UH-72As: MEDEVAC
(click to view full)

DID’s FOCUS articles offer in-depth, updated looks at significant military programs of record. This is DID’s FOCUS Article regarding the US Army’s Light Utility Helicopter program, covering the program and its objectives, the winning bid team and industrial arrangements, and contracts.

The US Army’s LUH program will finish as a 325 helicopter acquisition program that will be worth about $2.3 billion when all is said and done. It aimed to replace existing UH-1 Hueys and OH-58 Kiowa utility variants in non-combat roles, freeing up larger and more expensive UH-60 Black Hawk helicopters for front-line duty. In June 2006, a variant of Eurocopter’s EC145 beat AgustaWestland’s AB139, Bell-Textron’s 412EP Twin Huey, and MD Helicopters’ 902 Explorer NOTAR (No Tail Rotor) design. The win marked EADS’ 1st serious military win in the American market, and their “UH-145” became the “UH-72A Lakota” at an official December 2006 naming ceremony.

Eurocopter has continued to field new mission kits and deliver helicopters from its Mississippi production line, while trying to build on their LUH breakthrough. A training helicopter win will keep the line going for a couple more years…

The LUH Program: Objectives & Background



RAH-66 Comanche
(click to view full)

The LUH program spun out of the canceled $9 billion AH-66 Comanche stealth scout/attack helicopter, as one of the US Army’s cheaper reinvestment and recapitalization options. LUH helicopters are intended to replace Vietnam era UH-1H Hueys and OH-58A/C Kiowa aircraft in the U.S. Army and National Guard. Note that the US Marine Corps will continue to fly the modernized UH-1Y Venom, and the civilian para-military DEA (Drug Enforcement Agency) is likely to retain many of its OH-58s and may pick some up from Army surplus.

The US Army’s OH-58D Kiowa Warrior scout helicopters, meanwhile, will be replaced by 368 militarized Bell 407s between FY 2006-2013 under the $2.2 billion Armed Reconnaissance Helicopter (ARH) program, the first of the AH-66 spinoffs. These efforts are part of the Army Aviation Modernization Program, along with programs like the Warrior UAV and hopefully the Joint Cargo Aircraft to replace the Army’s C-123 Sherpa light transport planes.


UH-60 Blackhawk

The intent was to acquire a Commercial-Off-the-Shelf (COTS)/ Non-Developmental Item (NDI) aircraft that is Federal Aviation Agency (FAA) Type Standard Certified, and produce approximately 322 new LUH helicopters between 2006-2015. They will fill the niche missions in which the Army’s standard UH-60 Black Hawk’s size, capability, and operating expenses may be unnecessary, performing a wide range of general support missions in the United States and overseas. Transport of personnel and supplies, disaster relief operations, medical evacuation, reconnaissance, drug interdiction, and homeland security will all be likely tasks.

In 2006, therefore, while the rest of EADS was targeted for divestment and beginning to face bottom line issues, Eurocopter continued to fly. Fresh off of major wins with Korea’s KHP development program ($1.3 billion) and Australia’s NH90 order ($1.5 bilion), Eurocopter racked up the biggest win of all in June: its EC145 would serve as the USA’s future Light Utility Helicopter, replacing existing UH-1s and OH-58s in a 322 helicopter, $3+ billion program between 2006-2015. Losing entries included Team MD Helicopters’ 902 Explorer NOTAR (No Tail Rotor) design, Bell-Textron’s 412EP Twin Huey, and Team AgustaWestland’s AB139. See DID coverage of the 4 competing teams.

Excel
download

The US military subsequently raised the planned number of UH-72 LUH helicopters to 345, but shifts near the end of the program cut the final number to 325, and aimed to place the last orders in FY 2014. In 2015, however, Airbus was picked for a 100-helicopter contract as the US Army Aviation Center of Excellence’s prime training helicopter. Budgets over the life of the program included:

The LUH Winner: Eurocopter’s EC145/ UH-72A

EC145 w. hoist
(click to view full)

The UH-72A Lakota is a militarized version of the Eurocopter EC145, which in turn is a new and thoroughly modified version of the famous BK 117-C1. It was given its Lakota designation in keeping with the Army’s tradition of naming rotary-wing aircraft after native American Indian tribes. Requests for the naming originate with the tribes themselves, and their history and traditions must be aligned with the helicopter’s characteristics and uses in US Army service.

The Lakota is outfitted with an advanced avionics suite that includes a “glass” (digital screen) cockpit for flight and navigation instrument display. Its civilian version is already FAA Instrument Flight Rules (IFR) certified, and safety features include redundant hydraulic and electrical systems. An array of radios allows communication with civilian first responders, as well as military channels.

The aft cabin, including baggage area, is 50.77 ft2, at 4.59 x 11.23 feet. That cabin can be switched between a 6-seat (3-3) arrangement, or 2-3 seats plus 2 MEDEVAC stretcher rails. If a medic needs to work on a patient in the air, operational capacity drops to 1 stretcher. A high-set main and tail rotor design allow safe loading and unloading through the main side doors and rear-fuselage clamshell doors, even while the rotors are turning.

Those turning rotors are relatively quiet, for a helicopter. That was true of the old BK-117, is true of the EC145, and remains true for its military counterpart. Quietness makes helicopters easier to operate in civilian airspace, and provides front-line advantages if UH-72 variants are ever deployed that way.

UH-72A S&S
(click to view full)

So far, the US military’s UH-72As have stuck to their original intent, and are used for service away from the front lines. They’ve been used most often for medical evacuation (MEDEVAC) missions, search and rescue, border patrols along the U.S./Mexican border, and VIP transport. They’ve also found niche roles in missile testing, and in general aviation support and combat flight training at the Joint Multinational Readiness Center (JMRC) in Hohenfels, Germany; the Joint Readiness Training Center (JRTC) at Ft. Polk, LA; and the National Training Center at Ft. Irwin, CA. Special missions have included disaster response following the January 2010 earthquake in Haiti, and oil spill monitoring and response flights along the U.S. Gulf Coast after the 2010 Deepwater Horizon oil spill.

They’ve also remained true to their initial affordability promises. Deliveries have been on time and on-budget, and in 2012, US Army project manager for utility helicopters, Col. Thomas Todd, said that the UH-72A is cheaper to operate than its predecessors were. He cited a readiness rate of over 90%, which is excellent even for such a young fleet, and a parts cost that’s 30-40% less than UH-1 and OH-58 legacy helicopters. That parts cost is especially good news. The history of modern military programs has usually involved lower availability rates, and higher maintenance costs, than the equipment it replaces. Since operating and maintenance costs are a majority of any platform’s real costs over time, lowering those costs makes a big cumulative difference to the Army’s future budgets.

UH-72A Lakota Variants

UH-72A S&S
(click to view full)

Overall, 7 UH-72A variants exist, but several of them are really kits that can be rolled on and off of the base helicopter.

MEDEVAC/Search and Rescue. This mission “B-kit” includes the external rescue hoist, 2 stretchers, plus associated medical equipment and systems. Two medics are positioned in rear-facing seats behind the pilot and co-pilot.

Missile Test LUH. This variant operates in the Ronald Reagan Ballistic Missile Defense Test Site at Kwajalein Atoll, Pacific Ocean. The Kwajalein helicopters are painted in high visibility orange, and come with skid-mounted floats, integrated life rafts, and jettisonable cockpit doors.

UH-72A Security & Support (S&S) Battalion. This 3rd kit is more extensive. It includes an external hoist, a forward centerline-mounted camera system which can track targets at up to 9 miles away using electro-optical and infrared sensors, a laser pointer, a 30 million candlepower searchlight, an operator console, cockpit and cabin touch-screen displays with moving maps that can navigate to streets as well as military coordinates, a video management system, a digital video recorder and data downlink system, and additional avionics and communications equipment that can be synced with first responders on the ground. The US Army National Guard plans to buy at least 100 UH-72A S&S helicopters: 17 retrofitted and 83 new build.

Training. Current proposals would replace existing US Army TH-67 (Bell 206) and OH-58 training helicopter fleets with the UH-72A, allowing those existing types to completely retire from US Army service.

Airbus is also trying to interest the Navy in using the UH-72 as a replacement for its aging TH-57 Sea Ranger (Bell 206) helicopter trainer fleet. The helicopters would add Garmin G1000H avionics, and be fitted with student, instructor, and observer seats.

VIP transport. This adds more and nicer seats, for a total of 3 rear-facing seats located behind the cockpit, 2 forward-facing seats just aft of the helicopter’s side doors, and 3 seats behind them.

2 more kits are left deliberately undefined, except to say that they are “associated with training missions that teach soldiers how to fight aircraft and recognize friend or foe on the battle space.”

US Navy. The 7th variant was produced for a different customer, the U.S. Naval Test Pilot School at Patuxent River Naval Air Station, MD. Their variant is exactly what you would expect: it trains test pilots from the U.S. military and allied countries. Navy H-72A modifications include jettisonable cockpit doors, a cockpit voice and flight data recorder, a main rotor blade folding kit, and an air traffic advisory system.

AAS-72X+ concept
(click to view full)

The platform’s next frontier was supposed to involve a step beyond kits, into a fully armed version.

In 2009, EADS North America moved to build on their success. With Bell’s ARH-70 Armed Reconnaissance Helicopter canceled due to cost overruns, EADS announced a partnership with Lockheed Martin to offer an EC645/AAS-72X variant for the US Army’ Armed Aerial Scout competition. After initial tests, they decided to favor performance over full commonality, and used the EC145-T2 as the base for their armed scout. The AAS-72X+ adds uprated Arriel 2E engines and the Helionix avionics suite, and switches to an enclosed Fenestron tail rotor instead of the UH-72A’s twin-tail high configuration.

Lockheed Martin is in charge of mission systems and weapons, and the team’s bid will push the advantages of having a similar base type for armed scout, training, and support roles. The problem is that the USA decided to do away with their scout helicopter fleet altogether, so any sales will have to be exports.

LUH Industrial Arrangements

UH-72A program management is located in Huntsville, Alabama and led by the EADS North America Defense business unit of EADS North America. Production takes place at American Eurocopter’s Columbus, Mississippi facility, which received a major expansion to accommodate the Light Utility Helicopter program.

The production line is a version of Eurocopter’s EC145 multi-mission helicopter line in Donauworth, Germany. The initial UH-145s were actually built on Eurocopter’s existing EC145 production line in Germany, and shipped to Columbus, MS for final assembly and completion. Even before the contract was formally awarded, the first UH-145 helicopters were already under assembly, and components had been allocated for the manufacture of 7 more UH-145s. It was a gutsy move, but once the contract was won, it helped American Eurocopter deliver its first 8 machines to the US government on budget and ahead of schedule.

The line was duplicated in Columbus through a series of steps that began with partial assembly, followed by full assembly and the subsequent U.S. manufacture of major subsystems. Growth continued at Columbus, up until full build-up of the aircraft on a new assembly line in 2007.

Columbus, MS facility
(click to view larger)

American Eurocopter’s expansion of the 92,200 square foot Columbus facility grew it to to approximately 276,000 square feet to accommodate the UH-145 program. As of July 2006, this plant built A-Star AS350 helicopters at a rate of about 30 per year, and its advanced metallic production center manufactures components that include aft fuselage sections for all new production A-Star/Ecureuil helicopters sold worldwide. It also handles assembly and customization of other American Eurocopter helicopter models for U.S. customers. On a federal level, the Columbus plant was already re-engining and upgrading U.S. Coast Guard Eurocopter HH-65 Dolphin search and rescue helicopters to the improved performance HH-65C version; and assembling, customizing and delivering EC120B helicopters ordered by the Department of Homeland Security’s U.S. Customs and Border Protection.

Employment at Columbus grew from the current staffing of 129 to approximately 330, plus 20-40 additional jobs at the company’s headquarters in Grand Prairie, Texas for program support.

Other suppliers also geared up. Turbomeca USA, which builds the UH-145’s Arriel 1E2 engines, grew its Grand Prairie, Texas facility by 35-45 new jobs. Thales USA transferred production of its Meghas avionics suite from Europe to a new facility in Irvine, California. Meghas also equips the Eurocopter EC145, EC135, EC155, EC120, EC130 and AS350 helicopters, and manufacturing of avionics for all these aircraft types, as well as the UH-145, was relocated to Irvine.

UH-72 LUH
(click to view full)

UH-72A deliveries have gone well. UH-72A deliveries to the US Army commenced in December 2006; the first 7 helicopters were delivered by June 2006, whereupon the first active unit was equipped. Deliveries continued at the rate of 1 per month until September 2007, then rose to 2 helicopters per month.

By 2010, there were 7 different H-72 configurations produced on the line, and 10 new fielding sites stood up, making 31 basing locations in the continental U.S., Puerto Rico, Germany, and the Pacific Ocean’s Kwajalein Atoll.

From December 2006 – November 2012, EADS North America delivered 243 Lakota helicopters, on budget and either on time or ahead of schedule. Delivery rates can now reach over 4 helicopters per month, or up to 53 helicopters per year. As the LUH program winds down, however, that production rate is set to slow and then stop. It’s currently 3 helicopters per month, but under the proposed FY 2014 budget that will taper to 1 per month by September 2014. By June 2015, LUH production will end.

American UH-72As: Contracts and Key Events

Unless otherwise noted, all contracts are issued by the US Army Aviation and Missile Command at Redstone Arsenal, AL; and the recipient is EADS North American Defense in Arlington, VA.

FY 2016

MEDEVAC exercise
(click to view full)

November 16/15: Airbus has received a further order for 12 of their UH-72A light helicopters by the US government which will bring the total ordered to 400. The latest batch is said to be used for pilot training.

FY 2013 – 2014

Orders; AAS-72X tests but ARH is cancelled; From early termination to another 90-100 training helicopters.

Sept 29/14: Thailand. The US DSCA announces Thailand’s official export request for up to 9 UH-72A Lakota Helicopters, an Aviation Mission Planning Station, plus warranty, spare and repair parts, support equipment, communication equipment, publications and technical documentation, personnel training and training equipment, and other Government and contractor support. The estimated cost is up to $89 million, and the principal contractor will be EADS North America in Herndon, VA.

Thailand’s last UH-72A request became an order in under a year. The 9 helicopters will surely be welcome in the Mississippi plant, but they aren’t about to make a significant industrial difference. Read “Huey’s Departure: Thailand’s New Helicopters” for full coverage of their importance to Thailand.

DSCA: Thailand (9)

Sept 22/14: Lawsuit. AgustaWestland sues the US Army, seeking an injunction to stop its planned UH-72A training helicopter purchase. The claim states that the Sept 4/14 sole-sourcing decision wasn’t justified properly, while claiming a massive price difference of $7 million per UH-72 vs. $3.25 million for their helicopter. That price matches expected costs for the AW119Kx Koala, which is built near Philadelphia.

AgustaWestland representatives point out that the UH-72 has a restricted flight maneuver envelope, while Bell Helicopter representatives cite “a cost difference of $1,000 to $1,500 per flying hour more for the UH-72” in exchange for training on a glass cockpit and a twin-engine platform.

The stakes are higher than usual. AgustaWestland is also touting the Koala as a replacement for the US Navy’s TH-57 Creek, which is based on the same Bell 206 airframe as the Army’s TH-67 fleet that the Airbus UH-72 would replace. The Navy doesn’t have a formal program to replace the TH-57 Sea Ranger fleet, but it is aging, and an Army trainer buy would be a natural cross-service lead in. Meanwhile, the threat of sequestration (q.v. Aug 24/14) is driving pressure to buy more UH-72As immediately. If the lawsuit delays the training buy for long enough, the Army has to choose between accepting the risk of a smaller replacement fleet, or picking a cheaper option. Sources: AIN, “AgustaWestland Sues over Airbus Army Trainer Plan” | Bloomberg, “AgustaWestland Sues U.S. to Block Airbus Helicopter Buy” | Reuters, “Finmeccanica unit sues to block U.S. helicopter deal for Airbus” | Defense News, “AgustaWestland Pitches AW119 for US Navy Helicopter Trainer”.

Aug 24/14: TUH-72. Despite Kendall’s cautions, all 4 Congressional defense committees are moving to approve a $110.8 million reprogramming request that would buy another 21 UH-72As in FY 2014. These helicopters would be slotted for the training fleet, and sequestration is the reason for their haste. The FY 2016 budget is the one under threat if sequestration continues, and Fort Rucker, AL needs a bare minimum of 60 helicopters for instructor and student training needs. The added 21 + 55 in FY 2015 would provide 76, leaving the fleet ready to go despite sequestration.

If things work out in FY 2016, the remaining 24 helicopters can be ordered to raise the training fleet to 100. If sequestration hits, FY 2015 funds could be reprogrammed, or some helicopters could be moved out of the National Guard. Sources: Forecast International, “Congress Signs Off on Plan to Buy 21 Additional UH-72A Lakotas in FY14”.

Aug 6/14: TUH-72. Pentagon Under Secretary of Defense for Acquisition, Technology and Logistics Frank Kendall says that he wants to see the Army’s business case for buying 90 UH-72s to replace existing TH-67 Creek (Bell Model 206B Jet Ranger III, initial training) and OH-58 Kiowa (tactical training) machines, under the proposed Army Aviation Restructure Plan.

We can summarize the cases. The Army says that removing these helicopter types from the fleet, and consolidating on the UH-72A, will save on support costs. Bell Helicopters says that the single-engine TH-67 fleet is 16 years old on average, and can still be used and supported for some time. On the other hand, the UH-72A production line won’t be around forever. Sources: Defense News, “Kendall Wants Business Case for US Army Helicopter Swap”.

June 26/14: Support. EADS-NA in Herndon, VA receives a $14.4 million firm-fixed-price contract modification, for UH-72A contractor logistics support. All funds are committed immediately, using FY 2014 Army O&M budgets.

Work will be performed at Columbus, MS with an estimated completion date of May 15/15. US Army Contracting Command Redstone Arsenal – Aviation at Redstone Arsenal, ALmanages the contract (W58RGZ-06-C-1094, P00811).

May 27/14: Support. EADS North America, Inc. in Herndon, VA receives a $33.8 million modification, exercising an option to increase contractor logistics support for the UH-72A. All funds are committed immediately, using FY 2014 Army O&M budgets.

Work will be performed in Columbus, MS, with an estimated completion date of June 30/16 (W58RGZ-06-C-0194, PO 0795).

May 23/14: Politics. The Senate Armed Services Committee has completed the mark-up of the annual defense bill, which passed by a 25-1 vote. The section relevant to the UH-72 is explained this way:

“Authorizes $612.6 million in procurement for UH-72A Light Utility Helicopter (LUH). At the request of the Chief of the National Guard Bureau, the Secretary of Defense directed the Army to procure 100 additional LUH as a replacement training aircraft rather than transfer any from National Guard for that purpose. Additional funds would authorize procurement of a total 90 new aircraft to replacement of the Army’s legacy aviation training aircraft.”

$612.6 million is $196 million above the Defense Department’s budget request, and supposedly adds 35 more helicopters in Fiscal Year 2015. That creates a total of 90 ordered if the House agrees, which explains phrases like “decreases the risk and cost to the Army in their divestiture of TH-67 training aircraft”. Implicitly, it also removes the 45 helicopters and $387.6 million planned for 2016, and cuts the future training fleet from 100 to 90. Sources: US Senate Armed Services Committee, “Senate Committee on Armed Services Completes Markup of the National Defense Authorization Act for Fiscal Year 2015” | WTVY.com, “Senate Bill would Fund Alabama Defense Programs”.

May 14/14: #300. Airbus Group delivers 300th UH-72A to the US military, on time and on budget. The UH-72A S&S will enter service with the Missouri National Guard. The firm touts an American workforce that is “more than 50 percent U.S. military veterans”. No doubt they’re all happy about the 2-year extension to Army orders. Sources: Airbus, “Airbus Group delivers 300th on-time, on-budget UH-72A Lakota helicopter to U.S. Army”.

#300

May 6/14: Support. EADS North America in Herndon, VA receives a $25.5 million option for UH-72A contractor logistics support.

All funds are committed immediately, using FY 2014 Army O&M budgets. Work will be performed in Columbia, MS, with an estimated completion date of Nov 30/15. US Army Contracting Command in Redstone Arsenal, AL manages the contract (W58RGZ-06-C-0194 P00787).

March 28/14: EADS-NA in Herndon, VA receives a $34 milllion contract modification to sole-source, foreign military sales contract for 6 UH-72A Lakota helicopters with AN/ARC-231 radios, the Mission equipment package, and environmental control units to deal with Thailand’s heat.

It’s a dubious purchase, as Thailand already operates similar helicopter fleets from other manufacturers, and won’t make much of an industrial difference with the Us Army committed to its training order. Read “Huey’s Departure: Thailand’s New Helicopters” for full coverage.

Thailand buys 6

March 4-11/14: FY15 Budget. The US military slowly files its budget documents, detailing planned spending from FY 2014 – 2019. The UH-72 gets a big win. As part of the Aviation Restructure Initiative (ARI) the UH-72A will become the primary training aircraft at the US Army Aviation Center of Excellence in Ft. Rucker, AL.

That means 100 more UH-72A orders are scheduled for FY 2015 – 2016, to equip the Army’s Initial Entry Rotary Wing training fleet.

Feb 18/14: +4. A $22.9 million modification for 4 UH-72A Lakota helicopters, with the standard add-ons of ARC-231 radios and engine inlet barrier filters to keep incoming air clean.

All funds are committed immediately, using Army FY 2014 other procurement budgets. Work will be performed in Columbia, MS, and the estimated completion date is March 31/15. US Army Contracting Command in Redstone Arsenal, AL manages the contract (W58RGZ-06-C-0194, PO 0766).

4 UH-72As

Jan 17/14: Budgets. Congress doubles the planned buy of UH-72As in 2014, so the final order will be for 20 rather than 10. It ends up being a mid-point compromise between 10 and the original 31. It’s part of the omnibus spending package. Sources: Airbus Group, “Congress continues support of UH-72A Lakota helicopter”.

OH-58D, Afghanistan

Jan 14/14: No AAS. The US Army’s OH-58D scout helicopter fleet will be retired without a successor. This means the end of Airbus’ hopes to sell the AAS-72X to the US military, though they could still offer it as an export package if a country was willing to pay the remaining development costs.

Instead, the Army will rely on a mix of their AH-64E attack helicopters and UAVs. The Army realized that they didn’t have enough money to buy enough AH-64s, and that they were going to shrink the number of people in the Army. The current leadership has decided that 698 AH-64Es, who will be able to control the planned fleets of unarmed RQ-7B Shadow and armed MQ-1C Gray Eagle UAVs from the air, will provide an “80% solution.” In parallel, a rebalancing will move more UH-60 utility helicopters to the National Guard alongside the UH-72s, where they can offer useful capabilities during natural disasters etc., while shifting AH-64 attack helicopters to the active-duty force. Sources: US Army, “Army aviation flying smarter into fiscal squeeze” | Alabama.com, “Army planning to scrap OH-58 Kiowa Warriors helicopter fleet: Reports” | Jackson Sun, “National Guard: Tennessee could lose 30 OH-58D helicopters, including at Jackson flight facility, under proposed Army plan” | The Motley Fool, “The U.S. Army Is About to Make a Huge Mistake”.

End of US Scout helicopters

July 1/13: Support. EADS North America in Herndon, VA receives a $12.9 million firm-fixed-price option for contractor logistics support for the Army’s aviation assets. Work will be performed in Columbus, MS.

The only platform that fits is the UH-72A, and the Pentagon says that this award brings the cumulative total face value of the LUH contract to $2.265 billion (W58RGZ-06-C-0194, PO 0703).

June 20/13: Thailand. The US Defense Security Cooperation Agency announces [PDF] Thailand’s formal request for 6 ready-to-fly UH-72A Lakota Helicopters, communication equipment, an Aviation Mission Planning Station, plus spare and repair parts, support equipment, publications and technical documentation, personnel training and training equipment, and other forms of contractor and government support. The estimated cost is up to $77 million.

It’s part of an effort by Thailand to add a new light utility helicopter to its fleet, and would represent the UH-72A’s 1s export order, but the base EC145 has been exported to a number of other countries already. If the UH-72A is chosen, the principal contractor will be EADS North America, in Herndon, VA. Implementation will require U.S. Government or contractor representatives in Thailand for a period of 5 weeks for equipment de-processing/fielding, system checkout and new equipment training; plus a Contractor Furnished Service Representative (CFSR) for a period of 1 year. Read “Huey’s Departure: Thailand’s New Helicopters” for full coverage of Thailand’s multi-platform recapitalization drive.

DSCA Thailand: 6

May 30 – June 7/13: Lobbying. EADS North America is lobbying to reverse planned cuts to the UH-72A program, and essentially restore a year’s worth of orders. The have Congressional representatives attending, but the rallies are at their own plants in Mississippi and Texas. EADS NA re: MS | AL.com | WCBI, incl. video | EADS NA re: TX.

April 25/13: #250. American Eurocopter delivers the 250th UH-72A, which will be operated out of Oklahoma City by the Oklahoma National Guard. It’s actually the 255th, if you count the US Naval Test Pilot School’s 5 machines, and it’s the 54th UH-72A S&S configuration delivered to the US military.

EADS NA says that the combined Lakota fleet’s operations have now exceeded 150,000 flight hours, while maintaining over 90% availability. EADS North America.

#250

April 10/13: FY 2014 Budget. The President releases a proposed budget at last, the latest in modern memory. The Senate and House were already working on budgets in his absence, but the Pentagon’s submission is actually important to proceedings going forward. See ongoing DID coverage.

The UH-72A’s record of on-time and on-budget delivery didn’t entirely protect the LUH program. Instead of buying 31 in 2014 and the last 10 in 2015, the proposed budget would cut 31 machines, and close the program with a 10-helicopter buy in 2014. EADS North America chairman Sean O’Keefe vowed to fight the cuts, which would remove about $345 million from the firm’s order books. It will be interesting to see if he has any luck. See also EADS North America.

Feb 27/12: Support. EADS North America in Herndon, VA receives a $15.3 million firm-fixed-price contract modification for Contractor Logistics Support. At this point EADS North America’s site is advertising 279 LUH helicopters delivered.

Work will be performed in Columbus, MS with an estimated completion date of Dec 31/13. US Army Contracting Command in Redstone Arsenal, AL (W58RGZ-06-C-0194).

Jan 3/13: MEP support. EADS North America in Herndon, VA receives a $26.3 million firm-fixed-price contract. The award will provide for the modification of an existing contract to procure contractor logistics support for LUH Mission Equipment Packages.

Work will be performed in Columbus, MS, with an estimated completion date of June 30/16. One bid was solicited, with 1 bid received (W58RGZ-06-C-0194).

Nov 16/12: +34. EADS North America, Herndon, VA receives a $181.8 million firm-fixed-price contract, to deliver 34 more UH-72A helicopters (10 standard, and 24 S&S), plus engine inlet filter barrier kits that help the helicopters cope with dust and sand.

This order brings the total number of UH-72As ordered to 312/347; so far, about 243 have been delivered. EADS North America says that the Lakota fleet has averaged an operational availability rate greater than 90% in the 21 military units that enjoy full contractor logistics (CLS) support. The spare parts fill rate under the hybrid CLS concept supporting all 33 units has averaged 97%, but there’s no word of the total availability rate.

34 UH-72As

Work will be performed in Columbus, MS, with an estimated completion date of Aug 31/14 (W58RGZ-06-C-0194). See also EADS-NA.

Oct 12/12: AAS-72X. The US Army holds preliminary flying tests of the EC145-T2 at Fort Hood. It’s related to the AAS program, but they’re flying the civilian version instead of the AAS-72X+ prototype. DVIDS.

FY 2012

Orders; #200 delivered; Security & Support variant operational; UH-72A delivering lower operating costs; Armed Aerial Scout unveiled.

UH-72A at JMRC
(click to view full)

Sept 25/12: Support. A $10.9 million firm-fixed-price contract modification for services in support of the UH-72A Lakota. Work will be performed in Columbus, MS, with an estimated completion date of Sept 28/13. The bid was solicited through the Internet, with 1 bid received (W58RGZ-06-C-0194).

Aug 28/12: Ancillaries. A $33.5 million firm-fixed-price contract modification to buy UH-72A Security and Support Mission Equipment Packages. Work will be performed in Columbus, MS, with an estimated completion date of Aug 31/14. The bid was solicited through the Internet, with 1 bid received (W58RGZ-06-C-0194).

Aug 17/12: Support. A $19.8 million modification to the existing firm-fixed-price contract (W58RGZ-06-C-0194) for logistic support. Work will be performed in Columbus, MS, with an estimated completion date of Dec. 31, 2012.

August 2012: MEDEVAC. The US Army Aeromedical Research Laboratory (USAARL) announces that after an inaugural test cycle that included Electromagnetic Interference (EMI) testing, 12 medical devices are now Airworthiness Certified on the UH-72A.

July 18/12: AFTD gets 3. The US Army fields 3 UH-72A Lakota at Redstone Arsenal, AL for the Aviation Flight Test Directorate, a part of the Redstone Test Center. They’ll be used for general support, and as a rotary wing chase platform to support the developmental testing of aircraft and aviation systems. Huntsville Times.

July 17/12: Support. A $9.7 million firm-fixed-price contract for UH-72A engineering support services. Work will be performed in Columbus, MS, with an estimated completion date of June 30/16. One bid was solicited, with 1 bid received (W58RGZ-06-C-0194).

July 9/12: A $15.2 million firm-fixed-price contract modification of an existing contract buys contractor logistics support to June 30/16. One bid was solicited, with 1 bid received (W58RGZ-06-C-0194).

May 29/12: Support. A $26 million firm-fixed-price contract modification, for contractor logistics support. Work will be performed in Columbus, MS, with an estimated completion date of Dec 31/12. One bid was solicited, with 1 bid received (W58RGZ-06-C-0194).

May 22/12: 100,000 flight hours. EADS North America announces that the US Army & National Guard’s fleet of 219 delivered UH-72As achieved 100,000 total flight hours on May 10/12.

100,000 hours

April 9/12: Support. A $12.8 million firm-fixed-price contract for contractor logistics support services. Work will be performed in Columbus, MS, with an estimated completion date of Dec 31/12. Five bids were solicited, with 3 bids received by US Army Contracting Command in Redstone Arsenal, AL (W58RGZ-06-C-0194).

April 3/12: Update. US Army project manager for utility helicopters, Col. Thomas Todd, discusses the UH-72A Lakota fleet. So far, the Army has taken delivery of 209, and the fleet is in use in 42 states and approaching 100,000 flight hours. Fully 2/3 of the fleet will be located in National Guard units. Along the Mexican border, for instance, 11 Lakota aircraft have racked up 700 flying hours working the Southwest Border Mission, from operating locations in Larado and Harlingen, TX. Col. Todd:

“The real success story for us: it’s been on schedule [and] it’s met its cost targets perhaps better than any other aviation program we have got that’s active right now… It maintains consistently 90 percent operational availability rates… When we compare [to OH-58s and UH-1s] our parts fill rate is higher, and our parts cost or our contracts cost is easily 30-40 percent less. That’s a huge measuring stick for us, in these resources constrained times.”

April 2/12: AAS-72X+. American Eurocopter unveils its AAS-72X+ contender for the Army’s Armed Aerial Scout, which may or may not become a program. Unlike the LUH, it will be based on Eurocopter’s EC-145 T2, which adds more powerful 1,038 shp Turbomeca Arriel 2E engines, replaces the dual-tail rear rotor with an enclosed Fenestron, and uses the Helionix glass cockpit and avionics suite instead of Thales Meghas. American Eurocopter.

March 1/12: #200. A ceremony at American Eurocopter in Colombus, MS marks the 200th UH-72A delivered the U.S. Army, a Security and Support (S&S) variant. American Eurocopter says that the program remains on-time and on-budget. American Eurocopter.

#200

Dec 23/11: +39. A $212.7 million firm-fixed-price contract modification to buy 39 UH-72As. Work will be performed in Columbus, MS with an estimated completion date of Nov 30/13. One bid was solicited, with 1 bid received (W58RGZ-06-C-0194).

American Eurocopter adds that 32 of these UH-72As will be produced in the Army’s Security and Support (S&S) Battalion configuration, and says that US Army deliveries stand at 198 UH-72As as of January 2012.

39 UH-72As

Nov 5/11: S&S stood up. The first battalion of UH-72A helicopters with the Security & Support Mission Equipment Package enters service with the US military, in the Mississippi National Guard’s Company C, 1st of the 114th Security and Support Battalion.

EADS says that 69 of the 100 anticipated S&S MEP installations have been ordered. Of those, 52 will be built-in, 16 will be retrofits, and the last will be the S&S MEP prototype, which was delivered and fielded in this 1st UH-72A S&S battalion. EADS NA.

UH-72 S&S

FY 2011

Orders; Haiti mission; Dedication at Crazy Horse Memorial; New Eurocopter manager; Rescue; AAS-72 testing.

DC Guard UH-72As
(click to view full)

Sept 7/11: A $9.9 million firm-fixed-price contract modification, to increase the funding for contractor logistics support flight hours. Work will be performed in Columbus, MS, and Trumbull, CT, with an estimated completion date of Aug 31/13. One bid was solicited, with one bid received (W58RGZ-06-C-0194).

Aug 29/11: +32 S&S kit cut-ins. A $43.8 million firm-fixed-price contract modification buys production line cut-in for 32 Security & Support mission equipment packages on 32 base UH-72As.

Work will be performed in Columbus, MS, with an estimated completion date of Aug 31/13. One bid was solicited, with one bid received (W58RGZ-06-C-0194).

Aug 24/11: Half-time. EADS North America announces that it has now delivered more than half of the planned 345 Lakotas to the U.S. Army, with sustained output reaching 53 helicopters per year and 180 machines delivered to the US military.

UH-72A Lakota helicopters are now operating from 31 basing locations, and the U.S. Army has ordered 219/345 possible UH-72As under the current contract. EADS NA.

July 25/11: A $10.2 million firm-fixed-price contract modification to provide UH-72A spares support. Work will be performed in Columbus, MS, with an estimated completion date of Dec 31/11. One bid was solicited, with one bid received (W58RGZ-06-C-0194).

June 16/11: +14. A $74.4 million firm-fixed-price contract for 14 UH-72As and 14 airborne radio communication systems (previous contracts suggest the AN/ARC-231). Work will be performed in Columbus, MS, with an estimated completion date of Aug 31/12. One bid was solicited with one bid received (W58RGZ-06-C-0194).

14 UH-72As

June 7/11: Personnel. American Eurocopter announces Peter Cutler’s hiring as VP Military and Federal Government Programs. In this position, he will be responsible for the U.S. Army UH-72A LUH program, the associated Armed Aerial Scout capture effort, and expanding sales to the U.S. Coast Guard, Customs and Border Protection and FBI.

Before his hiring, Cutler spent 24 years at Sikorsky, finishing as the leader of their product support organization. He holds a B.Sc. Industrial Engineering from Rutgers University, and an MBA in Industrial Management from Fairleigh Dickinson University.

May 27/11: Haiti. Soldiers from Florida’s Army National Guard’s B Company, 2nd Battalion, 151st Aviation (Security and Support) return to Cecil Field in Jacksonville after a 30-day rotation in Haiti. The overwater deployment involved 2 helicopters and 12 personnel, and missions included over 140 sorties over 30 days for passengers and cargo, command and control operations, reconnaissance operations, personnel recovery training exercises, and hoist training exercises. EADS NA.

May 16/11: Crazy Horse. A ceremony at South Dakota’s Crazy Horse Memorial mountain marks the inauguration of UH-72A Lakota helicopters into the state’s National Guard. The ceremony included a Native American blessing, singing and dancing, and a commemorative blast on the mountain carving of the Lakota warrior. EADS NA UH-72 site.

Standing Rock Sioux Tribe chairman Charles Murphy says “Lakota” is a word that will represent all the people in the 7 tribes in the Dakotas and Nebraska, and he says they appreciate what the Guard has done.

April 2011: Update. The Army UH-72A fleet surpasses the 60,000 flight hour milestone.

Production in 2010 saw 53 helicopters delivered, and another 41 retrofitted with new missions equipment. That includes the now FAA-certified Combat Training Center mission package. The Security and Support MEP began retrofits this month, and early 2012 will see first delivery of new-production UH-72A S&S helicopters. So far, the Army’s UH-72As have freed up at least 23 Black Hawk helicopters for military service oversees. Source 1 | Source 2.

March 30/11: +4. A $21.5 million firm-fixed-price contract for 4 more UH-72A light utility helicopters; 4 AN/ARC-231 radio system production cut-ins; and 1 engine inlet barrier filter production cut-in.

Work will be performed in Columbus, MS, with an estimated completion date of April 30/12. One bid was solicited with one bid received (W58RGZ-06-C-0194).

4 UH-72As

March 1/01: This is not a drill. A UH-72A operating from the U.S. Army’s National Training Center Air Ambulance Detachment at Ft. Irwin, performs a real rescue, when a man is trapped in his truck in the surging Mojave River. EADS’ UH-72 site

Feb 14/11: FY 2012 request. The Pentagon releases its FY 2012 request, though the failure of the last Congress to pass a budget means that it’s FY 2011 requests are also pending.

All UH-72 funds from FY 2010-2012 are procurement funds; there is no RDT&E outlay. Orders are tailing off slightly from $325.2 million for 54 helicopters in FY 2010, to $305.3 million for 50 helicopters in FY 2011, to $250.4 million for 39 helicopters in FY 2012. The overall program, as noted earlier, calls for 345 UH-72s, plus the 5 the Navy ordered for its test pilots school.

Feb 9/11: Update. EADS North America provides an update on orders to date:

“The U.S. Army has ordered a total of 32 UH-72A Lakotas from EADS North America in Fiscal Year 2011… The latest contract brings Lakota orders to 219, composed of 214 rotary-wing aircraft for the U.S. Army and five for the U.S. Navy. Another Army order for 18 more UH-72As is projected in the current Fiscal Year budget, with the Army targeting a total acquisition of 345 helicopters through 2015, for a total of 350 from both services.”

Jan 4/11: +12. A $52.5 million firm-fixed-price contract for 12 UH-72A helicopters, 12 Airborne Radio Communication systems, and 2 Engine Inlet Barrier Filters that keep sand and fine particles out of the intakes.

Work will be performed in Columbus, MS, with an estimated completion date of April 30/12. One bid was solicited with one bid received (W58RGZ-06-C-0194).

12 UH-72As

Dec 7/10: AAS-72. EADS North America flies the 2nd of 3 company-funded Armed Aerial Scout 72X Technical Demonstration Aircraft (TDA), at the company’s American Eurocopter facility in Grand Prairie, TX. The 40 minute flight was used to demonstrate integrated targeting sensor, manned/unmanned teaming (MUM-T) and communications and navigation capabilities. EADS NA.

Nov 18/10: Update. The US Army showcases the new security and support model at the Pentagon. The Army says that 140 of 345 planned UH-72As have been delivered. Col. Neil Thurgood, project manager for Utility Helicopters at Redstone Arsenal, AL says that Lakotas are almost exclusively being used by the National Guard in support of homeland security, adding that there are no current plans to send the helicopter into combat. US Army.

Oct 26/10: Update. EADS North America touts the 5 UH-72A variants to date, and states that 138 Lakotas have been delivered to Army and Army National Guard units (133), and the U.S. Navy (5). Overall, the UH-72A fleet has flown more than 40,000 hours in operational service.

The 5 variants are MEDEVAC, Security & Support, VIP transport, and 2 more “associated with training missions that teach soldiers how to fight aircraft and recognize friend or foe on the battle space.” EADS UH-72 site.

Oct 25/10: AAS-72. The Armed Aerial Scout 72X (AAS-72X) team of Lockheed Martin, Eurocopter, and American Eurocopter is preparing for the initial flight of their 1st company-funded Technical Demonstration Aircraft (TDA). The 3 AAS-72X TDAs will have fully-integrated Mission Equipment Packages (MEP), and the initial flight is scheduled to occur in December 2010.

The MEP has been simulated in flight tests with a weight of 2,300 pounds, and development has continued at the MEP Systems Integration Laboratory in Lockheed Martin’s Orlando, FL facility. EADS NA.

Oct 18/10: Sub-contractors. Curtiss-Wright Controls, Inc. announces a contract from American Eurocopter to provide Skyquest Video Management Systems for the U.S. Army’s UH-72A Security and Support (S&S) Battalion Mission Equipment Package (MEP). The estimated value of the contract is $20 million, based on projected helicopter production and deliveries over the next 5 years. EADS North America has 187 Lakota helicopters on order from the Army, with the potential for up to 345 helicopters through 2015.

The Skyquest airborne surveillance system is designed, developed and manufactured at the firm’s Embedded Computing facility in Laindon, East London, UK. The hardware will be shipped to American Eurocopter’s Columbus, MS facility, where it will integrate the Skyquest VMS system onto the S&S Battalion-configured Lakotas. The contract will continue through 2015.

FY 2010

Orders; Production hits full rate; Navy deliveries; New security & Support kit; New missile test copters; #100 delivered; C-17 loading test; AAS-72 tests.

Kwajalein UH-72A
(click to view full)

Sept 29/10: +36 S&S. A $67.1 million firm-fixed-price contract for 16 security and support (S&S) mission equipment package (MEP) retrofits, and 20 S&S MEP production cut-ins, for Army National Guard LUHs. Work is to be performed in Columbus, MS, with an estimated completion day of Aug 31/12. One bid was solicited with one bid received (W58RGZ-06-C-0194).

U.S. Army National Guard security and support battalions are on call to their own and neighboring states to help civil authorities as requested, and they can also be tasked for military missions. Most currently fly UH-1 Hueys. Asked about this MEP set, Eurocopter USA replied:

“The UH-72A S&S Battalion configuration includes a forward centerline-mounted camera system with electro-optical and infrared sensors and laser pointer, a 30 million candlepower searchlight, operator console, cockpit and cabin touch-screen displays with moving map, a video management system, a digital video recorder and data downlink system, plus an external hoist and additional avionics and communications equipment.”

36 UH-72A S&S

July 28/10: Update. Eurocopter says that it has delivered 125 UH-72As so far, all of which have been on time and on budget.

June 6/10: Kwaj. The US Army deploys 4 specialized UH-72A helicopters to the Ronald Reagan Ballistic Missile Defense Test Site at Kwajalein Atoll, Pacific Ocean. The Kwajalein helicopters arrived in a C-17, and are painted in high visibility orange. They’re also equipped with skid-mounted floats, integrated life rafts, and jettisonable cockpit doors. Source.

April 2010: Germany. The US military delivers 5 UH-72As to the U.S. Army’s Joint Multinational Readiness Center (JMRC) in Germany. The JMRC helicopters will support pilot training for combat engagements, carry observers of war game scenarios performed against aggressor unit aircraft squadrons, and perform MEDEVAC duties as needed. The JMRC’s UH-72A fleet is scheduled to rise to 10 by January 2011. Eurocopter | UH-72 site.