25/15: Belgium’s four NH90 NFH naval helicopter fleet have achieved Initial Operating Capability, eight years after they were ordered in May 2007 through a mixed order for ten NH90 helicopters. Three of the country’s four helicopters have now entered service, with a fourth scheduled to join them in early 2016.
June 22/15: Belgium’s fleet of NH90 tactical transport helicopters has achieved Initial Operating Capability, following a procurement contract in 2007. The fourth and final NH90 helicopter was handed to the Belgian military last November. The country has also ordered four naval variants of the helicopter. France announced last week that it intends to modify some of its NH90s for Special Forces use, including installing electro-optic/infrared (EO/IR) systems and data links.
March 6/15: New order to Germany. Despite the spontaneous combustion issue, Germany remains committed to the NH90, signing a deal for 18 new helicopters for its navy.
Feb 8/15: Germany is no longer putting happy face on NH90 issues; demanding Airbus fix the mess, which apparently involves a manufacturer-admitted “design flaw.” A February 6 statement(German): “The MoD now expects soon as possible the elimination of the problem by the manufacturer.” Analysts and the press are griping that the Bundeswehr didn’t play it straight.
2014
Qatar orders 22; New Zealand completes 2006 order; Finalist in India; Dutch, Germans, French have a problems with NH90 corrosion; Dutch suspend deliveries; German engine explosion suggests a troubling flaw; Marte-ER integration work would give the NH90-NFH a full anti-ship missile.
Nov. 26/14: Fluganst doesn’t stop deal. Germany’s defense ministry came to an agreement with NHI, following cuts announced in March 2013 whose structure didn’t fully satisfy defense minister Ursula von der Leyen and had been put on ice. The new master contract, worth about €8.5B ($10.5B) settles on 80 NH90s for the Army, 18 for the Navy, and 22 options that the Germans are now pitching to NATO countries as a Germany-based pooled resource. A previous order for 80 Tigers is cut down under this same deal, with a final operational fleet of only 40 Tigers. This still needs to be approved in Parliament, and get traction among alliance partners.
Earlier in November the Bundeswehr had lifted a flight ban on NH90s after concluding that the June incident in Uzbekistan was an isolated problem. But the Frankfurter Allgemeine Zeitung reports that pilots are afraid safety issues are glossed over for political reasons. Fluganst (flight fear) is a more dangerous condition than Schadenfreude when your job is to fly helicopters.
Sources: Der Spiegel: Von der Leyen beendet Hubschrauber-Chaos | FAZ: Flugangst [both in German].
German cuts formalized
NH90 & Marte 2/S
(click to view full)
Oct 31/14: New Zealand. More than 8 years after New Zealand’s order for 9
NH90-TTH helicopters (q.v. July 31/06), the last NH90 arrives at RNZAF Base Ohakea on North Island. Sources: IHS Jane’s Defence Weekly, “New Zealand receives final NH90 helo”.
Final NZ delivery
Oct 31/14: Netherlands. Defence minister Jeanine Hennis-Plasschaert report to the legislature that delays caused by late NH90-NFH deliveries and corrosion issues will cost the Dutch another EUR 105.8 million to keep the existing Eurocopter AS532 Super Puma fleet flying, on top of EUR 1.2 billion for the 20 NH90s. Neighboring Belgium has had a similar experience with its H-3s (q.v. June 6/13).
So far, the Dutch have accepted 13 NH90-NFHs, but deliveries remain suspended (q.v. June 27/14) until the corrosion problem is fixed. The Dutch MvD now expects to have a solution and finish negotiations over who should pay for this by the end of 2014 – a bit of slip from the June forecast of September 2014. The last Dutch NH90 is now scheduled for delivery in 2016. Sources: Flightglobal, “Dutch NH90 delays cost government more than €100 million”.
Oct 24/14: Germany. German media report that a June 2014 NH90 MEDEVAC flight from Uzbekistan to Afghanistan had to make an emergency landing in Termes, Uzbekistan after an engine exploded shortly after takeoff. Most electronic systems immediately failed, and the landing was a narrow escape for the pilots. The NH90 remains in place, until it can be repaired well enough for a short flight to Mazar-i-Sharif, Afghanistan, and be transported out in a leased SALIS AN-124 heavy-lift aircraft.
Engineers later found that a drive shaft in the engine was bent, and a report from engineering firm P3 says that a temporary flight ban may be needed. Analysis of numerous machines has raised concerns about engines that had been started too many times in one day, which is a serious limitation for a combat helicopter. P3’s conclusion was that the NH90s wouldn’t be able to support foreign deployments effectively until at least 2016. Sources: Die Welt, “Motor des NH90-Helikopters zu sensibel für Einsatze” | The Local – Germany, “German helicopter fleet ‘not fit for Nato'” | Eurasia.NET, “Helicopter Crash Complicates Germany-Uzbekistan Base Negotiations”.
German accident
Oct 15/14: HMD. A 1,500 page from international audit firm KPMG has lots of criticism for the Bundeswehr, and some of its details pertains especially to the NH90.
The Thales TopOwl helmet mounted display comes in for special mention, as its weight is causing pilot injuries that make them unavailable for flying. Co-pilots, who spend their time monitoring the various instruments and screens, are especially hard-hit. The helicopter also gets dinged for not having enough reliable seating, and for corrosion issues (q.v. June 27/14). Sources: Der Spiegel, “Mangel bei der Bundeswehr: Schwere Helme machen Piloten krank”.
HMD problems
July 28-29/14: India. The investigation into India’s AW101 VVIP helicopter buy, which became a full-blown legal dispute between India and Finmeccanica in 2013, continues to stall India’s maritime helicopter buy. The introduction of a new BJP government doesn’t seem to have changed that yet, but Italy’s decision to end its investigation seems likely to leave India’s CBI without a case.
India’s MRH finalists are reportedly Sikorsky’s S-70/ MH-60R, and the NH90 NFH which is led by Finmeccanica. Meanwhile, India’s Navy can only provision 20% of its capable ships with helicopters, and its anti-submarine capabilities are crumbling. For a full account, read “Anti-Submarine Weakness: India Has a Problem“.
July 18/14: Weapons. Navy Recognition reports that NH Industries and MBDA have started integration of the 100+ km Marte-ER anti-ship missile on the NH90 NFH. The Marte Mk.2/S light anti-ship missile gives the helicopter a 30 km reach, but naval defenses are quickly making it difficult to survive at that distance. Meanwhile, the longer-range AM39 Exocet is ineligible; it apparently creates too much turbulence, and messes with the NH90’s center of gravity. The Marte-ER is much more compact, and Italy has reportedly expressed interest. Navy Recognition doesn’t mention this, but India’s maritime helicopter competition may be the larger driver, since it demands an anti-ship missile with 100+ km range. At present, neither finalist has an integrated missile with this performance; adding Marte-ER first could give the NH90-NFH an edge against Sikorsky’s S-70B.
Marte-ER fitting trials began in June 2014, and while flight and separation tests are planned for the fall of 2014. Sources: Navy Recognition, “NHIndustries and MBDA started integration of MARTE ER missile on NH90 maritime helicopter”.
June 27/14: Corrosion. The Dutch will suspend NH90 deliveries until corrosion problems are solved, after the Dutch National Aerospace Laboratory found 92 corrosion issues in their NH90-NFH helicopters. That’s a somewhat surprising problem, given that the NH90’s composite construction was supposed to minimize corrosion. The problem is apparently due to combination of combining materials without isolating them, the wrong choice of materials in some cases, and other design and assembly faults. France is reportedly having similar problems, albeit on a smaller scale.
The Dutch Ministry of Defense says that they informed NHIndustries of this problem in March 2013 through the program managers at NAHEMO (NATO Helicopter Management Agency),; so far, NHI’s engineering task force has found technical solutions for around 60% of the problems. The rest are expected to be solved by September 2014, which will need to be followed by a refit and remediation program. Unsurprisingly, the MvD wants NHI to pay for the fixes, which remains an unsettled contract issue. Meanwhile, the Dutch are working on a corrosion prevention program with NHI that will add some overhead, and the problem is expected to delay the overall delivery schedule by about 6 months. Sources: Dutch MvD, Full brief [PDF] and “Minister van Defensie schort afname Nederlandse NH90-helikopters op” | Aviation Week, “Corrosion Delays Dutch NH90 Acquisition” | War is boring, “Uh Oh—A Crappy Italian Company Might Build The Netherlands’ New Stealth Fighters”.
NFH corrosion issue
March 27/14: Qatar. The Gulf Emirate orders 22 NH90s, at a reported purchase price of around QAR 8.9 billion (about $2.446 billion). The order is for 12 NH90-TTH utility helicopters, and 10 NH90-NFH naval helicopters. It’s just one part of a $23 billion weapon shopping spree announced at DIMDEX 2014 in Doha, Qatar.
The helicopters will replace Qatar’s 12-13 old Westland Commando (Sea King) maritime utility and patrol helicopters, and at least some of its Lynx and/or Puma family helicopters. With this buy, Qatar joins their near neighbor Oman as an NH90 customer. No word yet re: their delivery schedule.
Other Qatari buys at DIMDEX included 24 attack helicopters, air defense and anti-tank missiles, fast attack boats, 2 A330 aerial refueling planes, and 3 E-737 AWACS aircraft. Sources: Al Defaiya, “Qatar Announces Big Defense Deals at DIMDEX 2014” | Arabian Aerospace, “Qatar in $23bn arms order including Apache and NH90 helicopters” | Reuters, “Qatar buys helicopters, missiles in $23 billion arms deals”.
Qatar: 22 mixed
2013
France orders 34 TTH; Germany cuts its contract by 40, but will fly NH90-NFH too; Spain wants to cut from 45 – 22; NH90 loses SAR Australia settles contract issues; Dutch are 1st NH90-NFH foreign deployment.
German NH90 & Tiger
(click to view full)
Nov 29/13: Dutch. The Royal Netherlands Navy (RNLN) has taken delivery of the Final Operative Configuration for their NH90 NFH Mission Planning & Analysis System (MPAS), following operational feedback from more than a year of RNLN service experience. The initial version, based on AgustaWestland’s multi-helicopter SkyFlight system, was released into service in 2011. Sources: Shephard Rotorhub, “RNLN takes delivery of NH90 NFH MPAS”.
Nov 8/13: Italy. The Navy’s 5th Helicopter Sqn at Sarzana-Luni NB receives its 6th helicopter, and its 1st fully operational “Step B” NH90-NFH. The new configuration adds mission systems integration for Marte MK/2S anti-ship missiles and torpedoes, advanced satellite and encrypted communications, and radar and avionics enhancements. Italy’s first 5 NH90-NFHs will be retrofitted to this status in 2014. Sources: NH Industries, “Delivery Of The First NH90 Step B To Italian Navy”.
Aug 1/13: Belgium. Eurocopter delivers Belgium’s 1st NH90 NFH, which is also is the first one built at Eurocopter’s Donauworth, Germany facility. Its configuration is identical to the Dutch NH90-NFH, and the helicopter was delivered at the Full Operational Capability rating. Belgium becomes the sub-type’s 5th customer, after France, Italy, the Netherlands and Norway.
Training of Belgian Navy flight and maintenance crews will begin next month, and operational capability will begin in 2014 using 2 of the 4 contracted helicopters. The NH90s are replacing Belgium’s H-3 Sea Kings. EADS.
July 26/13: Spain. The Spanish government approves an extra EUR 877.33 million (about $1.165 billion) in their 2013 budget, in order to finance payments that have come due on several major weapons programs. At the same time, in order to finance investments in their troubled S-80 submarine program, and purchases of their Pizarro (ASCOD) tracked IFVs, they will look to cut other programs.
The NH90 will see the sharpest cuts, as Spain looks for a way to reduce their planned buy of 45 NH90-TTH to just 22. That has been rumored for a little while, but the decision is now confirmed. The next step will involve negotiations with NH Industries around issues like cancellation fees, potential resale, etc.
The A400M aerial transport contract doesn’t allow Spain to cancel deliveries, but the government has officially decided to take delivery of the last 13 planes in “austere” condition, with few to no options, and then sell them on the second-hand market. They also intend to sell 6 of their 24 Tiger HAD/HAD-E attack helicopters, and reduce the number of serving Leopard 2A6E tanks from 190 – 116. Sources: Defense-Aerospace | Publico [in Spanish].
Spain wants to halve their order
July 9/13: Norway loss. Norway’s Ministry of Justice and Public Security announces the finalists for their NAWSARH search and rescue helicopter competition. The program had started with the NH90-NFH as the assumed platform, with 10 options built into Norway’s initial NH90 contract, but now the NH90 is out. Sikorsky, who forced the buy into a competition, is also out.
Further negotiations will now take place with AgustaWestland (AW101) and Eurocopter (EC725). Norway aims to sign a contract by the end of 2013, and aims to phase out the last H-3 Sea King by 2020. For full coverage, see “AW101 Flies off With Norway’s SAR Helicopter Competition“.
Norway loss
June 23/13: German FAME. The German army declares its NH90 FAME MEDEVAC helicopters “operationally capable.” The Germans have 4 helicopters in Afghanistan at Mazar-e-Sharif, and Aviation Week reports that a MEDEVAC mission will use both operational helicopters in a pickup-escort arrangement, while the other 2 are held back as “technical reserve”. The German contingent’s 4 EC665 Tiger Asgard-T attack helicopters are also available as escorts, if needed. Aviation Week.
June 18/13: Industrial. Aviation Week reports that NH90 partners have been delivering around 30 per year year, but are looking to continue ramping up production to 40-50 in 2013, and 60 per year beyond that. The problem is budget crunches among participating governments, which are likely to create renegotiated and extended delivery schedules. Even at 60 per year, existing orders would keep the consortium busy for another 6 years just clearing the backlog.
Portugal continues to negotiate the cancellation of its 10-helicopter order, and Spain is reportedly looking to cut its 45-helicopter order in half, to 22. Eurocopter EVP Dominique Maudet is more optimistic about Norway, which is reportedly satisfied with its initial models and will make its SAR helicopter decision in 2014. India and Qatar have also reportedly expressed interest. Aviation Week.
May 29/13: France. La Tribune reports that France has ordered their final tranche of 34 NH90 TTH Army helicopter options from Eurocopter, in a contract that was said to approach EUR 1 billion. Defense-Aerospace points out that the order had been described as “imminent” back in January 2012. La Tribune [in French] | Defense-Aerospace | Lloyd’s.
France: 34 TTH
June 6/13: Belgium. A delay in the delivery of Belgium’s 4 NH90-NFH helicopters means that they can’t retire their fleet of aged H-3 Sea Kings on-schedule. Which means more money, and availability problems. Add Belgium to the list of unhappy customers, especially since they placed their order 6 years ago, in 2007 (q.v. June 19/07). Shephard Rotorhub.
May 9/13: Australia. Australia’s Defence Materiel Organisation (DMO) signs a Deed of undertaking with Eurocopter subsidiary Australian Aerospace and their industry partners to re-baseline the “MRH90” army helicopter project’s schedule, settle a number of disputed program issues, and change some contract terms. The biggest change is free delivery of a 47th helicopter for maintenance training at the Army’s Aviation Maintenance school at Oakey, Queensland.
The MRH90 program is 3 years behind, and currently sits on the government’s notorious “Projects of Concern” list. Australian Aerospace agreed on a number of technical fixes back in 2012, and this contract aims to settle the remaining issues and get the MRH90 removed from the Projects of Concern list by the end of 2013. Meanwhile, the MRH90’s problems appear to have cost the NH90 a role as Australia’s future naval helicopter, which was awarded to Sikorsky’s MH-60R Seahawk instead (vid. June 16/11 entry). Australia DoD | Australian Aerospace | Projects of Concern.
Australia MRH90 settlement & changes
May 2/13: Italy. The Italian Army gets its 21st of 60 NH90-TTH machines, but it’s the 1st in Full Operational Configuration. Meanwhile, the Italian Army has now flown 5 Initial Operational Configuration NH90s in Afghanistan’s demanding conditions for 470 combat flight hours.
Note that Italy’s order total in DID’s table shows 70 NH90 TTH helicopters, because the Italian Navy ordered 10 of its own. NH Industries.
April 8/13: Belgium. NH Industries announces the first flight of Belgium’s NH90-NFH, part of Belgium’s 8-helicopter, evenly split order. It’s being delivered:
“…in its full operational capability standard, already known as the “Step B.” This aircraft is very close to the Dutch NH90 NFH Step B currently operationally deployed with the Royal Netherland’s [sic] Navy.”
March 15/13: German cuts. Germany and Eurocopter sign an agreement that substantially cuts its NH90-TTH and Tiger UHT buys, while adjusting their mix of helicopters and ending any hope of a naval helicopter competition.
Under the agreement, Germany’s total buy of NH90s shrinks from 122 to 82, and its purchase of Army & Air Force helicopters shrinks even further. As part of the agreement, Germany will buy 18 NH90-NFH naval helicopters, down from its original requirement of 30. This removes any potential competition for that order, and marks a reduction of 58 NH90-TTH helicopters (47.5%) for the Army and Air Force.
At the same time, Germany is cutting its order for EC665 Tiger UHT scout/attack helicopters from 80 to 57 – a cut that will require them to return 11 helicopters to Eurocopter for resale. Financial savings have not been disclosed yet. German Ministry of Defence [in German].
Germany cuts its order
Jan 21/13: Netherlands. A Dutch NH90 NFH becomes the 1st of its type to deploy abroad, embarked aboard HRMS De Ruyter for anti-piracy patrols in the Gulf of Aden. Rotorhub.
1st NFH deployment
2012
Portugal cancels its 10 NH90s; 1st NH90 combat deployment; Norway threatens cancellation; 100th NH90 delivered – took a while.
FS Aquitaine & Caiman
(click to view full)
Nov 28/12: Norway. NHIndustries delivers Norway’s 2nd NH90 NFH at AgustaWestland’s Tessera, Italy facility, where it was assembled. The Norwegians have been getting antsy (vid. Aug 2/12 entry), so every little bit helps. Note that delivery is not the same as “ready for operations.” NH Industries.
Sept 18/12: Belgium. Belgium’s 1st of 4 NH90 TTH helicopters begins flight testing from Eurocopter’s facility in Marignane, France. NH Industries adds that:
“The Belgian NH90 TTH is a Full Operational Capability standard helicopter. This aircraft is very close to the french [sic] NH90 Caiman TTH for which deliveries started in the end of 2011 in Full Operational Capability Standard. This commonality brings to the Belgian customer all the return of experience collected during the development of the French NH90 TTH.”
The same may not be true of Belgium’s 4 NH90 NFH naval helicopters, as that variant isn’t finished development yet. The helicopters were ordered in July 2007. NH Industries.
Aug 31/12: Deployed. Italy deploys the 1st NH90 helicopters abroad.
The 5 helicopters were airlifted into Afghanistan aboard C-17s (either NATO SAC or USAF), and the plan is to have 6 NH90s in Herat for 6 months. They will serve alongside heavier Italian CH-47 Chinook heavy-lift helicopters, and A129 Mongoose attack helicopters, to help Italy cover ISAF’s large northwestern sector near Iran. NH Industries and follow-on.
1st deployment abroad
Aug 2/12: Norway out? Flight International reports that Norway, which ordered 8 NH90-NFH utility helicopters in 2001 and has received just 1 so far (vid. Nov 30/11 entry), is threatening to cancel its order and buy a different helicopter.
“Speaking last month on a tour with the coastguard in northern Norway, secretary of state for defence Roger Ingebrigtsen said: “NH90 is greatly delayed and I am very concerned about this situation. We therefore have to consider what the options are to ensure the coastguard has the helicopter capacity we depend on.”
The defence ministry adds: “If the manufacturer doesn’t manage to deliver the helicopters [to deadline] we are considering cancelling the contract… There are several helicopters on the market that are combat-proven and in use by other nations,”
If Norway canceled its entire order, it would also be canceling its 6 NH90-NFH anti-submarine helicopters. There are alternatives. Sikorsky’s comparable S-92 is already in use by other Coast Guards, and their smaller MH-60R is a proven anti-submarine helicopter. AgustaWestland’s larger AW101 has Coast Guard credentials, and its naval helicopter variant is in service with Britain and Italy. A few days later, an article in AftenPosten [in Norwegian] states that an Air Force report recommends asking a quote from Sikorsky for MH-60Rs, as a plan B in case NH Industries continues to fail. Back in 2007 their neighbor Finland settled its differences with the manufacturer for a relatively modest penalty, but that was a short delay on a smaller order.
July 3/12: Portugal out. Jane’s reports that Portugal has chosen to cancel its Puma replacement effort, and suspend its participation in the NH90 program. This means the country will abandon the monies paid to date, as well as all 10 helicopters they were to have received. Savings are estimated at EUR 420 million (about $530 million).
Portugal is also said to be renegotiating other contracts, such as its 2005 order with General Dynamics for 260 Pandur II 8×8 wheeled armored personnel carriers.
Portugal quits
June 29/12: Oman. NH Industries delivers another 2 NH90-TTH to Oman, bringing their total deliveries to 10 of 20 ordered. The contract was signed on July 24/04.
May 27/12: Flight International reports that the NH90’s orders from Greece, Portugal, and Spain are all in peril of cancellation or reduction.
To date, Greece is the only one of the 3 that has received any helicopters, despite orders that began in 2001. Only 1 of Greece’s 4 delivered NH90s is even in the process of conversion to the full operational version, out of a 2003 order for up to 34 (16 TTH, 4 Special Ops variants, 14 options). Portugal has yet to accept any of its 10 TTH machines ordered in 2001, while Spain is reportedly looking to cut up to 8 helicopters from its 2006 order for 45.
March 8/12: Writedown. EADS reports its 2011 financial results, and Eurocopter results were generally good. The firm finished its 100th NH90 in 2011, but:
“A net charge of around [EUR] 115 million was booked in 2011. This mainly relates to governmental programmes [i.e. NH90 and Tiger] as well as to SHAPE [the firm’s restructuring plan]. The 2010 figure included a net charge of [EUR] 120 million.”
Aviation Week adds that:
“Departing EADS CFO Hans-Peter Ring says he “cannot guarantee” that there won’t be further charges . He blames the NH90 problems on the companies’ willingness to allow too much customization, with almost every buyer having a near-bespoke configuration.”
March 8/12: France. DCNS, the French Navy, and the French DGA procurement agency successfully complete a series of deck landing trials with the new NH90 NFH (“Caiman Marine”), on board the new FREMM frigate FS Aquitaine. DCNS.
Jan 30/12: France. An official unveiling ceremony is held for the 1st French Army NH90 TTH, which will also be referred to as “Caiman” in French service, alongside the NH90 NFH utility variant. The helicopter will go to GAMSTAT in Valencia to begin its technical and operational testing. French DGA [in French].
Jan 3/12: #100. NH Industries announces delivery of the 100th NH90 variant, about 11.5 years after the initial base contract was signed.
2011
Germany will upgrade 12 NH90s for MEDEVAC; Final Operational Configuration for NH90-TTH; French NH90 naval helicopters enter service; Problems in Australia force a diagnostic review of the program; Australia buys MH-60R naval helicopters, instead of more NH90s; Sweden buys UH-60Ms for MEDEVAC, instead of more NH90s.
Australian MRH-90
(click to view full)
Dec 8/11: France’s “Caiman”. French NH90 NFHs operational. A ceremony marks the official entry of France’s NH90 NFH “Caiman” naval helicopters into service with Flotille 33F. So far, 5 helicopters have been delivered in utility configuration, of the 27 total. The name “Caiman” was chosen in conjunction with the French Army, who has ordered 34 NH90 TTH helicopters of its own.
The Marine Nationale’s eventual mix will be 13 utility models with a rear ramp, and 14 full anti-submarine models without the rear ramp. They’ll be based at BAN (NAS) Hyeres on the French Riviera and BAN Lanveoc in Brittany, plus 1 detached to Cherbourg in Normandy. From there, they’ll deploy aboard France’s high-end frigates: the 2 Horizon Class air defense ships, and its forthcoming Aquitaine Class FRMM multi-role ships. They may also deploy to France’s amphibious ships like the Mistral Class, but the number of NH90 NFH helicopters ordered will make that an occasional posting. Besides a door gunner, their initial armament will be MU90 Eurotorp lightweight torpedoes, with light anti-ship missiles to follow around 2021. Navy Recognition.
French “Caimans” operational
Nov 30/11: Norway. Norway holds a delivery ceremony at AgustaWestland in Verigate, Italy, for their 1st NH90 NFH naval helicopter. Their 14 NH90s will replace the Coast Guard’s AgustaWestland’s Lynx helicopters (8 NH90s), and serve as the new Nansen Class AEGIS frigates’ ASW helicopters (6 NH90s). They will be based at Bardufoss Air Station. AgustaWestland.
Nov 8/11: Germany. Reuters reports that Eurocopter and HN Industries are looking to compensate for Germany’s NH90 TTH cut by pushing the country to buy the naval NH90-NFH, to replace 21 H-3 Sea King and 22 AgustaWestland Sea Lynx helicopters. Reuters adds that the German Navy hasn’t been impressed with the NH90-NFH so far, and has concerns about its upgradeability.
Even if that’s true, Eurocopter has a card to play. Eurocopter CEO Lutz Bertling said that talks over the proposed contract changes would begin in mid-December 2011, with the goal of an agreement in principle by March 2012. The implication is that Eurocopter would forego some or all cancellation fees on existing EC665 Tiger UHT and NH90-TTH contracts, if Germany agreed to buy the NH90-NFH instead of competitors like Sikorsky’s MH-92/CH-148 or MH-60R/S; or AgustaWestland’s EH101 or AW159 Wildcat.
Another possibility involves agreement to fund development of a joint FTH heavy-lift helicopter with France and/or the USA, in which Eurocopter would likely partner with Boeing or Sikorsky.
Nov 8/11: NH90-TTH final configuration. NAHEMA issues the NH90 Tactical Transport Helicopter’s Final Operational Configuration certification, stating that it fully meets customer specifications. With this go-ahead, the French Army will receive their initial FOC NH90 TTH before 2011 ends, and deliveries to Italy, Belgium and Germany will begin in 2012.
The announcement also implies the start of retrofit programs, among customers who have already received early model NH90 TTHs for training use. NH Industries | EADS.
NH90 TTH FOC cert
Oct 21/11: German cuts? As German austerity measures cut further into an already weak defense budget, the government announces changes to its NH90 TTH plans. They’ll be cutting 42 NH90s from the 112 helicopter procurement plan, capping the total buy at 80. The final split between the Army and Air Force, who were going to fly slightly different versions of the TTH model, remains unclear. Also unclear: potential termination costs under the contract with NH Industries.
Eurocopter will actually be taking 2 hits. One from its share of NH90 work, another from Germany hal