2016-09-08



PAK-FA at MAKS-2011
(click to view larger)

Russia wants a “5th generation” fighter that keeps it competitive with American offerings, and builds on previous aerial and industrial success. India wants to maintain technical superiority over its rivals, and grow its aerospace industry’s capabilities. They hope to work together, and succeed. Will they? And what does “success” mean, exactly?

So far, preliminary cooperation agreements have been signed between Sukhoi/United Aircraft Corporation, for a platform based on Sukhoi’s T50/PAK-FA design. This DID FOCUS article consolidates specific releases and coverage to date, and adds analysis of the program’s current state and future hurdles.

The PAK-FA/ FGFA

Sukhoi’s “T50”



Movable LEX
(click to view larger)

The plane behind the project has taken on several names. The T50 may eventually become the SU-50, but for now it’s referred to as PAK-FA. The aircraft project is also known as FGFA (India: Fifth Generation Fighter Aircraft), and PMF (Russia: Prospective Multirole Fighter). Key characteristics include:

Shaping: Some observers have tried to characterize the T50 as a copy. That’s a mistake. The PAK-FA’s first flight revealed a distinctively Russian stealth-driven configuration, which borrows from previous Sukhoi designs and priorities. The prototype has some clear stealth-limiting features, from fit quality, to features like Sukhoi’s standard spherical InfraRed Scan & Track (IRST) system mounted near the cockpit. Those may change in the production aircraft; meanwhile, a smaller tail, clear stealth shaping, and internal weapons carriage all indicate a strong push toward a stealthier plane.

The PAK-FA’s air intakes are set back from the leading edge root extensions (LERX), and one interesting wrinkle involves movable LERX shapes that come forward from the wings to join the aircraft body. This “PChN/ Movable LEX” feature apparently allows some of the maneuverability bonuses normally associated with canards on planes like the SU-30SM, SU-34, etc., but in a much lower profile design.



RT feature

Engines: Reports concerning the fighter’s initial engines vary. Some sources contend that the engines used in its test flight are 5th generation engines, but most of them report that it is borrowing from the SU-35 program for now, until more advanced engines designed specifically for the plane can be fielded. Both descriptions could be correct. The SU-35S reportedly uses a heavily-upgraded and more reliable version of NPO Saturn’s AL-31F, named the Saturn 117S. It is said to offer over 30,000 pounds of thrust, with full 360 degree thrust vectoring, and is believed to equip initial PAK-FA fighters. The longer-term question is whether incremental 117S upgrades will let the aircraft reach its required “5th generation” performance levels, or whether the AL-41F project, which aims to use a new and improved engine core, will be able to replace the 117S in future.

Weapons: Russian reports cite carriage of 8 missile suspension points inside the fuselage, to match the F-22. While the Raptor has 2 body bays (with space-saving AVEL launchers) and 2 smaller side bays, the Russian plane is big enough to have 4 body bays and 2 side bays. Air-to-air weapons will certainly include the improved AA-11 (RVV-MD SRAAM) and AA-12 (RVV-SD MRAAM), but RIA Novosti adds that it has the ability to carry 2 ultra long range AAMs, presumably the 200-400 km Novator K-100-1. These “AWACS killers” are also intended for use on the SU-35, and their size may force the PAK-FA to carry them externally.

To date, the T50’s ground-attack weapon capabilities remain something of a mystery.

PAK-FA prototype
(click to view larger)

Sensors: The PAK-FA’s advanced Tikhomirov AESA radar is still undergoing testing on other platforms, and its readiness could be important to the project. As is true of all 4+ generation Russian designs, the radar will be supplemented by an IRST that looks for the heat produced by engines and air friction. This allows long-range, no warning missile attacks, and offsets enemy advantages from radar stealth.

Another approach to offset enemy radar stealth involves L-band radars in the wing’s leading edges, to help the plane find other X-band optimized stealth fighters. The plane’s SH121 radar complex will reportedly add another 3 small X-band AESA radars around the front and sides of the aircraft, in order to provide full radar coverage. Harmonizing these features with stealth, and ensuring that they don’t become a maintenance nightmare, will be another important technical challenge for the new fighter.

The fighter’s biggest technical challenge will involve harmonizing all of these sensors into a single view for the pilot. Russia and India aren’t short on programming talent, but pilot ergonomics has been a long-standing weakness in Russian fighters, as western pilots found when they began flying East German MiG-29s. Good sensor fusion is a technically challenging task, especially if the goal is a system that can accommodate upgrades without ruinous expense. The talent is there, but both Russia and India have mixed histories trying to manage those kinds of military efforts.

Other Electronics: Sukhoi’s releases emphasize an advanced datalink that allows PAK-FA aircraft to share situational awareness, much like NATO’s “Link 16” standard. As the USAF has discovered, however, having other platforms share information with stealth aircraft, while retaining “low probability of intercept” to avoid giving the stealth aircraft’s positions away, is difficult. Russia and India will need to resolve that issue, or accept the operational limitations of a unique but incompatible datalink.

Test flight
click for video

All of these characteristics show a convergence of Russian design with leading-edge technologies. Russian 4+ generation fighter designs have always placed a premium on super-maneuverability, and so does the T50. Russian AESA radars are becoming service-ready, and the T50 looks set to be a key platform for their use. Engine improvements may even allow Mach 1+ supercruise if the T50’s weight can be kept down, and if Saturn can deliver on promised operational performance – but both of those “ifs” remain to be proven.

Once it becomes operational, this plane is expected to get the designation SU-50. The big question right now is how close it is to reaching that goal.

Development Timelines, Risks, & Differences of Opinion

Defined Design? A Disagreement

From YF-22 to F-22
(click to view full)

As of February 2014, 5 PAK-FA prototypes are flying, and 2 more are in ground test roles, which is short of the 8 that were expected to be available by the end of 2013. The “T3” prototype was the first to have the full avionics and radar suite, including the AESA radar. The plane is reportedly preparing for full operational trials in 2015, and VVS fielding in 2016-2017, but the history of stealth fighters justifies some caution about those dates.

In 2009, former Hindustan Aeronautics Ltd. chairman Ashok Baweja took that caution several steps further, saying that that the current PAK-FA prototype and tests were only “proof of concept” level work. The Russians had already approved the design in 2008, so they clearly didn;t see things that way, but America’s F-22 program history made Baweja’s thesis plausible. The YF-22 prototype made quite a few modifications en route to its F-22A designation, over a period lasting several years. The Russian design has changed since 2009, including visible reinforcements to indicate a need for redesign in the wings and other areas. On the other hand, external design changes haven’t been much in evidence, and they continue to move forward with more advanced tests.

India’s low level of expertise designing advanced fighters, and the advanced nature of Russia’s project before India joined, both point toward a final FGFA design that’s much closer to the planes Russia is already flying.

Russian & Indian Timelines

PAK-FA Mach flow
(click to view full)

Differences of opinion re: the fighters’ readiness also express themselves in each side’s proposed timelines. Russia is focused on 2015-2016 production and 2017-2018 fielding, though senior officials acknowledge that full serial production won’t begin until 2020 – 2024.

Indian officials have pushed a timeline that’s up to 4-5 years longer, in order to develop many of the FGFA’s systems and make a long list of changes. As the cumulative cost and risk of their chosen course become apparent, however, they’re reducing their demands. A 2012 interview with Air Chief Marshal Browne suggests that India’s FGFAs will hew much more closely to Russia’s design, beginning with the current single-seat configuration instead of a new 2-seat layout. About 100 HAL engineers are already working on the project from a facility in Bangalore, and another contingent has moved to Russia to work in the Sukhoi design bureau.

That’s all well and good, but it’s 2014, and the joint R&D contract between Russian and India remains unsigned. Plenty of time remains for meddling, as India was expecting to receive prototypes in 2015, 2017, and 2018. India would still have to fund their own national program of FGFA (SU-50KI?) customization for the Indian air force by a joint team of Russian and Indian engineers. The difference is described as “mission hardware and software,” though it would be surprising if Indian bureaucrats’ fetish for “indigenization” was forced to stop there. Each prototype will be slightly different, creating an incentive for the military and political figures to press for additional changes and alternations.

If India’s FGFA R&D program can get underway in 2014, and if it progresses without major delays, a 2018 prototype would finalize the base configuration, and Indian development could end in 2019. Whereupon series manufacturing would begin at HAL in 2022.

Note the number of “ifs” required to meet even that target. Which will also have to contend with HAL’s known high-tech production industrial issues (vid. LCA Tejas & M-MRCA programs). They’ll need to be solved by the time FGFA production begins, because its manufacturing techniques are likely to be a step beyond anything HAL has attempted to date.

So much for the original plan of IAF service by 2017. If current dates hold true, India wouldn’t see operational serving FGFA fighters until 2025 at the earliest. At the same time, India’s planned FGFA buy is shrinking, from over 200 to around 144.

In a project of this nature, it’s par for the course for Russia and India to both end up being too optimistic in their initial schedules. There’s still more than enough room for that dynamic to happen within the revised schedules, as the project works through configuration, testing, and production issues. The history of modern fighters suggests that software could prove to be particularly troublesome.

Contracts & Key Events

2015 – 2016

Sukhoi insists it will meet new 2016 production deadlines.

Airshow demo

September 9/16: Russia’s Deputy Minister for Defense Yuri Borisov has said that the Sukhoi PAK-FA is ready for mass production with Moscow planning to acquire a squadron of aircraft in 2017. Equipped with advanced avionics and all-digital flight systems, the PAK-FA is set to become the first operational stealth aircraft of the Russian Aerospace Forces. An export version is expected to be available by 2025.

June 21/16: United Aircraft Corporation (UAC) has announced that its Sukhoi T-50 PAK-FA is now ready for mass production. According to Russian newspaper Izvestia, the fifth generation fighter almost fully meets the requirements of the military’s combat capabilities. UAC is also currently preparing a proposal to be submitted to the Russian Ministry of Defense on starting serial production.

December 11/15: The Russian Deputy Defense Minister Yuri Boisov has said that testing of the PAK FA is nearly complete. The 5th generation fighter is intended to replace the Mig-29 and Su-27 currently currently in service. The fighter is part of a development partnership between Russian manufacturer Sukhoi and India’s Hindustan Aeronautics Limited. The Indian Air Force may purchase 154 of the aircraft once they come into service in 2016. The PAK FA is set to rival the US made F-35 fighter, but holds a major export advantage in that it is much more cost effective.

August 27/15: Russia’s “fifth generation” Sukhoi PAK FA stealth fighter is to get the X-58USHK missile, which will reportedly reach mach 3.5. But the critical advantage the new combo would bring was expressed in the a Tass sub-headline: “The missile will be placed inside the fighter’s fuselage.” Thus the PAK FA – also called the T-50 – will remain stealthy, where the F-35’s weapons bay has grown even smaller on the new variants and most weapons will have to be mounted externally.

Feb 2/15: Agreement on production split. The Hindu reports that the main sticking point (who produces what) is settled between the Russians and the Indians. Up to now, the Indians were producing only 13 percent of the fighter, and none of the interesting technology bits. The agreed-upon split hasn’t been made public.

Feb 2/15: On (new) schedule. Originally slated for 2015 production, the PAK-FA, now being called the T-50 in press materials, is to be produced in Komsomolsk-on-Amur in 2016, according to company officials. There is no mention of an export market. India had already cut its order from 200 fighters to 144, but bureaucrats have also pushed back certification to 2019, after which production could be authorized. Complaints by the Indian Air Force in early 2014 may indicate some buyer’s remorse.

2014

Negotiations with India turn tense, remain in limbo as Russia moves ahead; Better stealth than the F-22?

Oct 21/14: Sub-contractors. Russia’s Radio Electronic Technologies concern has provided the 1st batch of Himalayas internal electronic warfare systems for the new jet.

The Himalayas EW system was developed by RET’s Kaluga Scientific Research and Radio Technology Institute, and is manufactured at its Signal Radioplant in Stavropol. Sources: Defense World, “Russian T-50 Aircraft Gets Himalayas EW System”.

Sept 15/14: Negotiation. The Russians and Indians are saying different things to Defense News. “A “Russian diplomat in India” tells them they they “have finally sorted out all sticky issues that have been holding back an agreement,” adding that India’s workshare was eventually expected to increase from 13-18% to 40%. India’s MoD refused to confirm this, “especially those [issues] related to workshare between the two countries”.

We’ve seen enough programs involving India to be skeptics, even when Indian officials will confirm such stories. The magazine’s sources say that India and Russia will sign a final agreement on the program the end of 2014. Take that as the metric, and believe it when you see it. Sources: Defense News, “Indo-Russian Jet Program Finally Moves Forward”.

Aug 30/14: Tension. India isn’t pleased with the lack of response to its questions concerning the recent PAK-FA engine fire (q.v. June 10/14), NPO Saturn AL-41FI jet engine performance, Byelka AESA radar performance, the lack of permission for its pilots to fly the jet in Russia, and HAL’s low workshare. India’s lack of a firm development agreement is the 1-sentence argument for much of this situation, except for the engine fire question and HAL’s workshare.

HAL’s workshare has reportedly dropped from 25% to just 13%: tires, the VOR-DME basic navigation avionics, coolant for the radar, a laser designation pod and the head-up display. This list appears to justify analysis that HAL simply doesn’t yet have the capability to be a full partner in such a sophisticated aircraft, and may also be a function iof Indian dithering as Russia simply goes ahead and makes final decisions about the PAK-FA’s development..

Within HAL’s workshare, the Laser Designation pod itself is unlikely to come from India, but may be produced under license. Israel’s RAFAEL LITENING pods equip many Indian aircraft, including the SU-30MKI, but Eastern European and American pressure on Israel makes SU-50 integration tough to contemplate. Thales’ Damocles pod, which already equips Malaysia’s Su-30MKMs and would equip Indian Rafales, would be a more logical choice.

The real challenge here is twofold. One is the M-MRCA program, whose $10 billion cost growth really shrinks the overall room for PGF funding within India’s budgets. The related challenge is time, and “IAF sources told IHS Jane’s that this deadline [to begin Indian production in 2020 – 2021] would be missed by several years.” Sources: Daily Mail India, “India-Russia jet deal hits turbulence over ‘technical worries’ ” | IHS Jane’s Defence Weekly, “Indian Air Force unhappy at progress of PAK-FA fifth-gen fighter”.

Aug 4/14: Negotiations. Still no firm production agreement re: the PAK-FA/ FGFA/ PMF, following the end of the initial engineering development contract in 2013. Russian sources continue to make hopeful noises, but at this point, it means very little until there’s a firm contract in place. Sources: Itar-Tass, “Sukhoi to sign another contract with India on FGFA”.

June 10/14: Fire. A commission will be investigating:

“Today after the regular test flight of the T-50 aircraft at the airfield of the M.M.Gromov Flight Research Institute in Zhukovsky near Moscow, while the plane was landing, a smoke above the right air intake was observed, then a local fire broke out. The fire was quickly extinguished. The plane is to be repaired…. This incident will not affect the timing of the T-50 test program.”

The Moscow Times suggested that the damage might leave the plane out of action for a little while, as people reportedly: “…saw smoke and flame billow out of the front of the engine and [it] caused visible damage to the exterior of the aircraft.” Sounds like an engine issue. Maybe one day, we’ll know. Sources: Sukhoi, “Sukhoi’s message over the incident with the T-50 aircraft” | Moscow Times, “Russian Advanced Prototype Fighter Jet Erupts into Flames on Landing”.

Fire

Feb 21/14: Production version. Sukhoi announces that their production version will not be waiting until 2016, while the current set of 4 flying and 2 ground prototypes continue their work at Zhukovsky. In fact:

“Today the flight model of the prospective 5th — generation fighter aircraft (PAK-FA, T-50) arrived to the 929th Chkalov State Flight Test Centre’s airfield in Akhtubinsk for State Joint Tests…. The PAK FA tests program included aero-dynamic features evaluation, tests of stability and controllability and of dynamic strength, function check of on-board equipment and aircraft systems. Optical locator system as well as active electronically scanned array radar was tested on the aircraft with positive results obtained. Air refueling mode was tested. Supermaneuverability tests of the aircraft are under way. Aircraft systems are being tested on the test stands, ground experimental works continue.”

It’s still possible for hardware or software problems to make the delivery of 60 combat-capable aircraft an impossible goal by 2020, and Russian reports aren’t going to involve public accountability or discussion of test results. Even so, the Akhtubinsk arrival is embarrassing timing for War Is Boring’s same-day report. Sources: Sukhoi, “T-50-2 fighter aircraft made the flight to Akhtubinsk” | Russia & India Report, “Russian Air Force receives first FGFA T-50 fighter for tests”.

Feb 21/14: No mystery. “Russia’s New Air Force Is a Mystery” wonders why Russia is buying SU-30MK2s, SU-30SMs and SU-35s, in addition to the future PAK-FA. It turns out that the answer is extremely simple: industrial priorities that bought up aircraft the Chinese stopped buying, took advantage of successful advanced SU-30MKx export developments, and aim to provide the SU-35 with a home country order base for potential exports. That sort of thing happens all the time, everywhere. The article ends up stinging itself with this quote re: the PAK-FA:

“The T-50’s schedule has stretched farther and farther to the right. Originally planned for handover to the air force’s Akhtubinsk flight test center for evaluation in 2014, recent announcements suggest this might now slip until the second half of 2016. This would derail plans to declare initial operational capability, and the start of full-scale production, at the end of 2016.

The best-case scenario would have seen 60 production T-50s delivered between 2016 and 2020, but this now seems a distant hope. As a result, the air force is badly in need of supplementary equipment.”

The 1st PAK-FA arrives in Akhtubinsk for testing that same day. Sources: War Is Boring, “Russia’s New Air Force Is a Mystery”.

Feb 7/14: Timelines. Russia and India are still negotiating the FGFA R&D contract, but India’s Chief of the Air Staff and Air Chief Marshal Norman Anil Kumar (A K) Browne tells the Press Trust of India that the 1st FGFA prototype will arrive in India this year, for testing at Ojhar AB, located NE of Mumbai. One imagines that he’s speaking on the basis of a draft R&D contract that would have Indian scientists and test pilots in Russia until the R&D phase is scheduled to end in 2019.

2022 is now given as the planned in-service date, as India slip farther and farther from the original plan of having these planes in service by 2017. That 2017 date was always a pipe dream, and even present dates depend on very large financial decisions being made very soon by an unpopular government, or by its electoral successor. It’s more realistic to assume that the draft R&D agreement won’t actually become a signed contract and disbursed funds until 2015 or later, with attendant effects on India’s schedule.

Meanwhile, Russia continues to develop the plane,m but even they are several years from serious fielding. Federal Service for Military-Technical Cooperation (FSMTC) First Deputy Director Alexander Fomin is quoted as saying that testing and manufacturing ramp-ups will require: “At least… [6-10 years] before we build a sample of the fifth generation fighter plane and being its serial production.” Sources: Itar-Tass, “Russia fulfils FGFA obligations with India – Alexander Kadakin”.

Jan 21/14: India. India’s Air Force is directly criticizing the stealth fighter program, according to the minutes of a Dec 24/13 meeting chaired by secretary of defence production Gokul Chandra Pati:

“Business Standard has reviewed the minutes of that meeting. The IAF’s three top objections to the FGFA were: (a) The Russians are reluctant to share critical design information with India; (b) The fighter’s current AL-41F1 engines are inadequate, being mere upgrades of the Sukhoi-30MKI’s AL-31 engines; and (c) It is too expensive. With India paying $6 billion to co-develop the FGFA, “a large percentage of IAF’s capital budget will be locked up.”

On January 15, the IAF renewed the attack in New Delhi, at a MoD meeting to review progress on the FGFA. The IAF’s deputy chief of air staff (DCAS), its top procurement official, declared the FGFA’s engine was unreliable, its radar inadequate, its stealth features badly engineered, India’s work share too low, and that the fighter’s price would be exorbitant by the time it enters service.

Top MoD sources suspect the IAF is undermining the FGFA to free up finances for buying 126 Rafale medium multi-role combat aircraft (MMRCA) for an estimated $18 billion, an acquisition that has run into financial headwinds because of budgetary constraints….”

Perhaps if India hadn’t structured its MMRCA competition to completely ignore the costs of the competing aircraft, this wouldn’t be happening. But they did, and it is. Sources: India’s Business Standard, “Russia can’t deliver on Fifth Generation Fighter Aircraft: IAF”.

Jan 16/14: T-50 trolling. Rosoboronexport’s parent firm Rostec decides to troll the aviation world, with claims that the PAK-FA will have better stealth than the American F-22 Raptor:

“The average [radar cross section value] for the T-50 fighter is between 0.1 and 1 square meter…. the T-50 is now ahead of not only all other fighters of the Russian Army, but also foreign models. For example, the visibility of the American fifth-generation F-22 fighter is 0.3-0.4 square meters, according to PAK FA chief designer Alexander Davidenko.”

This means almost nothing. First, the Russian PAK-FA range includes values that are a closer match for the Eurofighter than the F-22. Second, Davidenko couldn’t know the F-22’s real production values without access to American flight test data, and there are rumors that it’s smaller than 0.3 m2. The third issue is production. Davidenko’s claims for the PAK-FA back existing assessments that it’s a legitimate stealth aircraft design, but production work affects final values for any plane. If it’s shoddy and alignment is poor, for instance, a design with RCS of 0.1 m2 could easily hit 1.0 m2 in reality. Russia is known for many things, including excellent and robust fighter designs, but precision work? Not so much. A real comparison would require test data from production aircraft (q.v. Nov 12/12 caveats), including different values from various angles, and their different success levels against different radar bands. That isn’t on offer for either plane.

Other points in the release are more informative, if true. Rostec says that composite materials are just 25% of the fighter’s weight, but cover 70% of its surface. A new power system design from Rostec’s Aviation Equipment provides double the amount of electrical power offered by previous Russian systems. We hope they have better luck than Boeing has, but that power will be needed by Radioelectronic Technologies’ new avionics and related systems. With respect to the plane’s biggest current deficit, UEC has an initial-model of the next-generation AL-41F1 thrust-vectoring engines installed in a prototype now, and Rostec is feeding general expectations that the AL-41 will give the new fighter supercruise capability. Sources: Rostec, “The T-50 Fighter will feature even greater stealth capabilities” | Air & Cosmos, “Le T-50 russe serait plus furtif que le F-22”.

2013

Test flights, incl. the new 5th prototype; Negotiations and tensions with India.

T50, incoming
(click to view full)

Oct 28/13: #5. Sukhoi flies the 5th T50 prototype at its Y.A.Gagarin KnAAZ aircraft plant in Komsomolsk-on-Amur. Once it finishes local flight tests, the aircraft will join the program flight tests at Zhukovsky, near Moscow.

Sukhoi pegs the number of flights to date at “more than 450”, with another 2 planes are involved in ground tests as a complex ground stand and static testing platform, respectively. Sources: Sukhoi release, Oct 28/13.

Oct 21/13: Indian complaints. Aviation Week reports that India is dissatisfied with their development workshare, in a project they came op late and close to lockdown on their partner’s side, and for which they have only recently managed to produce anything resembling their specifications (q.v. April 10/13):

“We have a major opportunity in the FGFA program,” Indian air force (IAF) Deputy Chief Air Marshal S. Sukumar says. However, “at the moment [the 15% development share] is not very much in favor of Indian development. We are flagging it through the government. It should be much more focused towards indigenous development capability.”

The problem is that 4 Russian T50 prototypes have performed about 450 test flights since January 2010, and the VVS plans to begin inducting the fighter in 2015-2016. Even if they’re a year late, it doesn’t leave much room for development. That would have required fast decisions to begin the contract early, when the design was still in need of refinement.

India’s desires and its modus operandi are in conflict once again, and the question is whether the dichotomy will become a stumbling block in negotiations for the final $11 billion system development contract. At this point, the only way to square that circle would be to increase the number of differences between the Russian and Indian fighters, or to involve India in developing the “Block 10” next iteration of a fighter whose core technologies are already a big stretch for Indian firms. Either approach would drive up overall costs for the contract under negotiation (q.v. July 15/13), and add substantial risk to India’s plans to begin manufacturing at HAL in 2022 – itself a problematic proposition, given HAL’s record. Sources: Aviation Week, “India Concerned About Fifth-Gen Fighter Work Share With Russia”.

Oct 18/13: Aircraft issues. An article in The Aviationist looks at issues with the PAK-FA, which don’t get the same exposure as western projects with their public oversight. Piotr Butowski of the Polish Magazyn Lotnictwo notes that:

“…the plane still suffers from the strict g-limits…. The plane underwent a modernization in the Sukhoi facility on the Polikarpov Street in Moscow Dec. 2012 and May 2013. The airframe was reinforced according to the flight tests and static tests that were already carried out; many new [metal strip] overlays can be seen on the airplane’s surface.”

Problems and modifications aren’t abnormal. The 1st PAK-FA prototype has structural cracks in 2011, and the 2nd had an engine flameout cancel its public MAKES 2011 air show performance. Sources: The Aviationist, “Russia’s most advanced fighter jet’s troublesome childhood”.

July 15/13: India Delays. The FGFA project’s parameters may be set (q.v. April 10/13), but there’s a problem with the R&D deal, which was pegged at $11 billion equivalent. The Times of India:

“Defence ministry sources said the inking of the final design and R&D contract for the stealth fighter has been hit by a huge delay, with Russia also jacking up costs for the futuristic project. “It’s very unlikely the FGFA final design contract will be concluded in the 2013-2014 fiscal,” said a source. “The timeframes will now have to be revised. MoD has established a committee of specialists and finance officials to verify the rise in costs. An internal contract negotiation committee is also in progress…”

Russia isn’t going to wait, and will continue development of their version while they wait for India’s signature. Operational testing is slated to begin in 2014. If FGFA negotiations stretch into 2015, the net effect will be to severely delay India’s variant, even as the base Russian design becomes more and more firmly set.

April 25/13: VVS flight. The Russian air force’s (VVS) Chkalov Flight Test Center begins flying the PAK-FA prototypes, with a 2-hour flight from the M.M. Gromov Flight Research Institute in Zhukovsky (Moscow region).

At present, Sukhoi has 4 flying test planes, which are mostly flown by company test pilots, and 2 ground test planes. Sukhoi.

April 10/13: India. Sukhoi announces that the parameters for their joint FGFA project with India are set:

“The contract to develop a sketch and technical project of the Russian-Indian perspective multi-functional 5th-generation fighter (PMI/FGFA) was completed. The fighter design was fully developed. The both parties have agreed upon on the amount and division of work during the research and development (R&D) stage. A contract for the R&D is being prepared. It is to be signed this year.”

March 1/13: Plans & Schedule. High-level Russian and Indian sources offer a bit more clarity concerning dates, but they seem to be at odds regarding electronics.

Russian VVS commander Gen. Victor Bondarev expects weapons release trials to begin in 2013, as the number of aircraft rises from 4 – 8. If tests go well, the fighter could enter series production in late 2015 or early 2016. Based on past fighter programs, that may be a bit optimistic.

Meanwhile, IAF chief of staff Air Marshall N.A.K. Browne is expecting to sign the big design & development contract for the FGFA in 2013. They’ll receive 3 developmental prototypes in India in 2015, 2017 and then 2018, rather than the wider 2014-2019 window reported earlier. That SDD version would apparently be fully common between Russia and India, making Pogosyan (vid. Feb 7/13) correct to that point. India would then fund, as a separate project, FGFA (SU-50KI?) customization for the Indian air force by a joint team of Russian and Indian engineers. The difference is described as “mission hardware and software,” though it would be surprising if Indian bureaucrats’ fetish for “indigenization” was forced to stop there. Series manufacturing would begin at HAL in 2022.

If true, it means that India wouldn’t see operational serving FGFA fighters until 2025 at the earliest, and that’s only if HAL’s known industrial issues with high-tech production are fully solved by 2022. AIN.

Feb 7/13: Avionics. At Aero India 2013, Obedinnoe Avaitstroitel’noi Corporatsii (United Aircraft Corp.) President Mikhail Pogosyan says that the new fighter will “have a single set of on-board equipment [cockpit avionics],” as a requirement of the Indian Air Force. He adds that India’s fighters will also share the Russian single-seat configuration.

Both of those statements would represent major changes from India. India’s initial plans involved a 2-seat variant that would follow the example of programs like the SU-30MKI, and create a unique cockpit avionics set that used equipment from Indian companies and foreign vendors. If Pogosyan is correct, India has backtracked toward a standard type configuration, and joint funding of upgrades. UPI.

2012

India’s timeline keeps falling back, as it cuts plans to 144 jets; No SU-50 for ROKAF; Prototype #4 flies; AESA radar testing begins.

#T2 lands
(click to view full)

Dec 12/12: #4 flies. The 4th prototype takes flight at the snowy Komsomolsk-on-Amur Aircraft Production Association (KnAAPO). UAC.

Nov 12/12: RCS guess. Airpower Australia uses public-domain photos coupled with the Physical Optics (PO) method for predicting the Radar Cross Section of complex targets on Russia’s T50, using VisCam View software to produce a PolyChromatic Spherical Representation (PCSR). Without flight test data, it’s still a guess, but it’s a kind of guess that Moore’s Law has made available outside of large intelligence agencies.

Their guess? It won’t match the F-22, or even China’s J-20, but if they introduce a rectangular faceted design to the engine nozzles and add radar absorbent coatings, they might beat the F-35. Sources: Airpower Australia, “A Preliminary Assessment of Specular Radar Cross Section Performance in the Sukhoi T-50 Prototype” | WIRED Danger Room, “Russia’s Stealth Fighter Could Match U.S. Jets, Analyst Says”.

Oct 9/12: During an interview with India Strategic, Chief of the Air Staff Air Chief Marshal NAK Browne confirms that HAL has committed $6 billion to joint development. Plans have changed, and India’s 144 planned FGFAs will all be single seaters, now, hewing much more closely to the Russian baseline. In the same vein as India’s SU-30 MKIs, however, they’ll have some avionics and integration differences. According to the ACM Browne:

“… the first prototype is likely to be delivered to India in 2014 followed by two more in 2017 and 2019. The series production then “will only be ordered based on the final configuration and performance of the third prototype.”

See: India Strategic | IANS.

Aug 19/12: Even later to India. Reports now indicate that the 1st FGFA prototype flight tests should start in India in 2014, with deliveries to the Indian Air Force by 2022, a full ten years from now. This would be the start of a $30+ billion, 250 plane program over the next decade, at roughly $100 million each.

Closer to the present, Russia and India are reportedly finalizing the research and development phase at $11+ billion, split evenly between the two parties. Business Standard | AviationWeek.

Aug 8/12: Radar. Sukhoi announces that they’ve begun flight tests of the PAK-FA’s Tikhomirov “active phased array radar system” in both air-to-air and air-to-surface test modes. Initial trials toward flight refueling also take place this month. Sukhoi | The DEW Line | RIA Novosti.

May 14/12: Late to India. India is already backtracking on service dates for its FGFA variant of Sukhoi’s T50, bringing them closer to predictions made by outside observers years ago. M M Pallam Raju has moved the plane’s certification and production start date from 2017 back to 2019. Close examination shows that 2020 or beyond is more likely.

India’s Business Standard also highlights a number of areas that aren’t settled, where ongoing specifications changes and/or technical problems may end up delaying the fighter and send India’s costs skyrocketing. India reportedly wants 40-45 design changes to the current PAK-FA, including its own avionics and a “360 degrees” AESA radar. That last requirement is likely to involve AESA “cheek fairings” that need to maintain aircraft stealth levels, a tailcone radar, and the internal computing and software required to fuse all of those radars into a single picture. They also want at least 2,000 hours of certification flying, and possible configuration changes in light of tests. India now expects their fighters to prepare for service no earlier than 2019, and if the IAF fields a 2-seat version, it’s likely to take even longer. All of India’s changes add 3 types of risk.

One is technical risk. India’s history is littered with overly ambitious projects that India’s Ministry of Defense and associated state-run agencies approved, but could not execute. The cutting-edge nature of the FGFA project magnifies those risks, even with Sukhoi’s assistance.

The 2nd risk is cost risk. Sukhoi’s help, and the associated design, production, and testing of new FGFA equipment, won’t come for free. The more changes India makes, the more the project will cost them. Russia isn’t going to pick up the tab for changes to a design their air force has already approved, and even the “Tactical Technical Agreement” that specified Indian changes isn’t going to mean much if costs become a problem. Russia has forcibly renegotiated critical defense contracts with India several times, and won’t hesitate to do so again.

The 3rd risk is schedule risk. Since Russia is focused on fielding the current single-seat configuration in its current form, while India is focused on major configuration changes and is still debating a 2-seat variant, both of those timelines could turn out to be true. Russia could wind up fielding SU-50 squadrons several years before India even finishes development. India’s Business Standard.

Jan 29/12: Korea: No PAK-FA. The Korea Times quotes a DAPA spokesman, who confirms the potential F-X-III competitors:

“No Russian firm submitted an application to attend the program’s explanatory session, which was a prerequisite to participate, by the Friday registration deadline,” a spokesman of DAPA said. He noted that a representative from Swedish company Saab, which has been searching for additional export orders for its Gripen multirole fighters, successfully filed an application for the mandatory session along with Boeing, Lockheed Martine [sic] and EADS.”

This means that the Indo-Russian PAK-FA will not be part of the $7+ billion competition, despite reports (vid. July 20/11) that it was intending to participate, just as Russian disinterest kept the SU-35 out of F-X-2.

2011

Prototypes #2 & 3 fly; Testing flameout; South Korean opportunity?

PAK-FA: takeoff!
(click to view full)

Dec 22/11: #3 flies. First flight of the 3rd PAK-FA prototype from Sukhoi’s KNAAPO aircraft plant in Komsomolsk-on-Amur. Sukhoi.

Sept 6/11: Exports? Russia & India Report highlights an analysis by Russia’s unofficial Centre for Analysis of World Arms Trade (CAWAT), which takes a look at potential buyers of the PAK-FA’s export version. They see a potential for 274-388 export units beyond India or states that spun out of the Soviet Union, like Kazakhstan et. al. Their projections for possible buyers, and their projected purchasing periods, include:

Algeria (2025-2030)

Argentina (2035-2040)

Brazil (2030-2035)

Venezuela (2027-2032)

Vietnam (2030-2035)

Indonesia (2028-2032)

Iran (subject to lifting of the arms embargo, 2035-2040)

Kazakhstan (2025-2035)

China (“subject to certain conditions”, 2025-2035)

Malaysia (2035-2040)

Syria (2025-2030)

Aug 24/11: Flameout. Flight International conveys NPO Saturn general director Ilya Federo’s explanation of the MAKS 2011 failure:

“The motor did not fail – in fact, it was put by erroneous control input into a wrong mode that caused the surge. This is not an engine failure, but the wrong data input caused by a malfunctioning sensor feeding data to the flight control system. After what had happened the motor was checked [and] the malfunctioning sensor was replaced by a good one. Today, there is no issue with this engine.”

Aug 22/11: Flameout. After performing a basic fly-over with the PAK FA, Sukhoi intended to close Russia’s MAKS 2011 air show with a bang – and did, sort of. The pilot of its second prototype PAK-FA/T50-2 was forced to abort his take-off run, and the planned flying routine, after 2 bursts of flame erupted from the right engine.

The show’s organizers compounded the embarrassment by promising that the 1st prototype would fly instead – but it was not on site, and is believed to be in maintenance following its Aug 17/11 demonstration. Flameout: Flight International (incl. flame burst picture) | India’s Open magazine | China’s Xinhua || Appearance: Moscow Times | Pravda | RIA Novosti | Voice of Russia | Reuters | UPI | WSJ Emerging Europe blog | op-ed – Right-wing Heritage Foundation, USA.

July 20/11: PAK-FA for South Korea? As South Korea’s DAPA eases the criteria to try and foster more competition, DAPA’s Col. Wi Jong-seong says that “Russian aircraft manufacturer Sukhoi expressed its intent to compete in the fighter jet procurement project early this year.” The report quotes him as saying that Sukhoi’s T50 PAK-FA will be up against Boeing’s stealth-enhanced F-15SE Silent Eagle, Lockheed Martin’s F-35 Lightning II, and EADS’ Eurofighter Typhoon. Assuming we don’t have an F-X-2 repeat, where all competitors but one drop out.

At this point, FX-III is being touted as a 60 jet buy of high-end fighters, with a budget of 8.29 trillion won ($7.86 billion). Eurofighter reportedly offered a better deal than the F-15K in F-X-2, but lost. The firm recently proposed to phase in Korean assembly for Phase III, with the 1st 10 made in Europe, the next 24 using Korean components, and the last 26 assembled in Korea. Korea Times.

March 3/11: #2 flies. Russia’s 2nd PAK-FA fighter prototype successfully completes its 1st test flight in Russia’s Far East region of Komsomolsk-on-Amur. Note that China’s Xinhua cites local reports dated Feb 23/11, but Sukhoi’s release pegs the date at March 3/11.

UAC’s Mikhail Pogosyan adds that they expect to have a fleet of 3 test aircraft by year end, and says the existing jets have now made 40 flights since last January to test the model’s aero-dynamic characteristics and electronics. Beyond that, Pogosyan tells Russian media that the Indian Air Force will “acquire 50 single-seater fighters of the Russian version” before their 2-seat FGFA is developed. If true, it would go a long way toward ensuring that India meets its 2017 induction target. On the Russian end, plans are to purchase the first batch with existing engines, buying the first 10 aircraft after 2012 and then 60 after 2016. Russia’s Centre for Analysis of Strategies and Technologies director Ruslan Pukhov predicts that Vietnam will be the 2nd export customer for the fighter. Sukhoi | Russia’s Pravda | China’s Xinhua.

Feb 9/11: With Aero India 2011 underway, Sukhoi offers some additional details regarding the December 2010 agreement with India:

“This is the first of a series of documents governing the obligations of the parties at different stages of the program. The PMF project includes the design and development of a next-generation fighter, which will have such advanced features as stealth, supersonic cruise speed, high maneuverability, highly integrated set of avionics, an advanced warning system about the situation, the internal deployment of weapons and the possibility of a centralized reporting and electronic warfare system. The fighter is being developed on the basis of the Russian perspective aviation complex (PAK FA) according to stringent technical requirements of the Indian side. The further development of the program envisages design and development of a two-place version of the aircraft and integration of an advanced engine with increased thrust. The two sides are supposed to cooperate in joint marketing of the complex in other countries.”

Feb 9/11: India. Indian defence minister AK Antony reiterates their target of a 2017 induction for the FGFA. India’s defense procurement history suggests that they’re unlikely to make it. Time will tell. Sukhoi.

2010

1st flight; Russian air force plans; Contract with India.

Sukhoi PAK-FA: 1st flight
(click to view larger)

Dec 20/10: Contract. Russian President Dmitry Medvedev reportedly signs a set of defense and nuclear agreements in India, including the FGFA development contract. Details remain sketchy. Bloomberg | BBC.

Dec 16/10: Hindustan Aeronautics Limited (HAL) Chairman Ashok Nayak tells Russia’s RIA Novosti that Russia and India have agreed on key features of the design contract for their joint fifth-generation fighter project. The cost of preliminary design is estimated at $295 million, with work expected to be complete within 18 months. The partnership will develop both a single-seat and a twin-seat version of the aircraft by 2016, focusing on the single-seat version in the initial stages of development.

Nayak said the contract could be signed by the representatives of India’s HAL and Russia’s United Aircraft Corporation (UAC) during a visit by Russian President Dmitry Medvedev to India on December 20-22. RIA Novosti.

Development contract

Nov 30/10: The right-wing American Heritage Foundation think tank releases an analysis of the Russia program and its implications: “What Russia’s Stealth Fighter Developments Mean for America“.

July 23/10: Testing. Sukhoi’s KnAAPO issues a release saying that:

“Sukhoi Company has completed the preliminary on-land and in-flight activities which involved all 3 engineering prototypes of the Frontline Aviation Advanced Airborne Complex (PAK FA)… These prototypes were used for testbed strength tests, on-land optimization of fuel systems and other work towards flight trials. The flying prototype has made 16 flights… enables execution of a complete program of flight trials… Vladimir Popovkin, the Russian Defense Minister First Deputy, in his interview to the Rossiyskaya Gazeta newspaper estimated the Russian Air Force’s demand for the 5th-generation fighters at 50 to 100 units. It is planned to complete all tests of the PAK FA airframe in 2011-2012, and to sign a contract in 2013 for a pilot lot of ten aircraft for testing the model’s entire weapons suite.”

July 13/10: Russia. RIA Novosti quotes senior Russian figures. Russian Air Force chief Col. Gen. Alexander Zelin confirms the expected delivery dates of over 60 planes, which they hope to begin in 2015-16, but equipped with older, “non-fifth” generation engines from existing SU-30 family planes.

“Deputy Defense Minister for Arms Procurement Vladimir Popovkin said the Defense Ministry would purchase the first 6 to 10 aircraft after 2012, based on the outcome of initial tests… The prime minister said 30 billion rubles (around $1 billion) had already been spent on the project and another 30 billion would be required to complete it, after which the engine, weaponry and other components would be upgraded.”

April 2010: Testing. The 1st flying prototype of the fighter, and the avionics testbed used for systems optimization before flight trials, are delivered to the flying test center of the OKB Sukhoi Experimental Design Bureau in Zhukovsky, near Moscow. On April 29/10, the flying prototype begins preliminary tests. Source.

March 29/10: Welcome to the new world of intelligence, where a pair of YouTube videos appear to provide insights into PAK-FA technologies. Veteran aviation journalist Bill Sweetman reports that:

“…the video highlights a new honeycomb core material designed for high temperatures. It also states that the T-50 will have no fewer than five radar arrays: the 1500-module forward active electronically scanned array (AESA), two side-facing X-band sub-arrays and two “decimetric” (L-band) arrays in the leading-edge root extensions. It also states that the goal is to fight the F-22 by closing within visual range. Another new video shows a novel inlet radar blocker… It uses flexible vanes with a rotating ring at the rear end: in the “stealth regime” it provides extensive blockage, but it clears the airflow when it doesn’t matter or you need full speed or power.”

Late March 2010: Testing. Acceptance trials of the flying prototype are fully completed. Source.

March 16/10: Russia. In “The future of the Russian Air Force: 10 years on“, RIA Novosti military commentator Ilya Kramnik discusses planned buys and pending recapitalization of the Russian Air Force over the next decade:

“According to various media reports, the Ministry wants to buy at least 1,500 aircraft, including 350 new warplanes, by 2020. The fleet would include 70% new equipment at that point, said Air Force Commander-in-Chief Colonel General Alexander Zelin… The Defense Ministry has now signed contracts for the purchase of 32 Su-34 Fullback advanced fighter-bombers to be delivered by 2013, 48 Su-35 Flanker-E fighters by 2015, 12 Su-27SM Flanker-B Mod. 1 fighters by 2011, 4 Su-30M2 Flanker-C planes by 2011 and 12 Su-25UBM Frogfoot combat trainers. This year, the Defense Ministry in